14729 W LEADWELL ST 91405

Certificate Information: 14729 W LEADWELL ST 91405

Application / Permit
23010-20000-02130
Plan Check / Job No.
B23VN06634
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN (N) DETACHED ADU PER ORDINANCE see comment
Permit Issued
Issued on 2/24/2024
Issuing Office
Current Status
CofO Issued on 2/3/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/31/2023 APPLICANT
Assigned to Plan Check Engineer 6/7/2023 MINA HABILI
Corrections Issued 6/8/2023 MINA HABILI
Plan Check Approved 2/11/2024 MINA HABILI
Issued 2/24/2024 APPLICANT
CofO in Progress 1/14/2026 VINCENT HANLEY
Permit Finaled 2/3/2026 RUBEN SALAS
CofO Issued 2/3/2026 RUBEN SALAS
Permit Finaled 2/3/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 9/19/2023 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 9/20/2023 CARLOS AGUILERA
Sewer availability Cleared 9/20/2023 CARLOS AGUILERA
Construction near power lines Cleared 12/26/2023 RIDWAN HARDY
Low Impact Development (LID) Cleared 1/12/2024 ERNEST TSE
Roof/Waste drainage to street Cleared 1/13/2024 CARLOS AGUILERA
ZA Case Cleared 1/16/2024 STEVEN WECHSLER

Contact Information

Contractor Owner-Builder       ,
Engineer Grigoryan,, Souren; Lic. No.: C93320 6506 TEESDALE AVE      NORTH HOLLYWOOD, CA 91606

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/26/2024 Approved VINCENT HANLEY
PLUMBING-Rough 7/31/2024 Partial Approval VINCENT HANLEY
Excavation/Setback/Form/Re-Bar 8/9/2024 Approved MATTHEW NELSON
Footing/Foundation/Slab 8/9/2024 Approved MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 10/3/2024 Approved VINCENT HANLEY
PLUMBING-Rough 10/3/2024 Approved VINCENT HANLEY
ELECTRICAL-Rough 11/12/2024 Corrections Issued VINCENT HANLEY
HVAC-Rough 11/12/2024 Approved VINCENT HANLEY
BUILDING-Rough-Frame 11/20/2024 Approved VINCENT HANLEY
ELECTRICAL-Rough 11/20/2024 Approved VINCENT HANLEY
Green Building Rough 11/20/2024 Approved VINCENT HANLEY
Verify Sprinkler Sign Off 11/20/2024 Not Ready for Inspection VINCENT HANLEY
Underground Mechanical 11/27/2024 Approved VINCENT HANLEY
Interior/Exterior Lathing 12/6/2024 Partial Approval VINCENT HANLEY
Shower Pan 12/27/2024 Approved VINCENT HANLEY
Insulation 1/7/2025 Corrections Issued MICHAEL CORTEZ
Insulation 1/9/2025 Approved VINCENT HANLEY
Drywall Nailing 1/17/2025 Not Ready for Inspection JOSE AVILA
Drywall Nailing 1/22/2025 Approved VINCENT HANLEY
Interior/Exterior Lathing 1/22/2025 Approved VINCENT HANLEY
Final 7/28/2025 No Access for Inspection VINCENT HANLEY
Green Building Final 7/28/2025 No Access for Inspection VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 7/28/2025 SGSOV Not Ready VINCENT HANLEY
Service/Power Release 7/28/2025 No Access for Inspection VINCENT HANLEY
Smoke Detectors 7/28/2025 No Access for Inspection VINCENT HANLEY
Final 9/16/2025 No Access for Inspection VINCENT HANLEY
Green Building Final 9/16/2025 No Access for Inspection VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 9/16/2025 SGSOV Not Ready VINCENT HANLEY
Service/Power Release 9/16/2025 No Access for Inspection VINCENT HANLEY
Smoke Detectors 9/16/2025 No Access for Inspection VINCENT HANLEY
ELECTRICAL-Final 9/30/2025 Approved VINCENT HANLEY
Final 9/30/2025 Corrections Issued VINCENT HANLEY
Green Building Final 9/30/2025 Approved VINCENT HANLEY
HVAC-Final 9/30/2025 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 9/30/2025 SGSOV Not Ready VINCENT HANLEY
Service/Power Release 9/30/2025 Approved VINCENT HANLEY
Smoke Detectors 9/30/2025 Approved VINCENT HANLEY
Final 10/28/2025 Corrections Issued VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 10/28/2025 SGSOV Approved VINCENT HANLEY
Final 1/13/2026 OK to Issue CofO VINCENT HANLEY
PLUMBING-Final 1/13/2026 Approved VINCENT HANLEY