1031 N FISKE ST 90272

Certificate Information: 1031 N FISKE ST 90272

Application / Permit
23010-20000-02273
Plan Check / Job No.
B23VN07079
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 77'0"X30'0" IRREGULAR SHAPED 2-STORY SINGLE FAMILY DWELLING WITH ATTACHED 2-CAR GARAGE. ALL ELECTRIC BUILDING NFPA 13 D FIRE SPRINKLERS REQUIRED THROUGHOUT
Permit Issued
Issued on 1/18/2024
Issuing Office
Current Status
CofO Issued on 4/23/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/31/2023 APPLICANT
Assigned to Plan Check Engineer 6/1/2023 MARVEL DELACRUZ
Corrections Issued 6/4/2023 MARVEL DELACRUZ
Quality Review Completed 6/9/2023 OMID HEDAYAT
Plan Check Approved 11/6/2023 MARVEL DELACRUZ
Issued 1/18/2024 APPLICANT
CofO in Progress 4/23/2026 DANIEL VERA
Permit Finaled 4/23/2026 RICHARD STEINBACH
CofO Issued 4/23/2026 RICHARD STEINBACH
Permit Finaled 4/23/2026 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 6/14/2023 DARIN LAM
Eng Process Fee Ord 176,300 Cleared 6/14/2023 DARIN LAM
Sewer availability Cleared 6/14/2023 DARIN LAM
Hydrant and Access approval Cleared 8/4/2023 GILBERT URREA
Low Impact Development (LID) Cleared 10/17/2023 MELINEH AGHAKHABIAN
Roof/Waste drainage to street Cleared 10/17/2023 DARIN LAM

Contact Information

Contractor J J P Construction Inc; Lic. No.: 960864-B 12555 VANOWEN STREET   2ND FLOOR OFC    NORTH HOLLYWOOD, CA 91605
Engineer Wang,, Hongyu; Lic. No.: C72679 8887 W FALMINGO RD STE 101      LAS VEGAS, NV 89147

Inspector Information

TEMISTOCLES CAAL, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI
JESUS PINEDA, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/10/2024 Partial Approval ARAM AVEDISIAN
PLUMBING-Rough 4/10/2024 Partial Approval ARAM AVEDISIAN
Excavation/Setback/Form/Re-Bar 4/11/2024 Not Ready for Inspection HERBERT GIRON
Underground Mechanical 4/11/2024 Not Ready for Inspection HERBERT GIRON
Footing/Foundation/Slab 4/16/2024 Approved KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 5/7/2024 Partial Approval ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 5/14/2024 Not Ready for Inspection ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 5/30/2024 Partial Approval ARAM AVEDISIAN
HVAC-Rough 6/10/2024 Approved ARAM AVEDISIAN
PLUMBING-Rough 6/12/2024 Approved ARAM AVEDISIAN
Shower Pan 6/17/2024 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 6/20/2024 Partial Approval EVAN COOPER
ELECTRICAL-Rough 6/28/2024 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 7/2/2024 Approved KENNETH NAGLE
Green Building Rough 7/2/2024 Approved KENNETH NAGLE
Interior/Exterior Lathing 7/2/2024 Partial Approval KENNETH NAGLE
Verify Sprinkler Sign Off 7/2/2024 Approved KENNETH NAGLE
Insulation 7/5/2024 Approved EVAN COOPER
Drywall Nailing 7/10/2024 Approved EVAN COOPER
Interior/Exterior Lathing 7/10/2024 Approved EVAN COOPER
Interior/Exterior Lathing 7/23/2024 Partial Approval ARAM AVEDISIAN
Sewer 7/24/2024 Approved ARAM AVEDISIAN
Underground Mechanical 7/24/2024 Partial Approval ARAM AVEDISIAN
Special/Order Compliance 8/22/2024 Not Ready for Inspection JESUS RODRIGUEZ
ELECTRICAL-Final 12/20/2024 Not Ready for Inspection JESUS RODRIGUEZ
HVAC-Final 12/20/2024 Approved JESUS RODRIGUEZ
PLUMBING-Final 12/20/2024 Not Ready for Inspection JESUS RODRIGUEZ
ELECTRICAL-Final 12/31/2024 Not Ready for Inspection JESUS RODRIGUEZ
PLUMBING-Final 12/31/2024 Approved JESUS RODRIGUEZ
ELECTRICAL-Final 1/2/2025 Not Ready for Inspection ARAM AVEDISIAN
PLUMBING-Final 1/2/2025 Not Ready for Inspection ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 1/7/2025 SGSOV Not Ready JESUS RODRIGUEZ
Excavation/Setback/Form/Re-Bar 7/3/2025 Corrections Issued STEPHANIE SWANSON
Footing/Foundation/Slab 7/3/2025 Corrections Issued STEPHANIE SWANSON
PLUMBING-Rough 7/3/2025 Partial Approval STEPHANIE SWANSON
Footing/Foundation/Slab 7/8/2025 Conditional Approval BOBBY KEY
Sewer 7/11/2025 Corrections Issued MEL KHACHATOURIAN
Footing/Foundation/Slab 7/14/2025 Conditional Approval BOBBY KEY
Sewer 7/14/2025 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 8/5/2025 Corrections Issued STEPHANIE SWANSON
HVAC-Rough 9/12/2025 Corrections Issued TEMISTOCLES CAAL
ELECTRICAL-Rough 9/15/2025 Approved TEMISTOCLES CAAL
HVAC-Rough 9/15/2025 Approved TEMISTOCLES CAAL
PLUMBING-Rough 9/22/2025 Not Ready for Inspection TEMISTOCLES CAAL
PLUMBING-Rough 9/23/2025 Not Ready for Inspection TEMISTOCLES CAAL
Interior/Exterior Lathing 9/25/2025 Partial Approval JAYLIN GRAVITTE
PLUMBING-Rough 10/3/2025 Not Ready for Inspection TEMISTOCLES CAAL
PLUMBING-Rough 10/6/2025 Partial Approval MEL KHACHATOURIAN
BUILDING-Rough-Frame 10/7/2025 Approved TEMISTOCLES CAAL
Green Building Rough 10/7/2025 Approved TEMISTOCLES CAAL
Verify Sprinkler Sign Off 10/7/2025 Approved TEMISTOCLES CAAL
PLUMBING-Rough 10/9/2025 Approved TEMISTOCLES CAAL
Underground Mechanical 10/15/2025 Partial Approval MEL KHACHATOURIAN
Shower Pan 10/24/2025 Approved STEPHANIE SWANSON
Interior/Exterior Lathing 11/19/2025 Approved TEMISTOCLES CAAL
ELECTRICAL-Final 4/22/2026 Approved DANIEL VERA
Final 4/22/2026 OK to Issue CofO DANIEL VERA
Footing/Foundation/Slab 4/22/2026 Approved DANIEL VERA
Green Building Final 4/22/2026 Approved DANIEL VERA
SGSOV-Seismic Gas S/O Valve 4/22/2026 SGSOV Not Required DANIEL VERA
Service/Power Release 4/22/2026 Approved DANIEL VERA
Smoke Detectors 4/22/2026 Approved DANIEL VERA