11720 W GAIN ST 91342
Certificate Information: 11720 W GAIN ST 91342
- Application / Permit
- 23010-20000-02149
- Plan Check / Job No.
- B23VN06678
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: (N) 2-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33.(c)-(d)
- Permit Issued
- Issued on 10/9/2023
- Issuing Office
- Current Status
- CofO Issued on 10/23/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/24/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/8/2023 | DANIEL YIP |
| Corrections Issued | 6/14/2023 | DANIEL YIP |
| Quality Review Completed | 6/14/2023 | GARO TELMI |
| Applicant returned to address corrections | 8/31/2023 | DANIEL YIP |
| Plan Check Approved | 10/4/2023 | JOHN FRANCIA |
| Issued | 10/9/2023 | APPLICANT |
| CofO in Progress | 10/8/2024 | MICHEL ABAJAN |
| Permit Finaled | 10/23/2024 | DANIEL ORRANTE |
| CofO Issued | 10/23/2024 | DANIEL ORRANTE |
| Permit Finaled | 10/23/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 6/26/2023 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 6/27/2023 | DAGOVERTO GUERRERO |
| Grading Pre-Inspection | Cleared | 8/9/2023 | ALEXANDER HELFER |
| Eng Process Fee Ord 176,300 | Cleared | 8/21/2023 | DAGOVERTO GUERRERO |
| Low Impact Development (LID) | Cleared | 8/21/2023 | SAMUEL LINN |
| Roof/Waste drainage to street | Cleared | 8/21/2023 | DAGOVERTO GUERRERO |
| GPI Written Notices | Cleared | 8/31/2023 | DANIEL YIP |
| Construction near power lines | Cleared | 9/15/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Keshishian,, Anthony; Lic. No.: C89551 | 2654 RISA D GLENDALE, CA 91208 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/28/2023 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 12/4/2023 | Partial Approval | MICHEL ABAJAN |
| Footing/Foundation/Slab | 12/13/2023 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/4/2024 | Corrections Issued | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/8/2024 | Partial Approval | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/17/2024 | Partial Approval | MICHEL ABAJAN |
| Pre-Inspection | 1/23/2024 | Partial Inspection | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 2/16/2024 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 2/16/2024 | Approved | MICHEL ABAJAN |
| Green Building Rough | 2/16/2024 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 2/16/2024 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 2/16/2024 | Approved | MICHEL ABAJAN |
| Verify Sprinkler Sign Off | 2/16/2024 | Approved | MICHEL ABAJAN |
| Insulation | 3/6/2024 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 3/6/2024 | Approved | MICHEL ABAJAN |
| Shower Pan | 3/6/2024 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 3/13/2024 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 3/27/2024 | Approved | MICHEL ABAJAN |
| Shower Pan | 3/27/2024 | Approved | MICHEL ABAJAN |
| Gas Test | 5/23/2024 | Approved | JOHN COLEMAN |
| PLUMBING-Rough | 5/23/2024 | Partial Approval | JOHN COLEMAN |
| Sewer | 5/23/2024 | Approved | JOHN COLEMAN |
| ELECTRICAL-Final | 8/28/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Final | 8/28/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Green Building Final | 8/28/2024 | Approved | SALVADOR MARTINEZ |
| HVAC-Final | 8/28/2024 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Final | 8/28/2024 | Corrections Issued | SALVADOR MARTINEZ |
| SGSOV-Seismic Gas S/O Valve | 8/28/2024 | SGSOV Approved | SALVADOR MARTINEZ |
| Service/Power Release | 8/28/2024 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Smoke Detectors | 8/28/2024 | Approved | SALVADOR MARTINEZ |
| ELECTRICAL-Final | 10/8/2024 | Approved | MICHEL ABAJAN |
| Final | 10/8/2024 | OK to Issue CofO | MICHEL ABAJAN |
| HVAC-Final | 10/8/2024 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 10/8/2024 | Approved | MICHEL ABAJAN |
| Service/Power Release | 10/8/2024 | Approved | MICHEL ABAJAN |