2829-2831 S ORCHARD AVE 90007
Certificate Information: 2829-2831 S ORCHARD AVE 90007
- Application / Permit
- 23010-20000-02302
- Plan Check / Job No.
- B23VN07200
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Apartment
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN NEW 17'-7" X 63'-3" (2) DETACHED ACCESSORY DWELLING UNITS PER GCS 65852.2(e)(1)(D) AND LAMC 12.22 A.33(c)(d) AND (g) WITH ATTACHED LAUNDRY ROOM. NFPA 13R SPRINKLERS THROUGHOUT. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 2/26/2024
- Issuing Office
- Current Status
- CofO Issued on 8/7/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/6/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/8/2023 | RAPHAEL ROSAS |
| Corrections Issued | 6/13/2023 | RAPHAEL ROSAS |
| Quality Review Completed | 6/16/2023 | STEVEN KIM |
| Applicant returned to address corrections | 7/27/2023 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 10/31/2023 | RAPHAEL ROSAS |
| Plan Check Approved | 11/8/2023 | RAPHAEL ROSAS |
| Issued | 2/26/2024 | APPLICANT |
| CofO in Progress | 8/7/2025 | JAMES POWERS |
| Permit Finaled | 8/7/2025 | ERNESTO CORRAL |
| CofO Issued | 8/7/2025 | ERNESTO CORRAL |
| Permit Finaled | 8/7/2025 | ERNESTO CORRAL |
Permit Application Clearance Information
| Address approval | Cleared | 6/16/2023 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 6/26/2023 | CELINA MORENO |
| Sewer availability | Cleared | 6/26/2023 | CELINA MORENO |
| Miscellaneous | Cleared | 6/28/2023 | MAYELA VILLA |
| Tenant Habitability Plan | Cleared | 8/31/2023 | HUGO GARRIDO GARZA |
| Hydrant and Access approval | Cleared | 9/6/2023 | MATTHEW CRAIG |
| Specific Plan | Cleared | 9/15/2023 | DANIEL MATA |
| ZI | Cleared | 9/15/2023 | DANIEL MATA |
| ZI | Cleared | 9/18/2023 | JASON CHAN |
| Low Impact Development (LID) | Cleared | 10/4/2023 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 10/19/2023 | STEVEN JIN |
| Miscellaneous | Cleared | 11/3/2023 | RUBEN VASQUEZ |
Contact Information
| Contractor | Orantes Builders Inc; Lic. No.: 1011856-B | , |
| Engineer | Yiu,, Siu; Lic. No.: S5801 | PO BOX 5143 EL MONTE, CA 91734 |
Inspector Information
| ALFREDO LOPEZ, (213) 482-0361 | Office Hours: 7:00-8:00 AM MON-FRI |
| JAMES POWERS, (213) 482-0361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| METHANE-Barrier | 4/10/2024 | Approved | JAMES POWERS |
| Footing/Foundation/Slab | 4/12/2024 | Partial Approval | JAMES POWERS |
| METHANE-Subgrade | 4/12/2024 | Approved | JAMES POWERS |
| Deputy Reinf. Concrete | 4/16/2024 | Conditional Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 5/3/2024 | Not Ready for Inspection | JAMES POWERS |
| Deputy Wood Construction | 7/31/2024 | Partial Approval | JAMES POWERS |
| Floor/Roof Diaphrgm/Shear Wall | 8/9/2024 | Partial Approval | JAMES POWERS |
| Green Building Rough | 8/9/2024 | Approved | JAMES POWERS |
| METHANE-Rough | 8/9/2024 | Not Ready for Inspection | JAMES POWERS |
| Verify Sprinkler Sign Off | 8/9/2024 | Not Ready for Inspection | JAMES POWERS |
| Wood Frame | 8/9/2024 | Partial Approval | JAMES POWERS |
| Insulation | 8/23/2024 | Approved | JAMES POWERS |
| Interior/Exterior Lathing | 8/23/2024 | Approved | JAMES POWERS |
| Drywall Nailing | 9/4/2024 | Approved | JAMES POWERS |
| Interior/Exterior Lathing | 9/4/2024 | Approved | JAMES POWERS |
| Final | 7/28/2025 | Not Ready for Inspection | JAMES POWERS |
| Footing/Foundation/Slab | 7/28/2025 | Approved | JAMES POWERS |
| Green Building Final | 7/28/2025 | Approved | JAMES POWERS |
| METHANE-Final | 7/28/2025 | Not Ready for Inspection | JAMES POWERS |
| METHANE-Rough | 7/28/2025 | Not Ready for Inspection | JAMES POWERS |
| SGSOV-Seismic Gas S/O Valve | 7/28/2025 | SGSOV Approved | JAMES POWERS |
| Smoke Detectors | 7/28/2025 | Approved | JAMES POWERS |
| Verify Sprinkler Sign Off | 7/28/2025 | Approved | JAMES POWERS |
| Wood Frame | 7/28/2025 | Partial Approval | JAMES POWERS |
| Final | 7/30/2025 | Not Ready for Inspection | JAMES POWERS |
| METHANE-Final | 7/30/2025 | Approved | JAMES POWERS |
| METHANE-Rough | 7/30/2025 | Approved | JAMES POWERS |
| Wood Frame | 7/30/2025 | Approved | JAMES POWERS |
| Final | 7/31/2025 | Not Ready for Inspection | JAMES POWERS |
| Final | 8/7/2025 | OK to Issue CofO | JAMES POWERS |