6369 W 78TH ST 90045
Certificate Information: 6369 W 78TH ST 90045
- Application / Permit
- 23010-20000-02230
- Plan Check / Job No.
- B23VN06949
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Recreation Room
- Work Description
- (N) 1-STORY 17'-6" x 25'-3" DETACHED ACCESSORY BUILDING WITH RECREATION ROOM AND STORAGE. WORK DONE PER ENGINEERING.
- Permit Issued
- Issued on 10/3/2023
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 4/16/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/26/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/1/2023 | GIOVANNY CHAVEZ |
| Corrections Issued | 6/1/2023 | GIOVANNY CHAVEZ |
| Building Plans Picked Up | 6/7/2023 | APPLICANT |
| Plan Check Approved | 9/26/2023 | GIOVANNY CHAVEZ |
| Issued | 10/3/2023 | APPLICANT |
| CofO in Progress | 4/16/2024 | TEMISTOCLES CAAL |
| Permit Finaled | 4/16/2024 | DANIEL ORRANTE |
| CofO Issued | 4/16/2024 | DANIEL ORRANTE |
| Permit Finaled | 4/16/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Specific Plan | Cleared | 6/21/2023 | FREDDY GARCIA |
| Construction near power lines | Cleared | 8/31/2023 | RIDWAN HARDY |
| Roof/Waste drainage to street | Cleared | 9/5/2023 | KIMBERLY HERNANDEZ |
| Eng Process Fee Ord 176,300 | Cleared | 9/7/2023 | KIMBERLY HERNANDEZ |
| Grading Pre-Inspection | Cleared | 9/26/2023 | GIOVANNY CHAVEZ |
Contact Information
| Architect | Samson,, Charles Andrew H; Lic. No.: C22979 | 6119 MARY ELLEN AVENUE VAN NUYS, CA 91401 |
| Contractor | Local Construction Remodeling; Lic. No.: 966738-B | 14901 TUBA STREET MISSION HILLS, CA 91345 |
| Engineer | Motavvef,, Nasser; Lic. No.: C40977 | 15335 MORRISON ST 370 SHERMAN OAKS, CA 91403 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/12/2023 | Corrections Issued | HERBERT GIRON |
| Footing/Foundation/Slab | 10/18/2023 | Conditional Approval | RICHARD STEINBACH |
| Floor/Roof Diaphrgm/Shear Wall | 12/1/2023 | Approved | TEMISTOCLES CAAL |
| HVAC-Rough | 12/12/2023 | Corrections Issued | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 12/13/2023 | Approved | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 12/13/2023 | Partial Approval | TEMISTOCLES CAAL |
| Verify Sprinkler Sign Off | 12/13/2023 | Corrections Issued | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 12/15/2023 | Approved | JESUS PINEDA |
| Green Building Rough | 12/15/2023 | Approved | JESUS PINEDA |
| HVAC-Rough | 12/15/2023 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 12/15/2023 | Approved | JESUS PINEDA |
| Verify Sprinkler Sign Off | 12/15/2023 | Approved | JESUS PINEDA |
| Insulation | 12/21/2023 | Approved | TEMISTOCLES CAAL |
| Drywall Nailing | 1/3/2024 | Approved | TEMISTOCLES CAAL |
| Underground Mechanical | 1/8/2024 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 4/5/2024 | Not Ready for Inspection | TEMISTOCLES CAAL |
| HVAC-Final | 4/5/2024 | Not Ready for Inspection | TEMISTOCLES CAAL |
| PLUMBING-Final | 4/5/2024 | Not Ready for Inspection | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 4/9/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Final | 4/9/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 4/9/2024 | Approved | TEMISTOCLES CAAL |
| Green Building Final | 4/9/2024 | Approved | TEMISTOCLES CAAL |
| HVAC-Final | 4/9/2024 | Corrections Issued | TEMISTOCLES CAAL |
| PLUMBING-Final | 4/9/2024 | Approved | TEMISTOCLES CAAL |
| SGSOV-Seismic Gas S/O Valve | 4/9/2024 | SGSOV Not Required | TEMISTOCLES CAAL |
| Service/Power Release | 4/9/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Smoke Detectors | 4/9/2024 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 4/11/2024 | Approved | TEMISTOCLES CAAL |
| Final | 4/11/2024 | OK to Issue CofO | TEMISTOCLES CAAL |
| HVAC-Final | 4/11/2024 | Approved | TEMISTOCLES CAAL |