7911 N ROYER AVE 91304
Certificate Information: 7911 N ROYER AVE 91304
- Application / Permit
- 23010-20000-02119
- Plan Check / Job No.
- B23VN06575
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New two stories irregular shaped 18' 10" x 35' 2 3/8" ADU per LAMC 12.22 A.33 (c)-(d).
- Permit Issued
- Issued on 8/13/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/8/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/19/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/25/2023 | NAREG ATARIAN |
| Corrections Issued | 5/26/2023 | NAREG ATARIAN |
| Quality Review Completed | 5/31/2023 | OMID HEDAYAT |
| Building Plans Picked Up | 5/31/2023 | APPLICANT |
| Applicant returned to address corrections | 4/8/2024 | NAREG ATARIAN |
| Plan Check Approved | 4/18/2024 | NAREG ATARIAN |
| Issued | 8/13/2024 | APPLICANT |
| CofO in Progress | 3/23/2026 | JEFFREY HARTLINE |
| Permit Finaled | 4/8/2026 | JOHN JANSON |
| CofO Issued | 4/8/2026 | JOHN JANSON |
| Permit Finaled | 4/8/2026 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 6/9/2023 | LEE GUILBEAUX |
| Construction near power lines | Cleared | 11/3/2023 | RIDWAN HARDY |
| Construction within easement | Cleared | 11/3/2023 | RIDWAN HARDY |
| Low Impact Development (LID) | Cleared | 3/25/2024 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 3/30/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 4/1/2024 | LEE GUILBEAUX |
| Sewer availability | Cleared | 4/1/2024 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 4/1/2024 | LEE GUILBEAUX |
Contact Information
| Architect | Hefner,, Charles David; Lic. No.: C23963 | 6320 VAN NUYS BOULEVARD #225 VAN NUYS, CA 91401 |
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/15/2024 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 8/15/2024 | Partial Approval | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 8/29/2024 | Partial Approval | CHRIS CHRISTENSEN |
| Green Building Rough | 8/29/2024 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Verify Sprinkler Sign Off | 8/29/2024 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 9/16/2024 | Partial Approval | JEFFREY HARTLINE |
| ELECTRICAL-Final | 6/12/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| ELECTRICAL-Rough | 6/12/2025 | Corrections Issued | JEFFREY HARTLINE |
| Floor/Roof Diaphrgm/Shear Wall | 6/12/2025 | Partial Approval | JEFFREY HARTLINE |
| Interior/Exterior Lathing | 6/12/2025 | Partial Approval | JEFFREY HARTLINE |
| PLUMBING-Final | 6/12/2025 | Not Ready for Inspection | JEFFREY HARTLINE |
| PLUMBING-Rough | 6/12/2025 | Approved | JEFFREY HARTLINE |
| BUILDING-Rough-Frame | 10/24/2025 | Approved | JEFFREY HARTLINE |
| ELECTRICAL-Rough | 10/24/2025 | Approved | JEFFREY HARTLINE |
| Green Building Rough | 10/24/2025 | Approved | JEFFREY HARTLINE |
| HVAC-Rough | 10/24/2025 | Approved | JEFFREY HARTLINE |
| Sewer | 10/24/2025 | Approved | JEFFREY HARTLINE |
| Underground Mechanical | 10/24/2025 | Approved | JEFFREY HARTLINE |
| Insulation | 10/31/2025 | Approved | JEFFREY HARTLINE |
| Shower Pan | 10/31/2025 | Approved | JEFFREY HARTLINE |
| Drywall Nailing | 11/4/2025 | Approved | JEFFREY HARTLINE |
| Interior/Exterior Lathing | 11/4/2025 | Partial Approval | JEFFREY HARTLINE |
| ELECTRICAL-Final | 3/9/2026 | Not Ready for Inspection | JEFFREY HARTLINE |
| Final | 3/9/2026 | Corrections Issued | JEFFREY HARTLINE |
| Green Building Final | 3/9/2026 | Approved | JEFFREY HARTLINE |
| HVAC-Final | 3/9/2026 | Not Ready for Inspection | JEFFREY HARTLINE |
| PLUMBING-Final | 3/9/2026 | Approved | JEFFREY HARTLINE |
| SGSOV-Seismic Gas S/O Valve | 3/9/2026 | SGSOV Approved | JEFFREY HARTLINE |
| Service/Power Release | 3/9/2026 | Not Ready for Inspection | JEFFREY HARTLINE |
| Smoke Detectors | 3/9/2026 | Approved | JEFFREY HARTLINE |
| ELECTRICAL-Final | 3/18/2026 | Approved | JEFFREY HARTLINE |
| Final | 3/18/2026 | OK to Issue CofO | JEFFREY HARTLINE |
| HVAC-Final | 3/18/2026 | Approved | JEFFREY HARTLINE |
| Service/Power Release | 3/18/2026 | Approved | JEFFREY HARTLINE |