9775 N TELFAIR AVE 91331

Certificate Information: 9775 N TELFAIR AVE 91331

Application / Permit
23010-20000-02140
Plan Check / Job No.
B23VN06661
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN NEW DETACHED Accessory dwelling unit per LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 10/4/2023
Issuing Office
Current Status
CofO Issued on 12/4/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/22/2023 APPLICANT
Assigned to Plan Check Engineer 5/25/2023 MOHAMMAD ESMAILI
Corrections Issued 5/26/2023 MOHAMMAD ESMAILI
Applicant returned to address corrections 9/21/2023 MOHAMMAD ESMAILI
Applicant returned to address corrections 9/26/2023 MOHAMMAD ESMAILI
Plan Check Approved 9/28/2023 MOHAMMAD ESMAILI
Issued 10/4/2023 APPLICANT
CofO in Progress 11/25/2024 MICHEL ABAJAN
Permit Finaled 12/4/2024 RUBEN SALAS
CofO Issued 12/4/2024 RUBEN SALAS
Permit Finaled 12/4/2024 RUBEN SALAS

Permit Application Clearance Information

ZA Case Cleared 5/30/2023 KENTON TRINH
ZI Cleared 5/30/2023 KENTON TRINH
Address approval Cleared 6/5/2023 NIKKI ZULUETA
Eng Process Fee Ord 176,300 Cleared 6/6/2023 NIKKI ZULUETA
Sewer availability Cleared 6/7/2023 NIKKI ZULUETA
Hydrant and Access approval Cleared 6/30/2023 GILBERT URREA
Low Impact Development (LID) Cleared 8/9/2023 VICTOR MENDOZA
Roof/Waste drainage to street Cleared 8/10/2023 NIKKI ZULUETA
Construction near power lines Cleared 9/11/2023 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Li,, Dacheng D; Lic. No.: NA58075       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Gas Test 10/16/2023 Approved MICHEL ABAJAN
PLUMBING-Rough 10/16/2023 Partial Approval MICHEL ABAJAN
Sewer 10/16/2023 Approved MICHEL ABAJAN
Underground Mechanical 10/16/2023 Partial Approval MICHEL ABAJAN
Footing/Foundation/Slab 10/19/2023 Approved MICHEL ABAJAN
Deputy Wood Construction 11/3/2023 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 11/6/2023 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 1/17/2024 Approved MICHEL ABAJAN
ELECTRICAL-Rough 1/17/2024 Approved MICHEL ABAJAN
Green Building Rough 1/17/2024 Approved MICHEL ABAJAN
HVAC-Rough 1/17/2024 Approved MICHEL ABAJAN
PLUMBING-Rough 1/17/2024 Approved MICHEL ABAJAN
Verify Sprinkler Sign Off 1/17/2024 Approved MICHEL ABAJAN
Insulation 1/19/2024 Approved MICHEL ABAJAN
Interior/Exterior Lathing 1/19/2024 Approved MICHEL ABAJAN
Drywall Nailing 1/24/2024 Approved MICHEL ABAJAN
Interior/Exterior Lathing 1/24/2024 Approved MICHEL ABAJAN
ELECTRICAL-Final 6/18/2024 Approved MICHEL ABAJAN
Final 6/18/2024 Corrections Issued MICHEL ABAJAN
Green Building Final 6/18/2024 Approved MICHEL ABAJAN
HVAC-Final 6/18/2024 Corrections Issued MICHEL ABAJAN
PLUMBING-Final 6/18/2024 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 6/18/2024 SGSOV Approved MICHEL ABAJAN
Service/Power Release 6/18/2024 Not Ready for Inspection MICHEL ABAJAN
Smoke Detectors 6/18/2024 Approved MICHEL ABAJAN
Final 7/22/2024 Corrections Issued MICHEL ABAJAN
HVAC-Final 7/22/2024 Approved MICHEL ABAJAN
Final 11/19/2024 Corrections Issued MICHEL ABAJAN
Final 11/25/2024 OK to Issue CofO MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 12/3/2024 SGSOV Not Required MICHEL ABAJAN