16533 W OLDHAM ST 91436

Certificate Information: 16533 W OLDHAM ST 91436

Application / Permit
23010-20000-02216
Plan Check / Job No.
B23VN06911
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
(N) 21'-0" x 11'-0" RECREATION ROOM WITH BATHROOM PER ENGINEERING
Permit Issued
Issued on 8/17/2023
Issuing Office
Current Status
Issued on 8/17/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/25/2023 APPLICANT
Assigned to Plan Check Engineer 5/31/2023 GIOVANNY CHAVEZ
Corrections Issued 5/31/2023 GIOVANNY CHAVEZ
Building Plans Picked Up 6/5/2023 APPLICANT
Issued 8/17/2023 APPLICANT

Permit Application Clearance Information

Sewer availability Cleared 6/2/2023 LEE GUILBEAUX
Low Impact Development (LID) Cleared 7/24/2023 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 7/24/2023 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 7/25/2023 LEE GUILBEAUX
Grading Pre-Inspection Cleared 8/17/2023 JESSE ARELLANO

Contact Information

Contractor Owner-Builder       ,
Engineer Yenjai,, Seree; Lic. No.: C73151 3249 SHADYLAWN DRIVE      DUARTE, CA 91010

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 9/5/2023 Approved VINCENT HANLEY
Underground Mechanical 9/5/2023 Approved VINCENT HANLEY
Excavation/Setback/Form/Re-Bar 9/18/2023 Approved VINCENT HANLEY
Footing/Foundation/Slab 9/18/2023 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 9/28/2023 Approved VINCENT HANLEY
ELECTRICAL-Rough 2/8/2024 Approved VINCENT HANLEY
PLUMBING-Rough 2/8/2024 Approved VINCENT HANLEY
BUILDING-Rough-Frame 3/8/2024 Partial Approval VINCENT HANLEY
Green Building Rough 3/8/2024 Approved VINCENT HANLEY
Interior/Exterior Lathing 3/8/2024 Approved VINCENT HANLEY
BUILDING-Rough-Frame 4/19/2024 Partial Approval VINCENT HANLEY
Green Building Rough 4/19/2024 Approved VINCENT HANLEY
Interior/Exterior Lathing 4/19/2024 Approved VINCENT HANLEY
Shower Pan 4/19/2024 Approved VINCENT HANLEY
BUILDING-Rough-Frame 5/9/2024 Approved VINCENT HANLEY
Drywall Nailing 5/9/2024 Approved VINCENT HANLEY
ELECTRICAL-Final 5/9/2024 Approved VINCENT HANLEY
Final 5/9/2024 Corrections Issued VINCENT HANLEY
Green Building Final 5/9/2024 Approved VINCENT HANLEY
HVAC-Final 5/9/2024 Approved VINCENT HANLEY
PLUMBING-Final 5/9/2024 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 5/9/2024 SGSOV Approved VINCENT HANLEY
Service/Power Release 5/9/2024 Approved VINCENT HANLEY
Smoke Detectors 5/9/2024 Approved VINCENT HANLEY
Verify Sprinkler Sign Off 5/9/2024 Approved VINCENT HANLEY