6612 N COSTELLO AVE 91405
Certificate Information: 6612 N COSTELLO AVE 91405
- Application / Permit
- 23010-20000-02182
- Plan Check / Job No.
- B23VN06771
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN ENLARGE AND CONVERT EXISTING DETACHED GARAGE INTO NEW 1200 SQ.FT 1 STORY ADU PER ORDINANCE LAMC 12.22 A.33(c)-(d)
- Permit Issued
- Issued on 7/25/2023
- Issuing Office
- Current Status
- CofO Issued on 3/29/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/23/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/8/2023 | JAD BASMA |
| Corrections Issued | 6/14/2023 | JAD BASMA |
| Quality Review Completed | 6/21/2023 | TEODORO DIAZ RODRIGUEZ |
| Plan Check Approved | 7/19/2023 | JAD BASMA |
| Issued | 7/25/2023 | APPLICANT |
| CofO in Progress | 3/26/2024 | RYAN SALAZAR |
| Permit Finaled | 3/29/2024 | DANIEL ORRANTE |
| CofO Issued | 3/29/2024 | DANIEL ORRANTE |
| Permit Finaled | 3/29/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 6/16/2023 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 6/16/2023 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 6/23/2023 | DAGOVERTO GUERRERO |
| Low Impact Development (LID) | Cleared | 7/14/2023 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 7/14/2023 | JOHN LIN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/4/2023 | Partial Approval | JENNIFER RABUCHIN |
| Pre-Inspection | 8/4/2023 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 8/11/2023 | Partial Approval | RYAN SALAZAR |
| Excavation/Setback/Form/Re-Bar | 8/17/2023 | Approved | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 10/5/2023 | Partial Approval | RYAN SALAZAR |
| BUILDING-Rough-Frame | 10/11/2023 | Approved | RYAN SALAZAR |
| ELECTRICAL-Rough | 10/11/2023 | Approved | RYAN SALAZAR |
| Green Building Rough | 10/11/2023 | Approved | RYAN SALAZAR |
| HVAC-Rough | 10/11/2023 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 10/11/2023 | Approved | RYAN SALAZAR |
| Insulation | 10/24/2023 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 10/24/2023 | Partial Approval | RYAN SALAZAR |
| Shower Pan | 10/24/2023 | Approved | RYAN SALAZAR |
| Drywall Nailing | 11/8/2023 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 11/15/2023 | Approved | RYAN SALAZAR |
| Footing/Foundation/Slab | 2/27/2024 | Approved | RYAN SALAZAR |
| Green Building Final | 2/27/2024 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 2/27/2024 | SGSOV Approved | RYAN SALAZAR |
| Smoke Detectors | 2/27/2024 | Approved | RYAN SALAZAR |
| Final | 3/6/2024 | Partial Approval | RYAN SALAZAR |
| Service/Power Release | 3/6/2024 | Approved | RYAN SALAZAR |
| Final | 3/21/2024 | OK to Issue CofO | RYAN SALAZAR |