9812 N OSO AVE 91311
Certificate Information: 9812 N OSO AVE 91311
- Application / Permit
- 23010-20000-02237
- Plan Check / Job No.
- B23VN06980
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 40'-6" X 30'-0" IRREGULAR SHAPED DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d).
- Permit Issued
- Issued on 9/5/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/6/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/26/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/2/2023 | ARTIN ZARUKIAN |
| Corrections Issued | 6/3/2023 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 6/6/2023 | APPLICANT |
| Applicant returned to address corrections | 8/28/2023 | LUISANGEL VALENZUELA |
| Plan Check Approved | 9/1/2023 | HAYATO TSUCHIYA |
| Issued | 9/5/2023 | APPLICANT |
| CofO in Progress | 4/12/2024 | DAVID SCANTLIN |
| CofO Issued | 5/6/2024 | JOHN JANSON |
| Permit Finaled | 5/6/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 6/10/2023 | DAGOVERTO GUERRERO |
| Permit | Cleared | 6/10/2023 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 6/10/2023 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 6/16/2023 | DAGOVERTO GUERRERO |
| Low Impact Development (LID) | Cleared | 7/27/2023 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 8/8/2023 | JOHN LIN |
| Disturb/Remove Protected Trees | Cleared | 8/17/2023 | ADALBERTO VERA |
| Construction near power lines | Cleared | 8/19/2023 | WALTER RAMIREZ |
| Hydrant and Access approval | Cleared | 8/23/2023 | LAVEON RIDER |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mroczka,, Peter J; Lic. No.: C42648 | 9301 DARBY AVE APT 1 NORTHRIDGE, CA 91325 |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 10/16/2023 | Approved | JOHN KIDWELL |
| Underground Mechanical | 10/16/2023 | Partial Approval | JOHN KIDWELL |
| Footing/Foundation/Slab | 10/24/2023 | Corrections Issued | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 11/14/2023 | Approved | JEFFREY HARTLINE |
| Footing/Foundation/Slab | 11/14/2023 | Approved | JEFFREY HARTLINE |
| HVAC-Rough | 11/29/2023 | Approved | DAVID SCANTLIN |
| PLUMBING-Rough | 11/29/2023 | Approved | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 12/18/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| ELECTRICAL-Rough | 12/18/2023 | Approved | DAVID SCANTLIN |
| Green Building Rough | 12/18/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| Shower Pan | 12/18/2023 | Approved | DAVID SCANTLIN |
| Verify Sprinkler Sign Off | 12/18/2023 | Approved | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 12/21/2023 | Approved | DAVID SCANTLIN |
| Green Building Rough | 12/21/2023 | Approved | DAVID SCANTLIN |
| Interior/Exterior Lathing | 12/21/2023 | Partial Approval | DAVID SCANTLIN |
| Insulation | 12/26/2023 | Corrections Issued | JEFFREY BULL |
| Drywall Nailing | 12/29/2023 | Approved | HENRY KIM |
| Insulation | 12/29/2023 | Approved | HENRY KIM |
| Interior/Exterior Lathing | 1/3/2024 | Approved | KRISTEN CAUSEY |
| Final | 4/1/2024 | Corrections Issued | DAVID SCANTLIN |
| Green Building Final | 4/1/2024 | Approved | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 4/1/2024 | SGSOV Approved | DAVID SCANTLIN |
| Service/Power Release | 4/1/2024 | Approved | DAVID SCANTLIN |
| Smoke Detectors | 4/1/2024 | Approved | DAVID SCANTLIN |
| Final | 4/12/2024 | OK to Issue CofO | DAVID SCANTLIN |