19105 W STRATHERN ST 91335
Certificate Information: 19105 W STRATHERN ST 91335
- Application / Permit
- 23010-20000-02245
- Plan Check / Job No.
- B23VN06028
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 1-STORY DETACHED TYPE V-A SFD PER SB9 (NFPA-13R FIRE SPRINKLERS THROUGHOUT) **ePlan**
- Permit Issued
- Issued on 9/14/2023
- Issuing Office
- Current Status
- CofO Issued on 12/15/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/9/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/25/2023 | NILOOFAR MEHRAIN |
| Corrections Issued | 5/31/2023 | NILOOFAR MEHRAIN |
| Quality Review Completed | 5/31/2023 | STEVEN KIM |
| Plan Check Approved | 9/13/2023 | NILOOFAR MEHRAIN |
| Issued | 9/14/2023 | APPLICANT |
| CofO in Progress | 12/5/2025 | JUAN ALVARADO |
| Permit Finaled | 12/15/2025 | JOHN JANSON |
| CofO Issued | 12/15/2025 | JOHN JANSON |
| Permit Finaled | 12/15/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 6/7/2023 | NIKKI ZULUETA |
| Eng Process Fee Ord 176,300 | Cleared | 6/9/2023 | NIKKI ZULUETA |
| Sewer availability | Cleared | 6/12/2023 | NIKKI ZULUETA |
| Low Impact Development (LID) | Cleared | 7/13/2023 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 7/17/2023 | NIKKI ZULUETA |
| Hydrant and Access approval | Cleared | 8/3/2023 | MATTHEW CRAIG |
| Senate Bill 9 | Cleared | 8/7/2023 | ALEX VELA |
Contact Information
| Architect | Dembsky,, Amit; Lic. No.: NA30383 | , |
| Contractor | My Design Remodeling Inc; Lic. No.: 982016-B | , |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 7/29/2024 | Approved | JEFFREY BULL |
| Special/Order Compliance | 7/29/2024 | Corrections Issued | JEFFREY BULL |
| Footing/Foundation/Slab | 8/29/2024 | No Access for Inspection | ARUTYUN MADATYAN |
| Footing/Foundation/Slab | 9/3/2024 | Approved | JEFFREY BULL |
| BUILDING-Rough-Frame | 2/26/2025 | Not Ready for Inspection | JUAN ALVARADO |
| ELECTRICAL-Rough | 2/26/2025 | Corrections Issued | JUAN ALVARADO |
| Floor/Roof Diaphrgm/Shear Wall | 2/26/2025 | Approved | JUAN ALVARADO |
| Green Building Rough | 2/26/2025 | Not Ready for Inspection | JUAN ALVARADO |
| HVAC-Rough | 2/26/2025 | Approved | JUAN ALVARADO |
| PLUMBING-Rough | 2/26/2025 | Corrections Issued | JUAN ALVARADO |
| Special/Order Compliance | 2/26/2025 | Partial Inspection | SEAN WIRCH |
| Verify Sprinkler Sign Off | 2/26/2025 | Approved | JUAN ALVARADO |
| Deputy Drilled-In Anchors | 3/18/2025 | Conditional Approval | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 3/20/2025 | Approved | ARUTYUN MADATYAN |
| ELECTRICAL-Rough | 3/20/2025 | Approved | ARUTYUN MADATYAN |
| Green Building Rough | 3/20/2025 | Approved | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 3/20/2025 | Partial Approval | ARUTYUN MADATYAN |
| PLUMBING-Rough | 3/20/2025 | Approved | ARUTYUN MADATYAN |
| Shower Pan | 3/20/2025 | Approved | ARUTYUN MADATYAN |
| Insulation | 4/2/2025 | Conditional Approval | JUAN ALVARADO |
| Drywall Nailing | 4/18/2025 | Approved | JUAN ALVARADO |
| Interior/Exterior Lathing | 4/18/2025 | Approved | JUAN ALVARADO |
| Underground Mechanical | 6/26/2025 | Approved | JUAN ALVARADO |
| ELECTRICAL-Final | 10/16/2025 | Approved | JUAN ALVARADO |
| Final | 10/16/2025 | Corrections Issued | JUAN ALVARADO |
| Green Building Final | 10/16/2025 | Approved | JUAN ALVARADO |
| HVAC-Final | 10/16/2025 | Approved | JUAN ALVARADO |
| PLUMBING-Final | 10/16/2025 | Approved | JUAN ALVARADO |
| SGSOV-Seismic Gas S/O Valve | 10/16/2025 | SGSOV Approved | JUAN ALVARADO |
| Service/Power Release | 10/16/2025 | Not Ready for Inspection | JUAN ALVARADO |
| Smoke Detectors | 10/16/2025 | Approved | JUAN ALVARADO |
| ELECTRICAL-Final | 12/4/2025 | Approved | JUAN ALVARADO |
| Final | 12/4/2025 | OK to Issue CofO | JUAN ALVARADO |
| HVAC-Final | 12/4/2025 | Approved | JUAN ALVARADO |
| PLUMBING-Final | 12/4/2025 | Approved | JUAN ALVARADO |
| Service/Power Release | 12/4/2025 | Approved | JUAN ALVARADO |