13471 W TERRA BELLA ST 91331

Certificate Information: 13471 W TERRA BELLA ST 91331

Application / Permit
23010-20000-02215
Plan Check / Job No.
B23VN06899
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 30' X 20' (2) STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 10/27/2023
Issuing Office
Valley
Current Status
Issued on 10/27/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/25/2023 APPLICANT
Assigned to Plan Check Engineer 6/1/2023 SELLA BENYAMIN
Corrections Issued 6/6/2023 SELLA BENYAMIN
Quality Review Completed 6/6/2023 STEVEN KIM
Building Plans Picked Up 6/7/2023 APPLICANT
Plan Check Approved 10/26/2023 SELLA BENYAMIN
Issued 10/27/2023 APPLICANT

Permit Application Clearance Information

Address approval Cleared 9/6/2023 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 9/6/2023 DAGOVERTO GUERRERO
Sewer availability Cleared 9/6/2023 DAGOVERTO GUERRERO
Construction near power lines Cleared 9/7/2023 WALTER RAMIREZ
Low Impact Development (LID) Cleared 10/12/2023 MELINEH AGHAKHABIAN
Roof/Waste drainage to street Cleared 10/17/2023 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/15/2023 Not Ready for Inspection MICHEL ABAJAN
Footing/Foundation/Slab 11/15/2023 Not Ready for Inspection MICHEL ABAJAN
METHANE-Barrier 11/15/2023 Approved MICHEL ABAJAN
METHANE-Subgrade 11/15/2023 Approved MICHEL ABAJAN
Deputy Drilled-In Anchors 12/1/2023 Approved MICHEL ABAJAN
Excavation/Setback/Form/Re-Bar 12/1/2023 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 12/11/2023 Partial Approval MICHEL ABAJAN
Footing/Foundation/Slab 12/11/2023 Approved MICHEL ABAJAN
PLUMBING-Rough 12/11/2023 Partial Approval MICHEL ABAJAN
Underground Mechanical 12/11/2023 Not Ready for Inspection MICHEL ABAJAN
Insulation 12/12/2023 Partial Approval MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 1/9/2024 Partial Approval MICHEL ABAJAN
Sewer 1/9/2024 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 1/29/2024 Partial Approval MICHEL ABAJAN
ELECTRICAL-Rough 2/28/2024 Approved MICHEL ABAJAN
PLUMBING-Rough 2/28/2024 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 4/17/2024 Corrections Issued JOHN COLEMAN
Deputy Wood Construction 4/17/2024 Conditional Approval ROBERT GOLD
Green Building Rough 4/17/2024 Not Ready for Inspection JOHN COLEMAN
HVAC-Rough 4/17/2024 Approved JOHN COLEMAN
MERV13>=Rough 4/17/2024 Approved JOHN COLEMAN
METHANE-Rough 4/17/2024 Approved JOHN COLEMAN
Verify Sprinkler Sign Off 4/17/2024 Approved JOHN COLEMAN
BUILDING-Rough-Frame 4/19/2024 Corrections Issued MICHEL ABAJAN
Gas Test 4/19/2024 Approved MICHEL ABAJAN
Green Building Rough 4/19/2024 Not Ready for Inspection MICHEL ABAJAN
BUILDING-Rough-Frame 4/25/2024 Approved MICHEL ABAJAN
Green Building Rough 4/25/2024 Approved MICHEL ABAJAN
Insulation 5/20/2024 Approved JENNIFER RABUCHIN
Shower Pan 5/20/2024 Corrections Issued JENNIFER RABUCHIN
Interior/Exterior Lathing 5/24/2024 Approved MICHEL ABAJAN
Shower Pan 5/24/2024 Approved MICHEL ABAJAN
Drywall Nailing 6/12/2024 Approved MICHEL ABAJAN
ELECTRICAL-Final 10/9/2025 Corrections Issued KEVIN BERBERYAN
Green Building Final 10/9/2025 Not Ready for Inspection KEVIN BERBERYAN
ELECTRICAL-Final 3/13/2026 Corrections Issued MICHEL ABAJAN
HVAC-Final 3/13/2026 Corrections Issued MICHEL ABAJAN
PLUMBING-Final 3/13/2026 Approved MICHEL ABAJAN