5428 1/2 N CALHOUN AVE 91401

Certificate Information: 5428 1/2 N CALHOUN AVE 91401

Application / Permit
23010-20000-02145
Plan Check / Job No.
B23VN06668
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) DWELLING UNIT 22' 6" X 33' 10" IN THE REAR YARD WITH NFPA 13R SPRINKLER SYSTEM THRU OUT AND TYPA VA CONSTRUCTION PER FIRE DEPARTMENT. PER SB9. ALL WORK DONE PER ENGINEER.
Permit Issued
Issued on 5/3/2024
Issuing Office
Current Status
CofO Issued on 5/14/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/22/2023 APPLICANT
Assigned to Plan Check Engineer 6/8/2023 NAREG ATARIAN
Corrections Issued 6/8/2023 NAREG ATARIAN
Quality Review Completed 6/14/2023 OMID HEDAYAT
Plan Check Approved 9/25/2023 NAREG ATARIAN
Issued 5/3/2024 APPLICANT
CofO in Progress 3/18/2026 VINCENT HANLEY
CofO Issued 5/14/2026 RUBEN SALAS
Permit Finaled 5/14/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 7/3/2023 NIKKI ZULUETA
Senate Bill 9 Cleared 7/25/2023 BRENNEN OBETO
Hydrant and Access approval Cleared 8/11/2023 KURT CORRAL
Eng Process Fee Ord 176,300 Cleared 8/25/2023 NIKKI ZULUETA
Low Impact Development (LID) Cleared 9/7/2023 TOMMY YIN
Roof/Waste drainage to street Cleared 9/13/2023 DAGOVERTO GUERRERO
Sewer availability Cleared 9/13/2023 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,
Engineer Andrejic,, Milos; Lic. No.: C67443 3601 BEVERLY RIDGE DR      SHERMAN OAKS, CA 91423

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/23/2024 Partial Inspection RYAN SALAZAR
Excavation/Setback/Form/Re-Bar 9/9/2024 Partial Approval RYAN SALAZAR
PLUMBING-Rough 9/16/2024 Partial Approval RYAN SALAZAR
Footing/Foundation/Slab 9/25/2024 Corrections Issued GAREN HAYRAPETYAN
Special/Order Compliance 9/25/2024 Approved DAVID MATSON
Footing/Foundation/Slab 9/30/2024 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 10/23/2024 Partial Approval RYAN SALAZAR
Pre-Inspection 10/23/2024 Partial Inspection RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 11/7/2024 Approved RYAN SALAZAR
PLUMBING-Rough 11/7/2024 Approved RYAN SALAZAR
Deputy Wood Construction 11/12/2024 Conditional Approval RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 11/13/2024 Approved RYAN SALAZAR
Rough-Elec/Plmb/HVAC 11/25/2024 Approved RYAN SALAZAR
Insulation 12/6/2024 Approved RYAN SALAZAR
BUILDING-Rough-Frame 1/21/2025 Not Ready for Inspection RUBEN SALAS
Drywall Nailing 1/21/2025 Not Ready for Inspection RUBEN SALAS
Final 1/21/2025 Not Ready for Inspection RUBEN SALAS
SGSOV-Seismic Gas S/O Valve 1/21/2025 SGSOV Not Ready RUBEN SALAS
Service/Power Release 1/21/2025 Not Ready for Inspection RUBEN SALAS
Smoke Detectors 1/21/2025 Not Ready for Inspection RUBEN SALAS
Verify Sprinkler Sign Off 1/21/2025 Not Ready for Inspection RUBEN SALAS
PLUMBING-Rough 4/24/2025 Partial Approval RYAN SALAZAR
Sewer 4/24/2025 Approved RYAN SALAZAR
Underground Mechanical 4/29/2025 Approved RYAN SALAZAR
BUILDING-Rough-Frame 7/31/2025 Approved KEVIN BERBERYAN
Drywall Nailing 7/31/2025 Approved KEVIN BERBERYAN
Final 7/31/2025 Corrections Issued KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 7/31/2025 SGSOV No Gas KEVIN BERBERYAN
Service/Power Release 7/31/2025 Not Ready for Inspection KEVIN BERBERYAN
Smoke Detectors 7/31/2025 Not Ready for Inspection KEVIN BERBERYAN
Verify Sprinkler Sign Off 7/31/2025 Approved KEVIN BERBERYAN
ELECTRICAL-Final 3/17/2026 Approved VINCENT HANLEY
Final 3/17/2026 OK to Issue CofO VINCENT HANLEY
HVAC-Final 3/17/2026 Approved VINCENT HANLEY
PLUMBING-Final 3/17/2026 Approved VINCENT HANLEY
Service/Power Release 3/17/2026 Approved VINCENT HANLEY
Smoke Detectors 3/17/2026 Approved VINCENT HANLEY