13282 N BORDEN AVE 91342
Certificate Information: 13282 N BORDEN AVE 91342
- Application / Permit
- 23010-20000-02294
- Plan Check / Job No.
- B23VN07177
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ****EPLAN**** Addition and Conversion of (E) garage to SFD UNIT PER SB9
- Permit Issued
- Issued on 2/21/2024
- Issuing Office
- Current Status
- CofO in Progress on 4/23/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/12/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/29/2023 | YASHAR EMAMI |
| Corrections Issued | 7/5/2023 | YASHAR EMAMI |
| Quality Review Completed | 7/18/2023 | KAVIAN REFAHI |
| Applicant returned to address corrections | 9/18/2023 | YASHAR EMAMI |
| Applicant returned to address corrections | 9/28/2023 | YASHAR EMAMI |
| Applicant returned to address corrections | 12/15/2023 | YASHAR EMAMI |
| Plan Check Approved | 2/7/2024 | YASHAR EMAMI |
| Issued | 2/21/2024 | APPLICANT |
| CofO in Progress | 4/23/2026 | KEVIN BERBERYAN |
Permit Application Clearance Information
| Address approval | Cleared | 10/2/2023 | GABRIELLA TORRES |
| Senate Bill 9 | Cleared | 10/11/2023 | BRENNEN OBETO |
| Eng Process Fee Ord 176,300 | Cleared | 10/16/2023 | GABRIELLA TORRES |
| Sewer availability | Cleared | 10/16/2023 | GABRIELLA TORRES |
| Low Impact Development (LID) | Cleared | 11/9/2023 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 11/13/2023 | GABRIELLA TORRES |
| Hydrant and Access approval | Cleared | 11/29/2023 | LAVEON RIDER |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yeghiayan,, Armond; Lic. No.: C69935 | 16873 MCKEEVER ST GRANADA HILLS, CA 91344 |
| Engineer | Yeghiayan,, Armond; Lic. No.: NA69935 | , |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/16/2024 | Conditional Approval | KEVIN BERBERYAN |
| Footing/Foundation/Slab | 7/18/2024 | Approved | KEVIN BERBERYAN |
| PLUMBING-Rough | 7/18/2024 | Corrections Issued | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 8/8/2024 | Conditional Approval | KEVIN BERBERYAN |
| Green Building Rough | 8/8/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/22/2024 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 8/22/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Underground Mechanical | 8/22/2024 | Partial Approval | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 12/13/2024 | Approved | KEVIN BERBERYAN |
| Green Building Rough | 12/13/2024 | Approved | KEVIN BERBERYAN |
| HVAC-Rough | 12/13/2024 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 12/13/2024 | Approved | KEVIN BERBERYAN |
| PLUMBING-Rough | 12/13/2024 | Approved | KEVIN BERBERYAN |
| Insulation | 12/17/2024 | Corrections Issued | KEVIN BERBERYAN |
| Insulation | 12/19/2024 | Approved | ROBERT GOLD |
| Drywall Nailing | 12/20/2024 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 12/24/2024 | Partial Inspection | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 1/6/2025 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 12/16/2025 | Approved | KEVIN BERBERYAN |
| Final | 12/16/2025 | Corrections Issued | KEVIN BERBERYAN |
| Green Building Final | 12/16/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 12/16/2025 | SGSOV Approved | KEVIN BERBERYAN |
| Smoke Detectors | 12/16/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| Final | 1/7/2026 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 1/7/2026 | Not Ready for Inspection | MICHEL ABAJAN |
| Smoke Detectors | 1/7/2026 | Approved | MICHEL ABAJAN |
| Final | 4/2/2026 | Corrections Issued | KEVIN BERBERYAN |
| Green Building Final | 4/2/2026 | Approved | KEVIN BERBERYAN |
| Final | 4/23/2026 | OK to Issue CofO | KEVIN BERBERYAN |