6602 N GLORIA AVE 91406
Certificate Information: 6602 N GLORIA AVE 91406
- Application / Permit
- 23010-20000-02147
- Plan Check / Job No.
- B23VN06669
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 70'-10" X 22' - 5" ONE STORY SINGLE FAMILY DWELLING PER SB-9 ALL WORK PER WFPP BUILDING SHALL BE FULLY SPRINKLERED WITH NFPA 13D. TO BE ISSUED CONCURRENTLY WITH 23016-20000-39150
- Permit Issued
- Issued on 11/9/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/14/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
Submitted | 5/24/2023 | APPLICANT |
Assigned to Plan Check Engineer | 6/8/2023 | SEWADA ZADOORIAN MILAGARDI |
Corrections Issued | 6/12/2023 | SEWADA ZADOORIAN MILAGARDI |
Quality Review Completed | 6/14/2023 | OMID HEDAYAT |
Building Plans Picked Up | 11/2/2023 | APPLICANT |
Plan Check Approved | 11/6/2023 | SEWADA ZADOORAN MILAGARDI |
Issued | 11/9/2023 | APPLICANT |
CofO in Progress | 12/9/2024 | SALVADOR MARTINEZ |
Permit Finaled | 12/14/2024 | RUBEN SALAS |
CofO Issued | 12/14/2024 | RUBEN SALAS |
Permit Finaled | 12/14/2024 | RUBEN SALAS |
Permit Application Clearance Information
Address approval | Cleared | 8/17/2023 | ROMAN GUTIERREZ |
Permit | Cleared | 8/17/2023 | ROMAN GUTIERREZ |
Low Impact Development (LID) | Cleared | 8/21/2023 | TOMMY YIN |
Eng Process Fee Ord 176,300 | Cleared | 8/22/2023 | ROMAN GUTIERREZ |
Roof/Waste drainage to street | Cleared | 8/22/2023 | ROMAN GUTIERREZ |
Sewer availability | Cleared | 8/22/2023 | ROMAN GUTIERREZ |
Hydrant and Access approval | Cleared | 10/13/2023 | GILBERT URREA |
Miscellaneous | Cleared | 10/30/2023 | NELSON RODRIGUEZ |
Senate Bill 9 | Cleared | 10/31/2023 | NELSON RODRIGUEZ |
Hold | Cleared | 1/26/2024 | MARIA VENDIVIL |
Contact Information
Contractor | Owner-Builder | , |
Inspector Information
SALVADOR MARTINEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
No Data Available. |
Inspection Request History
Pre-Inspection | 12/8/2023 | Partial Inspection | RAUL OLAGI |
Footing/Foundation/Slab | 1/2/2024 | Approved | JOHN COLEMAN |
PLUMBING-Rough | 1/2/2024 | Partial Approval | JOHN COLEMAN |
Footing/Foundation/Slab | 1/8/2024 | Corrections Issued | RAUL OLAGI |
Footing/Foundation/Slab | 1/18/2024 | Not Ready for Inspection | RAUL OLAGI |
Footing/Foundation/Slab | 1/19/2024 | Approved | RAUL OLAGI |
BUILDING-Rough-Frame | 1/29/2024 | Corrections Issued | CRAIG DAVIS |
PLUMBING-Rough | 1/29/2024 | Corrections Issued | CRAIG DAVIS |
Floor/Roof Diaphrgm/Shear Wall | 1/31/2024 | Partial Approval | RAUL OLAGI |
PLUMBING-Rough | 1/31/2024 | Partial Approval | RAUL OLAGI |
Floor/Roof Diaphrgm/Shear Wall | 2/12/2024 | Partial Approval | DAVID ANDERSON |
Floor/Roof Diaphrgm/Shear Wall | 2/22/2024 | Corrections Issued | RAUL OLAGI |
ELECTRICAL-Rough | 3/14/2024 | Corrections Issued | RAUL OLAGI |
HVAC-Rough | 3/14/2024 | Approved | RAUL OLAGI |
PLUMBING-Rough | 3/14/2024 | Corrections Issued | RAUL OLAGI |
Sewer | 3/14/2024 | Corrections Issued | RAUL OLAGI |
Verify Sprinkler Sign Off | 3/14/2024 | Approved | RAUL OLAGI |
Floor/Roof Diaphrgm/Shear Wall | 3/21/2024 | Approved | RAUL OLAGI |
PLUMBING-Rough | 3/21/2024 | Approved | RAUL OLAGI |
Sewer | 3/21/2024 | Approved | RAUL OLAGI |
BUILDING-Rough-Frame | 4/16/2024 | Approved | RAUL OLAGI |
ELECTRICAL-Rough | 4/16/2024 | Approved | RAUL OLAGI |
Shower Pan | 4/16/2024 | Approved | RAUL OLAGI |
Underground Mechanical | 4/16/2024 | Approved | RAUL OLAGI |
Insulation | 4/22/2024 | Corrections Issued | SALVADOR MARTINEZ |
Interior/Exterior Lathing | 4/22/2024 | Corrections Issued | SALVADOR MARTINEZ |
Insulation | 4/25/2024 | Approved | SALVADOR MARTINEZ |
Interior/Exterior Lathing | 4/25/2024 | Partial Approval | SALVADOR MARTINEZ |
Drywall Nailing | 5/1/2024 | Approved | RAUL OLAGI |
Green Building Rough | 5/1/2024 | Approved | RAUL OLAGI |
Interior/Exterior Lathing | 5/13/2024 | Approved | SALVADOR MARTINEZ |
Final | 9/17/2024 | Corrections Issued | RAUL OLAGI |
Green Building Final | 9/17/2024 | Approved | RAUL OLAGI |
SGSOV-Seismic Gas S/O Valve | 9/17/2024 | SGSOV Not Required | RAUL OLAGI |
Smoke Detectors | 9/17/2024 | Approved | RAUL OLAGI |
Final | 11/18/2024 | Corrections Issued | SALVADOR MARTINEZ |
Final | 11/22/2024 | Corrections Issued | SALVADOR MARTINEZ |
Final | 12/2/2024 | Corrections Issued | SALVADOR MARTINEZ |
Final | 12/6/2024 | OK to Issue CofO | SALVADOR MARTINEZ |
Service/Power Release | 12/6/2024 | Partial Inspection | SALVADOR MARTINEZ |