5428 N CALHOUN AVE 91401
Certificate Information: 5428 N CALHOUN AVE 91401
- Application / Permit
- 23010-20000-02146
- Plan Check / Job No.
- B23VN06668
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 33' 10" X 22' 6" NFPA 13R SPRINKLERED AND TYPE VA CONSTRUCTION PER FIRE DEPARTMENT ADU UNIT PER LAMC 12.22 A.33 (c)-(d) . ALL WORK DONE PER ENGINEER.
- Permit Issued
- Issued on 5/3/2024
- Issuing Office
- Current Status
- CofO Issued on 5/14/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/22/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/8/2023 | NAREG ATARIAN |
| Corrections Issued | 6/8/2023 | NAREG ATARIAN |
| Quality Review Completed | 6/14/2023 | OMID HEDAYAT |
| Plan Check Approved | 9/25/2023 | NAREG ATARIAN |
| Issued | 5/3/2024 | APPLICANT |
| CofO in Progress | 3/18/2026 | VINCENT HANLEY |
| Permit Finaled | 5/14/2026 | RUBEN SALAS |
| CofO Issued | 5/14/2026 | RUBEN SALAS |
| Permit Finaled | 5/14/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 7/3/2023 | NIKKI ZULUETA |
| Hydrant and Access approval | Cleared | 8/11/2023 | KURT CORRAL |
| Eng Process Fee Ord 176,300 | Cleared | 8/25/2023 | NIKKI ZULUETA |
| Low Impact Development (LID) | Cleared | 9/7/2023 | TOMMY YIN |
| Roof/Waste drainage to street | Cleared | 9/13/2023 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 9/13/2023 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Andrejic,, Milos; Lic. No.: C67443 | 3601 BEVERLY RIDGE DR SHERMAN OAKS, CA 91423 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/9/2024 | Partial Approval | RYAN SALAZAR |
| PLUMBING-Rough | 9/16/2024 | Partial Approval | RYAN SALAZAR |
| Footing/Foundation/Slab | 9/25/2024 | Corrections Issued | GAREN HAYRAPETYAN |
| Special/Order Compliance | 9/25/2024 | Approved | DAVID MATSON |
| Footing/Foundation/Slab | 9/30/2024 | Approved | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 10/11/2024 | Partial Approval | RYAN SALAZAR |
| BUILDING-Rough-Frame | 11/7/2024 | Not Ready for Inspection | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 11/7/2024 | Approved | RYAN SALAZAR |
| Verify Sprinkler Sign Off | 11/7/2024 | Approved | RYAN SALAZAR |
| ELECTRICAL-Rough | 11/13/2024 | Approved | RYAN SALAZAR |
| HVAC-Rough | 11/13/2024 | Approved | RYAN SALAZAR |
| Insulation | 11/13/2024 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 11/13/2024 | Partial Approval | RYAN SALAZAR |
| PLUMBING-Rough | 11/13/2024 | Approved | RYAN SALAZAR |
| Shower Pan | 11/13/2024 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 11/25/2024 | Partial Approval | RYAN SALAZAR |
| Drywall Nailing | 1/21/2025 | Approved | RUBEN SALAS |
| PLUMBING-Rough | 4/24/2025 | Partial Approval | RYAN SALAZAR |
| Sewer | 4/24/2025 | Approved | RYAN SALAZAR |
| Underground Mechanical | 4/29/2025 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 3/17/2026 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 3/17/2026 | Approved | VINCENT HANLEY |
| Final | 3/17/2026 | OK to Issue CofO | VINCENT HANLEY |
| HVAC-Final | 3/17/2026 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 3/17/2026 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 3/17/2026 | SGSOV Not Required | VINCENT HANLEY |
| Service/Power Release | 3/17/2026 | Approved | VINCENT HANLEY |
| Smoke Detectors | 3/17/2026 | Approved | VINCENT HANLEY |