1031 N FISKE ST 90272
Certificate Information: 1031 N FISKE ST 90272
- Application / Permit
- 23010-20000-02273
- Plan Check / Job No.
- B23VN07079
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 77'0"X30'0" IRREGULAR SHAPED 2-STORY SINGLE FAMILY DWELLING WITH ATTACHED 2-CAR GARAGE. ALL ELECTRIC BUILDING NFPA 13 D FIRE SPRINKLERS REQUIRED THROUGHOUT
- Permit Issued
- Issued on 1/18/2024
- Issuing Office
- Current Status
- CofO Issued on 4/23/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/31/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/1/2023 | MARVEL DELACRUZ |
| Corrections Issued | 6/4/2023 | MARVEL DELACRUZ |
| Quality Review Completed | 6/9/2023 | OMID HEDAYAT |
| Plan Check Approved | 11/6/2023 | MARVEL DELACRUZ |
| Issued | 1/18/2024 | APPLICANT |
| CofO in Progress | 4/23/2026 | DANIEL VERA |
| Permit Finaled | 4/23/2026 | RICHARD STEINBACH |
| CofO Issued | 4/23/2026 | RICHARD STEINBACH |
| Permit Finaled | 4/23/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 6/14/2023 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 6/14/2023 | DARIN LAM |
| Sewer availability | Cleared | 6/14/2023 | DARIN LAM |
| Hydrant and Access approval | Cleared | 8/4/2023 | GILBERT URREA |
| Low Impact Development (LID) | Cleared | 10/17/2023 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 10/17/2023 | DARIN LAM |
Contact Information
| Contractor | J J P Construction Inc; Lic. No.: 960864-B | 12555 VANOWEN STREET 2ND FLOOR OFC NORTH HOLLYWOOD, CA 91605 |
| Engineer | Wang,, Hongyu; Lic. No.: C72679 | 8887 W FALMINGO RD STE 101 LAS VEGAS, NV 89147 |
Inspector Information
| TEMISTOCLES CAAL, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
| JESUS PINEDA, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/10/2024 | Partial Approval | ARAM AVEDISIAN |
| PLUMBING-Rough | 4/10/2024 | Partial Approval | ARAM AVEDISIAN |
| Excavation/Setback/Form/Re-Bar | 4/11/2024 | Not Ready for Inspection | HERBERT GIRON |
| Underground Mechanical | 4/11/2024 | Not Ready for Inspection | HERBERT GIRON |
| Footing/Foundation/Slab | 4/16/2024 | Approved | KENNETH NAGLE |
| Floor/Roof Diaphrgm/Shear Wall | 5/7/2024 | Partial Approval | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/14/2024 | Not Ready for Inspection | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/30/2024 | Partial Approval | ARAM AVEDISIAN |
| HVAC-Rough | 6/10/2024 | Approved | ARAM AVEDISIAN |
| PLUMBING-Rough | 6/12/2024 | Approved | ARAM AVEDISIAN |
| Shower Pan | 6/17/2024 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 6/20/2024 | Partial Approval | EVAN COOPER |
| ELECTRICAL-Rough | 6/28/2024 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 7/2/2024 | Approved | KENNETH NAGLE |
| Green Building Rough | 7/2/2024 | Approved | KENNETH NAGLE |
| Interior/Exterior Lathing | 7/2/2024 | Partial Approval | KENNETH NAGLE |
| Verify Sprinkler Sign Off | 7/2/2024 | Approved | KENNETH NAGLE |
| Insulation | 7/5/2024 | Approved | EVAN COOPER |
| Drywall Nailing | 7/10/2024 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 7/10/2024 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 7/23/2024 | Partial Approval | ARAM AVEDISIAN |
| Sewer | 7/24/2024 | Approved | ARAM AVEDISIAN |
| Underground Mechanical | 7/24/2024 | Partial Approval | ARAM AVEDISIAN |
| Special/Order Compliance | 8/22/2024 | Not Ready for Inspection | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 12/20/2024 | Not Ready for Inspection | JESUS RODRIGUEZ |
| HVAC-Final | 12/20/2024 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Final | 12/20/2024 | Not Ready for Inspection | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 12/31/2024 | Not Ready for Inspection | JESUS RODRIGUEZ |
| PLUMBING-Final | 12/31/2024 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 1/2/2025 | Not Ready for Inspection | ARAM AVEDISIAN |
| PLUMBING-Final | 1/2/2025 | Not Ready for Inspection | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 1/7/2025 | SGSOV Not Ready | JESUS RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 7/3/2025 | Corrections Issued | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 7/3/2025 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 7/3/2025 | Partial Approval | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 7/8/2025 | Conditional Approval | BOBBY KEY |
| Sewer | 7/11/2025 | Corrections Issued | MEL KHACHATOURIAN |
| Footing/Foundation/Slab | 7/14/2025 | Conditional Approval | BOBBY KEY |
| Sewer | 7/14/2025 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 8/5/2025 | Corrections Issued | STEPHANIE SWANSON |
| HVAC-Rough | 9/12/2025 | Corrections Issued | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 9/15/2025 | Approved | TEMISTOCLES CAAL |
| HVAC-Rough | 9/15/2025 | Approved | TEMISTOCLES CAAL |
| PLUMBING-Rough | 9/22/2025 | Not Ready for Inspection | TEMISTOCLES CAAL |
| PLUMBING-Rough | 9/23/2025 | Not Ready for Inspection | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 9/25/2025 | Partial Approval | JAYLIN GRAVITTE |
| PLUMBING-Rough | 10/3/2025 | Not Ready for Inspection | TEMISTOCLES CAAL |
| PLUMBING-Rough | 10/6/2025 | Partial Approval | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 10/7/2025 | Approved | TEMISTOCLES CAAL |
| Green Building Rough | 10/7/2025 | Approved | TEMISTOCLES CAAL |
| Verify Sprinkler Sign Off | 10/7/2025 | Approved | TEMISTOCLES CAAL |
| PLUMBING-Rough | 10/9/2025 | Approved | TEMISTOCLES CAAL |
| Underground Mechanical | 10/15/2025 | Partial Approval | MEL KHACHATOURIAN |
| Shower Pan | 10/24/2025 | Approved | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 11/19/2025 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 4/22/2026 | Approved | DANIEL VERA |
| Final | 4/22/2026 | OK to Issue CofO | DANIEL VERA |
| Footing/Foundation/Slab | 4/22/2026 | Approved | DANIEL VERA |
| Green Building Final | 4/22/2026 | Approved | DANIEL VERA |
| SGSOV-Seismic Gas S/O Valve | 4/22/2026 | SGSOV Not Required | DANIEL VERA |
| Service/Power Release | 4/22/2026 | Approved | DANIEL VERA |
| Smoke Detectors | 4/22/2026 | Approved | DANIEL VERA |