5428 1/2 N CALHOUN AVE 91401
Certificate Information: 5428 1/2 N CALHOUN AVE 91401
- Application / Permit
- 23010-20000-02145
- Plan Check / Job No.
- B23VN06668
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) DWELLING UNIT 22' 6" X 33' 10" IN THE REAR YARD WITH NFPA 13R SPRINKLER SYSTEM THRU OUT AND TYPA VA CONSTRUCTION PER FIRE DEPARTMENT. PER SB9. ALL WORK DONE PER ENGINEER.
- Permit Issued
- Issued on 5/3/2024
- Issuing Office
- Current Status
- CofO Issued on 5/14/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/22/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/8/2023 | NAREG ATARIAN |
| Corrections Issued | 6/8/2023 | NAREG ATARIAN |
| Quality Review Completed | 6/14/2023 | OMID HEDAYAT |
| Plan Check Approved | 9/25/2023 | NAREG ATARIAN |
| Issued | 5/3/2024 | APPLICANT |
| CofO in Progress | 3/18/2026 | VINCENT HANLEY |
| CofO Issued | 5/14/2026 | RUBEN SALAS |
| Permit Finaled | 5/14/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 7/3/2023 | NIKKI ZULUETA |
| Senate Bill 9 | Cleared | 7/25/2023 | BRENNEN OBETO |
| Hydrant and Access approval | Cleared | 8/11/2023 | KURT CORRAL |
| Eng Process Fee Ord 176,300 | Cleared | 8/25/2023 | NIKKI ZULUETA |
| Low Impact Development (LID) | Cleared | 9/7/2023 | TOMMY YIN |
| Roof/Waste drainage to street | Cleared | 9/13/2023 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 9/13/2023 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Andrejic,, Milos; Lic. No.: C67443 | 3601 BEVERLY RIDGE DR SHERMAN OAKS, CA 91423 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/23/2024 | Partial Inspection | RYAN SALAZAR |
| Excavation/Setback/Form/Re-Bar | 9/9/2024 | Partial Approval | RYAN SALAZAR |
| PLUMBING-Rough | 9/16/2024 | Partial Approval | RYAN SALAZAR |
| Footing/Foundation/Slab | 9/25/2024 | Corrections Issued | GAREN HAYRAPETYAN |
| Special/Order Compliance | 9/25/2024 | Approved | DAVID MATSON |
| Footing/Foundation/Slab | 9/30/2024 | Approved | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 10/23/2024 | Partial Approval | RYAN SALAZAR |
| Pre-Inspection | 10/23/2024 | Partial Inspection | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 11/7/2024 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 11/7/2024 | Approved | RYAN SALAZAR |
| Deputy Wood Construction | 11/12/2024 | Conditional Approval | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 11/13/2024 | Approved | RYAN SALAZAR |
| Rough-Elec/Plmb/HVAC | 11/25/2024 | Approved | RYAN SALAZAR |
| Insulation | 12/6/2024 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 1/21/2025 | Not Ready for Inspection | RUBEN SALAS |
| Drywall Nailing | 1/21/2025 | Not Ready for Inspection | RUBEN SALAS |
| Final | 1/21/2025 | Not Ready for Inspection | RUBEN SALAS |
| SGSOV-Seismic Gas S/O Valve | 1/21/2025 | SGSOV Not Ready | RUBEN SALAS |
| Service/Power Release | 1/21/2025 | Not Ready for Inspection | RUBEN SALAS |
| Smoke Detectors | 1/21/2025 | Not Ready for Inspection | RUBEN SALAS |
| Verify Sprinkler Sign Off | 1/21/2025 | Not Ready for Inspection | RUBEN SALAS |
| PLUMBING-Rough | 4/24/2025 | Partial Approval | RYAN SALAZAR |
| Sewer | 4/24/2025 | Approved | RYAN SALAZAR |
| Underground Mechanical | 4/29/2025 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 7/31/2025 | Approved | KEVIN BERBERYAN |
| Drywall Nailing | 7/31/2025 | Approved | KEVIN BERBERYAN |
| Final | 7/31/2025 | Corrections Issued | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 7/31/2025 | SGSOV No Gas | KEVIN BERBERYAN |
| Service/Power Release | 7/31/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| Smoke Detectors | 7/31/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| Verify Sprinkler Sign Off | 7/31/2025 | Approved | KEVIN BERBERYAN |
| ELECTRICAL-Final | 3/17/2026 | Approved | VINCENT HANLEY |
| Final | 3/17/2026 | OK to Issue CofO | VINCENT HANLEY |
| HVAC-Final | 3/17/2026 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 3/17/2026 | Approved | VINCENT HANLEY |
| Service/Power Release | 3/17/2026 | Approved | VINCENT HANLEY |
| Smoke Detectors | 3/17/2026 | Approved | VINCENT HANLEY |