5763 N OSTIN AVE 91367

Certificate Information: 5763 N OSTIN AVE 91367

Application / Permit
23010-20000-02272
Plan Check / Job No.
B23VN07069
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
*EPLAN* 27'-6" X 21'-6" TWO STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 5/1/2024
Issuing Office
Current Status
CofO Issued on 8/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/31/2023 APPLICANT
Assigned to Plan Check Engineer 6/1/2023 SELLA BENYAMIN
Corrections Issued 6/6/2023 SELLA BENYAMIN
Quality Review Completed 6/14/2023 STEVEN KIM
Applicant returned to address corrections 9/8/2023 SELLA BENYAMIN
Applicant returned to address corrections 1/19/2024 SELLA BENYAMIN
Plan Check Approved 4/9/2024 SELLA BENYAMIN
Issued 5/1/2024 APPLICANT
CofO in Progress 7/10/2025 TROY SANDERS
CofO in Progress 7/21/2025 ROBERT GOLD
Permit Finaled 8/18/2025 JOHN JANSON
Permit Finaled 8/18/2025 JOHN JANSON
CofO Issued 8/18/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 6/16/2023 NIKKI ZULUETA
Eng Process Fee Ord 176,300 Cleared 6/20/2023 NIKKI ZULUETA
Sewer availability Cleared 6/20/2023 NIKKI ZULUETA
GPI Written Notices Cleared 9/8/2023 SELLA BENYAMIN
Grading Pre-Inspection Cleared 9/8/2023 SELLA BENYAMIN
Construction near power lines Cleared 9/26/2023 RIDWAN HARDY
Low Impact Development (LID) Cleared 2/6/2024 TOMMY YIN
Roof/Waste drainage to street Cleared 3/1/2024 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Zhuang,, Wenbin; Lic. No.: S5236 205 S CHAPEL AVE #D-1      ALHAMBRA, CA 91801

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/9/2024 Corrections Issued GEVORK IPCHYAN
PLUMBING-Rough 7/5/2024 Partial Approval TROY SANDERS
Footing/Foundation/Slab 7/19/2024 Approved TROY SANDERS
Floor/Roof Diaphrgm/Shear Wall 7/29/2024 Partial Approval TROY SANDERS
Special/Order Compliance 7/29/2024 Corrections Issued TROY SANDERS
Verify Sprinkler Sign Off 7/29/2024 Not Ready for Inspection TROY SANDERS
Underground Mechanical 8/6/2024 Partial Approval TROY SANDERS
Floor/Roof Diaphrgm/Shear Wall 8/28/2024 Approved TROY SANDERS
BUILDING-Rough-Frame 9/13/2024 Partial Approval TROY SANDERS
ELECTRICAL-Rough 9/13/2024 Approved TROY SANDERS
PLUMBING-Rough 9/13/2024 Approved TROY SANDERS
Verify Sprinkler Sign Off 9/13/2024 Approved TROY SANDERS
BUILDING-Rough-Frame 10/2/2024 Approved TROY SANDERS
Green Building Rough 10/2/2024 Approved TROY SANDERS
HVAC-Rough 10/2/2024 Approved TROY SANDERS
Interior/Exterior Lathing 10/2/2024 Partial Approval TROY SANDERS
Insulation 10/11/2024 Approved TROY SANDERS
Drywall Nailing 10/17/2024 Approved TROY SANDERS
Interior/Exterior Lathing 10/30/2024 Partial Approval TROY SANDERS
ELECTRICAL-Final 4/4/2025 Approved TROY SANDERS
Green Building Final 4/4/2025 Approved TROY SANDERS
Service/Power Release 4/4/2025 Approved TROY SANDERS
Final 6/4/2025 Not Ready for Inspection TROY SANDERS
SGSOV-Seismic Gas S/O Valve 6/4/2025 SGSOV Approved TROY SANDERS
Smoke Detectors 6/4/2025 Approved TROY SANDERS
Final 7/9/2025 OK to Issue CofO TROY SANDERS