9775 N TELFAIR AVE 91331
Certificate Information: 9775 N TELFAIR AVE 91331
- Application / Permit
- 23010-20000-02140
- Plan Check / Job No.
- B23VN06661
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN NEW DETACHED Accessory dwelling unit per LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 10/4/2023
- Issuing Office
- Current Status
- CofO Issued on 12/4/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/22/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/25/2023 | MOHAMMAD ESMAILI |
| Corrections Issued | 5/26/2023 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 9/21/2023 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 9/26/2023 | MOHAMMAD ESMAILI |
| Plan Check Approved | 9/28/2023 | MOHAMMAD ESMAILI |
| Issued | 10/4/2023 | APPLICANT |
| CofO in Progress | 11/25/2024 | MICHEL ABAJAN |
| Permit Finaled | 12/4/2024 | RUBEN SALAS |
| CofO Issued | 12/4/2024 | RUBEN SALAS |
| Permit Finaled | 12/4/2024 | RUBEN SALAS |
Permit Application Clearance Information
| ZA Case | Cleared | 5/30/2023 | KENTON TRINH |
| ZI | Cleared | 5/30/2023 | KENTON TRINH |
| Address approval | Cleared | 6/5/2023 | NIKKI ZULUETA |
| Eng Process Fee Ord 176,300 | Cleared | 6/6/2023 | NIKKI ZULUETA |
| Sewer availability | Cleared | 6/7/2023 | NIKKI ZULUETA |
| Hydrant and Access approval | Cleared | 6/30/2023 | GILBERT URREA |
| Low Impact Development (LID) | Cleared | 8/9/2023 | VICTOR MENDOZA |
| Roof/Waste drainage to street | Cleared | 8/10/2023 | NIKKI ZULUETA |
| Construction near power lines | Cleared | 9/11/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Li,, Dacheng D; Lic. No.: NA58075 | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Gas Test | 10/16/2023 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 10/16/2023 | Partial Approval | MICHEL ABAJAN |
| Sewer | 10/16/2023 | Approved | MICHEL ABAJAN |
| Underground Mechanical | 10/16/2023 | Partial Approval | MICHEL ABAJAN |
| Footing/Foundation/Slab | 10/19/2023 | Approved | MICHEL ABAJAN |
| Deputy Wood Construction | 11/3/2023 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 11/6/2023 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 1/17/2024 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 1/17/2024 | Approved | MICHEL ABAJAN |
| Green Building Rough | 1/17/2024 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 1/17/2024 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 1/17/2024 | Approved | MICHEL ABAJAN |
| Verify Sprinkler Sign Off | 1/17/2024 | Approved | MICHEL ABAJAN |
| Insulation | 1/19/2024 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 1/19/2024 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 1/24/2024 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 1/24/2024 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 6/18/2024 | Approved | MICHEL ABAJAN |
| Final | 6/18/2024 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 6/18/2024 | Approved | MICHEL ABAJAN |
| HVAC-Final | 6/18/2024 | Corrections Issued | MICHEL ABAJAN |
| PLUMBING-Final | 6/18/2024 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 6/18/2024 | SGSOV Approved | MICHEL ABAJAN |
| Service/Power Release | 6/18/2024 | Not Ready for Inspection | MICHEL ABAJAN |
| Smoke Detectors | 6/18/2024 | Approved | MICHEL ABAJAN |
| Final | 7/22/2024 | Corrections Issued | MICHEL ABAJAN |
| HVAC-Final | 7/22/2024 | Approved | MICHEL ABAJAN |
| Final | 11/19/2024 | Corrections Issued | MICHEL ABAJAN |
| Final | 11/25/2024 | OK to Issue CofO | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 12/3/2024 | SGSOV Not Required | MICHEL ABAJAN |