6612 N COSTELLO AVE 91405

Certificate Information: 6612 N COSTELLO AVE 91405

Application / Permit
23010-20000-02182
Plan Check / Job No.
B23VN06771
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN ENLARGE AND CONVERT EXISTING DETACHED GARAGE INTO NEW 1200 SQ.FT 1 STORY ADU PER ORDINANCE LAMC 12.22 A.33(c)-(d)
Permit Issued
Issued on 7/25/2023
Issuing Office
Current Status
CofO Issued on 3/29/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/23/2023 APPLICANT
Assigned to Plan Check Engineer 6/8/2023 JAD BASMA
Corrections Issued 6/14/2023 JAD BASMA
Quality Review Completed 6/21/2023 TEODORO DIAZ RODRIGUEZ
Plan Check Approved 7/19/2023 JAD BASMA
Issued 7/25/2023 APPLICANT
CofO in Progress 3/26/2024 RYAN SALAZAR
Permit Finaled 3/29/2024 DANIEL ORRANTE
CofO Issued 3/29/2024 DANIEL ORRANTE
Permit Finaled 3/29/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 6/16/2023 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 6/16/2023 DAGOVERTO GUERRERO
Sewer availability Cleared 6/23/2023 DAGOVERTO GUERRERO
Low Impact Development (LID) Cleared 7/14/2023 LUIS LUVANO
Roof/Waste drainage to street Cleared 7/14/2023 JOHN LIN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/4/2023 Partial Approval JENNIFER RABUCHIN
Pre-Inspection 8/4/2023 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 8/11/2023 Partial Approval RYAN SALAZAR
Excavation/Setback/Form/Re-Bar 8/17/2023 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 10/5/2023 Partial Approval RYAN SALAZAR
BUILDING-Rough-Frame 10/11/2023 Approved RYAN SALAZAR
ELECTRICAL-Rough 10/11/2023 Approved RYAN SALAZAR
Green Building Rough 10/11/2023 Approved RYAN SALAZAR
HVAC-Rough 10/11/2023 Approved RYAN SALAZAR
PLUMBING-Rough 10/11/2023 Approved RYAN SALAZAR
Insulation 10/24/2023 Approved RYAN SALAZAR
Interior/Exterior Lathing 10/24/2023 Partial Approval RYAN SALAZAR
Shower Pan 10/24/2023 Approved RYAN SALAZAR
Drywall Nailing 11/8/2023 Approved RYAN SALAZAR
Interior/Exterior Lathing 11/15/2023 Approved RYAN SALAZAR
Footing/Foundation/Slab 2/27/2024 Approved RYAN SALAZAR
Green Building Final 2/27/2024 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 2/27/2024 SGSOV Approved RYAN SALAZAR
Smoke Detectors 2/27/2024 Approved RYAN SALAZAR
Final 3/6/2024 Partial Approval RYAN SALAZAR
Service/Power Release 3/6/2024 Approved RYAN SALAZAR
Final 3/21/2024 OK to Issue CofO RYAN SALAZAR