6656 N TEESDALE AVE 91606

Certificate Information: 6656 N TEESDALE AVE 91606

Application / Permit
23010-20000-02153
Plan Check / Job No.
B23VN06697
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 22'-6" x 20'-0" DETACHED, FULLY ELECTRIC ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). WORK DONE PER WFPP.
Permit Issued
Issued on 11/19/2024
Issuing Office
Current Status
CofO Issued on 4/2/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/22/2023 APPLICANT
Assigned to Plan Check Engineer 6/27/2023 MIROOSH KHACHATOORIAN
Corrections Issued 6/28/2023 MIROOSH KHACHATOORIAN
Applicant returned to address corrections 7/25/2024 GIOVANNY CHAVEZ
Applicant returned to address corrections 11/6/2024 GIOVANNY CHAVEZ
Plan Check Approved 11/12/2024 MADISON O'DELL
Issued 11/19/2024 APPLICANT
CofO in Progress 3/28/2026 RAUL OLAGI
Permit Finaled 4/2/2026 RUBEN SALAS
CofO Issued 4/2/2026 RUBEN SALAS
Permit Finaled 4/2/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 7/25/2023 TAL SHEMEN
Construction near power lines Cleared 11/18/2023 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 2/26/2024 TAL SHEMEN
Sewer availability Cleared 2/26/2024 TAL SHEMEN
Low Impact Development (LID) Cleared 10/22/2024 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 11/8/2024 TAL SHEMEN

Contact Information

Contractor New E R A Construction Company; Lic. No.: 792694-B       ,

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Gas Test 11/25/2024 Corrections Issued GAREN HAYRAPETYAN
PLUMBING-Rough 11/25/2024 Partial Approval GAREN HAYRAPETYAN
Underground Mechanical 11/25/2024 Corrections Issued GAREN HAYRAPETYAN
Excavation/Setback/Form/Re-Bar 12/6/2024 Approved OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 1/6/2025 Corrections Issued GAREN HAYRAPETYAN
PLUMBING-Rough 1/6/2025 Approved GAREN HAYRAPETYAN
Sewer 1/6/2025 Partial Approval GAREN HAYRAPETYAN
BUILDING-Rough-Frame 1/13/2025 Approved GAREN HAYRAPETYAN
ELECTRICAL-Rough 1/13/2025 Approved GAREN HAYRAPETYAN
Green Building Rough 1/13/2025 Approved GAREN HAYRAPETYAN
HVAC-Rough 1/13/2025 Approved GAREN HAYRAPETYAN
Interior/Exterior Lathing 1/13/2025 Partial Approval GAREN HAYRAPETYAN
Verify Sprinkler Sign Off 1/13/2025 Approved GAREN HAYRAPETYAN
Insulation 1/16/2025 Corrections Issued GAREN HAYRAPETYAN
Shower Pan 1/16/2025 Approved GAREN HAYRAPETYAN
Insulation 1/22/2025 Not Ready for Inspection OGANES TARAKHCHYAN
Insulation 1/27/2025 Corrections Issued OGANES TARAKHCHYAN
Insulation 2/3/2025 Approved GAREN HAYRAPETYAN
Drywall Nailing 5/8/2025 Approved OGANES TARAKHCHYAN
Final 5/8/2025 Not Ready for Inspection OGANES TARAKHCHYAN
Footing/Foundation/Slab 5/8/2025 Approved OGANES TARAKHCHYAN
Green Building Final 5/8/2025 Not Ready for Inspection OGANES TARAKHCHYAN
Smoke Detectors 5/8/2025 Approved OGANES TARAKHCHYAN
Final 6/27/2025 Corrections Issued GAREN HAYRAPETYAN
Green Building Final 6/27/2025 Approved GAREN HAYRAPETYAN
Service/Power Release 6/27/2025 Conditional Approval GAREN HAYRAPETYAN
Final 3/3/2026 Corrections Issued WAYNE REGESTER
Service/Power Release 3/3/2026 Approved WAYNE REGESTER
Final 3/9/2026 Not Ready for Inspection WAYNE REGESTER
ELECTRICAL-Final 3/12/2026 Approved WAYNE REGESTER
Final 3/12/2026 Corrections Issued WAYNE REGESTER
Green Building Final 3/12/2026 Approved WAYNE REGESTER
HVAC-Final 3/12/2026 Approved WAYNE REGESTER
PLUMBING-Final 3/12/2026 Approved WAYNE REGESTER
Final 3/28/2026 OK to Issue CofO RAUL OLAGI