12571 N TELFAIR AVE 91342

Certificate Information: 12571 N TELFAIR AVE 91342

Application / Permit
23010-20000-02125
Plan Check / Job No.
B23VN06613
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 2-STORY ADU OF 1,196 SQ. FT.WITH AND 92 SQFT COVERED BALCONY ATTACHED 2-CAR GARAGE GARAGE OF 396 SQ. FT. PER LAMC 12.22 A.33(c)(d)
Permit Issued
Issued on 1/22/2024
Issuing Office
Valley
Current Status
CofO Issued on 12/2/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/19/2023 APPLICANT
Assigned to Plan Check Engineer 6/1/2023 PETER MOSESIAN
Corrections Issued 6/7/2023 PETER MOSESIAN
Quality Review Completed 6/9/2023 OMID HEDAYAT
Building Plans Picked Up 6/15/2023 APPLICANT
Plan Check Approved 10/4/2023 PETER MOSESIAN
Issued 1/22/2024 APPLICANT
CofO in Progress 11/17/2025 KEVIN BERBERYAN
Permit Finaled 12/2/2025 RUBEN SALAS
CofO Issued 12/2/2025 RUBEN SALAS
Permit Finaled 12/2/2025 RUBEN SALAS

Permit Application Clearance Information

ZA Case Cleared 6/14/2023 ALEX VELA
ZA Case Cleared 6/14/2023 ALEX VELA
ZA Case Cleared 6/14/2023 ALEX VELA
Address approval Cleared 6/17/2023 COLIN LOREDO
Hydrant and Access approval Cleared 7/26/2023 JOHN CONNEALLY
Eng Process Fee Ord 176,300 Cleared 9/18/2023 COLIN LOREDO
Sewer availability Cleared 9/18/2023 COLIN LOREDO
Low Impact Development (LID) Cleared 9/21/2023 ROGELIO CORTES
Roof/Waste drainage to street Cleared 9/23/2023 COLIN LOREDO

Contact Information

Contractor Owner-Builder       ,
Engineer Van, Valkenburg, John; Lic. No.: C74939 13259 KISMET AVE      SYLMAR, CA 91342

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/14/2024 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 3/20/2024 Partial Approval KEVIN BERBERYAN
Footing/Foundation/Slab 3/20/2024 Approved KEVIN BERBERYAN
Green Building Rough 3/20/2024 Not Ready for Inspection KEVIN BERBERYAN
PLUMBING-Rough 3/20/2024 Partial Approval KEVIN BERBERYAN
Verify Sprinkler Sign Off 3/20/2024 Approved KEVIN BERBERYAN
Floor/Roof Diaphrgm/Shear Wall 3/22/2024 Partial Approval KEVIN BERBERYAN
Floor/Roof Diaphrgm/Shear Wall 4/8/2024 Partial Approval KEVIN BERBERYAN
Green Building Rough 4/8/2024 Not Ready for Inspection KEVIN BERBERYAN
Deputy Drilled-In Anchors 6/21/2024 Conditional Approval ROBERT GOLD
Excavation/Setback/Form/Re-Bar 6/21/2024 Approved KEVIN BERBERYAN
BUILDING-Rough-Frame 10/11/2024 Corrections Issued KEVIN BERBERYAN
ELECTRICAL-Rough 10/11/2024 Corrections Issued KEVIN BERBERYAN
Green Building Rough 10/11/2024 Not Ready for Inspection KEVIN BERBERYAN
HVAC-Rough 10/11/2024 Approved KEVIN BERBERYAN
PLUMBING-Rough 10/11/2024 Corrections Issued KEVIN BERBERYAN
Interior/Exterior Lathing 11/7/2024 Approved KEVIN BERBERYAN
Shower Pan 11/7/2024 Approved KEVIN BERBERYAN
BUILDING-Rough-Frame 11/19/2024 Conditional Approval KEVIN BERBERYAN
ELECTRICAL-Rough 11/19/2024 Approved KEVIN BERBERYAN
Green Building Rough 11/19/2024 Approved KEVIN BERBERYAN
Interior/Exterior Lathing 11/19/2024 Approved KEVIN BERBERYAN
PLUMBING-Rough 11/19/2024 Approved KEVIN BERBERYAN
Insulation 11/26/2024 Conditional Approval KEVIN BERBERYAN
Drywall Nailing 12/6/2024 Not Ready for Inspection MICHAEL CORTEZ
Drywall Nailing 12/17/2024 Approved KEVIN BERBERYAN
Excavation/Setback/Form/Re-Bar 2/10/2025 Approved MISAEL ESPARZA
Underground Mechanical 8/19/2025 Not Ready for Inspection KEVIN BERBERYAN
Sewer 8/20/2025 Approved KEVIN BERBERYAN
Underground Mechanical 8/25/2025 Approved KEVIN BERBERYAN
BUILDING-Rough-Frame 10/24/2025 Approved KEVIN BERBERYAN
Final 10/24/2025 Corrections Issued KEVIN BERBERYAN
Green Building Final 10/24/2025 Not Ready for Inspection KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 10/24/2025 SGSOV No Gas KEVIN BERBERYAN
Service/Power Release 10/24/2025 Not Ready for Inspection KEVIN BERBERYAN
Smoke Detectors 10/24/2025 Approved KEVIN BERBERYAN
Final 10/31/2025 Corrections Issued KEVIN BERBERYAN
Green Building Final 10/31/2025 Approved KEVIN BERBERYAN
Service/Power Release 10/31/2025 Not Ready for Inspection KEVIN BERBERYAN
Final 11/5/2025 Not Ready for Inspection KEVIN BERBERYAN
Final 11/7/2025 OK to Issue CofO KEVIN BERBERYAN
Service/Power Release 11/7/2025 Approved KEVIN BERBERYAN