- Permit Issued
- Issued on 5/7/2024
- Issuing Office
- Current Status
- CofO Issued on 6/30/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/30/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/2/2023 | LUISANGEL VALENZUELA |
| Corrections Issued | 6/3/2023 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 11/27/2023 | LUISANGEL VALENZUELA |
| Plan Check Approved | 5/6/2024 | JOSEPH RAFOLS |
| Issued | 5/7/2024 | APPLICANT |
| CofO in Progress | 6/3/2026 | GAREN HAYRAPETYAN |
| CofO Issued | 6/30/2026 | RUBEN SALAS |
| Permit Finaled | 6/30/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 6/9/2023 | LEE GUILBEAUX |
| Sewer availability | Cleared | 6/9/2023 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 7/10/2023 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 7/10/2023 | LEE GUILBEAUX |
| Public Works-Sewers | Cleared | 7/10/2023 | LEE GUILBEAUX |
| Construction near power lines | Cleared | 11/9/2023 | RIDWAN HARDY |
| Address approval | Cleared | 4/4/2024 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Makeover Builders Inc.; Lic. No.: 986740-B | , |
| Contractor | Makeover Builders Inc; Lic. No.: 986740-B | , |
| Engineer | Babapirzadeh,, Ghazal; Lic. No.: C90480 | 7270 HILLSIDE AVE APT 306 LOS ANGELES, CA 90046 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/19/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 7/19/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 9/3/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 11/7/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 11/7/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 11/7/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 11/7/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 11/7/2024 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Sewer | 11/7/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Special/Order Compliance | 11/7/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Verify Sprinkler Sign Off | 11/7/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 11/8/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 11/19/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 11/19/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 11/19/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 11/19/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 11/19/2024 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 11/19/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Insulation | 11/21/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Drywall Nailing | 12/2/2024 | Approved | MICHAEL CORTEZ |
| Interior/Exterior Lathing | 12/2/2024 | Approved | MICHAEL CORTEZ |
| Shower Pan | 12/2/2024 | Approved | MICHAEL CORTEZ |
| Final | 5/19/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 5/19/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 5/19/2025 | SGSOV Not Required | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 5/19/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 5/19/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 5/29/2026 | Corrections Issued | GAREN HAYRAPETYAN |
| Green Building Final | 5/29/2026 | Approved | GAREN HAYRAPETYAN |
| Service/Power Release | 5/29/2026 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Final | 6/3/2026 | OK to Issue CofO | GAREN HAYRAPETYAN |
| Service/Power Release | 6/3/2026 | Approved | GAREN HAYRAPETYAN |