16911 W SEPTO ST 91343
Certificate Information: 16911 W SEPTO ST 91343
- Application / Permit
- 23010-20000-02317
- Plan Check / Job No.
- B23VN07256
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN NEW 1 STORY DETACHED ADU (728 SF) PER ENGINEER. PER GCS 65852.2(e)(1)(B)
- Permit Issued
- Issued on 3/13/2024
- Issuing Office
- Current Status
- CofO Issued on 2/20/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/4/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/8/2023 | KHUONG TRUONG |
| Corrections Issued | 6/9/2023 | KHUONG TRUONG |
| Applicant returned to address corrections | 7/10/2023 | KHUONG TRUONG |
| Applicant returned to address corrections | 9/5/2023 | KHUONG TRUONG |
| Plan Check Approved | 9/27/2023 | KHUONG TRUONG |
| Issued | 3/13/2024 | APPLICANT |
| CofO in Progress | 2/6/2025 | JAVIER RAMOS JR |
| Permit Finaled | 2/20/2025 | RUBEN SALAS |
| CofO Issued | 2/20/2025 | RUBEN SALAS |
| Permit Finaled | 2/20/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 6/30/2023 | ROMAN GUTIERREZ |
| Eng Process Fee Ord 176,300 | Cleared | 7/6/2023 | ROMAN GUTIERREZ |
| Sewer availability | Cleared | 7/6/2023 | ROMAN GUTIERREZ |
| Grading Pre-Inspection | Cleared | 7/14/2023 | ALEXANDER HELFER |
| ZA Case | Cleared | 7/20/2023 | NELSON RODRIGUEZ |
| GPI Written Notices | Cleared | 8/28/2023 | KHUONG TRUONG |
| Low Impact Development (LID) | Cleared | 8/30/2023 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 9/6/2023 | ROMAN GUTIERREZ |
| Construction near power lines | Cleared | 9/23/2023 | RIDWAN HARDY |
| Hold | Cleared | 4/2/2024 | MARIA VENDIVIL |
Contact Information
| Contractor | Gapzac Construction Inc; Lic. No.: 1091976-B | , |
| Engineer | Shahbaz,, Shant Pierre; Lic. No.: C93079 | 15445 VENTURA BLVD #63 SHERMAN OAKS, CA 91403 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/21/2024 | Conditional Approval | JOHN COLEMAN |
| Excavation/Setback/Form/Re-Bar | 3/26/2024 | Approved | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 3/26/2024 | Approved | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 4/4/2024 | Approved | JAVIER RAMOS JR |
| Rough-Elec/Plmb/HVAC | 4/11/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Rough-Elec/Plmb/HVAC | 4/19/2024 | Approved | ROBERT GOLD |
| BUILDING-Rough-Frame | 4/23/2024 | Conditional Approval | JOHN COLEMAN |
| Green Building Rough | 4/23/2024 | Not Ready for Inspection | JOHN COLEMAN |
| Verify Sprinkler Sign Off | 4/23/2024 | Approved | JOHN COLEMAN |
| Wood Frame | 4/23/2024 | Partial Approval | JOHN COLEMAN |
| Interior/Exterior Lathing | 6/10/2024 | Partial Approval | JAVIER RAMOS JR |
| Shower Pan | 6/10/2024 | Approved | JAVIER RAMOS JR |
| Wood Frame | 6/10/2024 | Approved | JAVIER RAMOS JR |
| Insulation | 6/13/2024 | Not Ready for Inspection | JAVIER RAMOS JR |
| Insulation | 7/22/2024 | Corrections Issued | LOUIS ESCOTO |
| Drywall Nailing | 7/29/2024 | Corrections Issued | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 8/12/2024 | Approved | LOUIS ESCOTO |
| ELECTRICAL-Rough | 9/18/2024 | Not Ready for Inspection | JACK KARGODORIAN |
| PLUMBING-Rough | 9/18/2024 | Not Ready for Inspection | JACK KARGODORIAN |
| Underground Mechanical | 9/18/2024 | Corrections Issued | JACK KARGODORIAN |
| Sewer | 9/26/2024 | Approved | JAVIER RAMOS JR |
| Underground Mechanical | 9/26/2024 | Partial Approval | JAVIER RAMOS JR |
| Underground Mechanical | 10/1/2024 | Partial Approval | JAVIER RAMOS JR |
| ELECTRICAL-Final | 10/11/2024 | Corrections Issued | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 10/22/2024 | Not Ready for Inspection | JACK KARGODORIAN |
| ELECTRICAL-Final | 10/22/2024 | Not Ready for Inspection | JACK KARGODORIAN |
| Final | 10/22/2024 | Corrections Issued | JACK KARGODORIAN |
| Green Building Final | 10/22/2024 | Not Ready for Inspection | JACK KARGODORIAN |
| Green Building Rough | 10/22/2024 | Not Ready for Inspection | JACK KARGODORIAN |
| HVAC-Final | 10/22/2024 | Not Ready for Inspection | JACK KARGODORIAN |
| PLUMBING-Final | 10/22/2024 | Not Ready for Inspection | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 10/22/2024 | SGSOV Not Ready | JACK KARGODORIAN |
| Service/Power Release | 10/22/2024 | Not Ready for Inspection | JACK KARGODORIAN |
| Smoke Detectors | 10/22/2024 | Not Ready for Inspection | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 10/28/2024 | SGSOV Not Ready | KEVIN BERBERYAN |
| ELECTRICAL-Final | 10/30/2024 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 11/1/2024 | Corrections Issued | JAVIER RAMOS JR |
| Final | 11/1/2024 | Not Ready for Inspection | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 11/19/2024 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 11/19/2024 | Partial Inspection | JAVIER RAMOS JR |
| Final | 11/19/2024 | Partial Inspection | JAVIER RAMOS JR |
| Green Building Final | 11/19/2024 | Not Ready for Inspection | JAVIER RAMOS JR |
| Green Building Rough | 11/19/2024 | Approved | JAVIER RAMOS JR |
| HVAC-Final | 11/19/2024 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 11/19/2024 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 11/19/2024 | SGSOV Not Required | JAVIER RAMOS JR |
| Service/Power Release | 11/19/2024 | Not Ready for Inspection | JAVIER RAMOS JR |
| Smoke Detectors | 11/19/2024 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 11/25/2024 | Approved | JAVIER RAMOS JR |
| Final | 11/25/2024 | Not Ready for Inspection | JAVIER RAMOS JR |
| Green Building Final | 11/25/2024 | Approved | JAVIER RAMOS JR |
| Final | 1/28/2025 | Not Ready for Inspection | JAVIER RAMOS JR |
| Final | 2/6/2025 | OK to Issue CofO | JAVIER RAMOS JR |