11720 W GAIN ST 91342

Certificate Information: 11720 W GAIN ST 91342

Application / Permit
23010-20000-02149
Plan Check / Job No.
B23VN06678
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: (N) 2-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33.(c)-(d)
Permit Issued
Issued on 10/9/2023
Issuing Office
Current Status
CofO Issued on 10/23/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/24/2023 APPLICANT
Assigned to Plan Check Engineer 6/8/2023 DANIEL YIP
Corrections Issued 6/14/2023 DANIEL YIP
Quality Review Completed 6/14/2023 GARO TELMI
Applicant returned to address corrections 8/31/2023 DANIEL YIP
Plan Check Approved 10/4/2023 JOHN FRANCIA
Issued 10/9/2023 APPLICANT
CofO in Progress 10/8/2024 MICHEL ABAJAN
Permit Finaled 10/23/2024 DANIEL ORRANTE
CofO Issued 10/23/2024 DANIEL ORRANTE
Permit Finaled 10/23/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 6/26/2023 DAGOVERTO GUERRERO
Sewer availability Cleared 6/27/2023 DAGOVERTO GUERRERO
Grading Pre-Inspection Cleared 8/9/2023 ALEXANDER HELFER
Eng Process Fee Ord 176,300 Cleared 8/21/2023 DAGOVERTO GUERRERO
Low Impact Development (LID) Cleared 8/21/2023 SAMUEL LINN
Roof/Waste drainage to street Cleared 8/21/2023 DAGOVERTO GUERRERO
GPI Written Notices Cleared 8/31/2023 DANIEL YIP
Construction near power lines Cleared 9/15/2023 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Keshishian,, Anthony; Lic. No.: C89551 2654 RISA D      GLENDALE, CA 91208

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/28/2023 Approved MICHEL ABAJAN
PLUMBING-Rough 12/4/2023 Partial Approval MICHEL ABAJAN
Footing/Foundation/Slab 12/13/2023 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 1/4/2024 Corrections Issued MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 1/8/2024 Partial Approval MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 1/17/2024 Partial Approval MICHEL ABAJAN
Pre-Inspection 1/23/2024 Partial Inspection MICHEL ABAJAN
BUILDING-Rough-Frame 2/16/2024 Approved MICHEL ABAJAN
ELECTRICAL-Rough 2/16/2024 Approved MICHEL ABAJAN
Green Building Rough 2/16/2024 Approved MICHEL ABAJAN
HVAC-Rough 2/16/2024 Approved MICHEL ABAJAN
PLUMBING-Rough 2/16/2024 Approved MICHEL ABAJAN
Verify Sprinkler Sign Off 2/16/2024 Approved MICHEL ABAJAN
Insulation 3/6/2024 Approved MICHEL ABAJAN
Interior/Exterior Lathing 3/6/2024 Approved MICHEL ABAJAN
Shower Pan 3/6/2024 Approved MICHEL ABAJAN
Drywall Nailing 3/13/2024 Approved WILLIAM WREN
Interior/Exterior Lathing 3/27/2024 Approved MICHEL ABAJAN
Shower Pan 3/27/2024 Approved MICHEL ABAJAN
Gas Test 5/23/2024 Approved JOHN COLEMAN
PLUMBING-Rough 5/23/2024 Partial Approval JOHN COLEMAN
Sewer 5/23/2024 Approved JOHN COLEMAN
ELECTRICAL-Final 8/28/2024 Corrections Issued SALVADOR MARTINEZ
Final 8/28/2024 Corrections Issued SALVADOR MARTINEZ
Green Building Final 8/28/2024 Approved SALVADOR MARTINEZ
HVAC-Final 8/28/2024 Corrections Issued SALVADOR MARTINEZ
PLUMBING-Final 8/28/2024 Corrections Issued SALVADOR MARTINEZ
SGSOV-Seismic Gas S/O Valve 8/28/2024 SGSOV Approved SALVADOR MARTINEZ
Service/Power Release 8/28/2024 Not Ready for Inspection SALVADOR MARTINEZ
Smoke Detectors 8/28/2024 Approved SALVADOR MARTINEZ
ELECTRICAL-Final 10/8/2024 Approved MICHEL ABAJAN
Final 10/8/2024 OK to Issue CofO MICHEL ABAJAN
HVAC-Final 10/8/2024 Approved MICHEL ABAJAN
PLUMBING-Final 10/8/2024 Approved MICHEL ABAJAN
Service/Power Release 10/8/2024 Approved MICHEL ABAJAN