7302 N LUBAO AVE 91306
Certificate Information: 7302 N LUBAO AVE 91306
- Application / Permit
- 23010-20000-02110
- Plan Check / Job No.
- B23VN06558
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: (N) 1-STORY ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(B) and applicable part of LAMC 12.22 A.33 (c)-(d), (g)
- Permit Issued
- Issued on 7/28/2023
- Issuing Office
- Current Status
- CofO Corrected on 6/17/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/18/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/1/2023 | DANIEL YIP |
| Corrections Issued | 6/5/2023 | DANIEL YIP |
| Quality Review Completed | 6/6/2023 | GARO TELMI |
| Plan Check Approved | 7/25/2023 | DANIEL YIP |
| Issued | 7/28/2023 | APPLICANT |
| CofO in Progress | 3/28/2024 | ALEXANDER HANDY |
| CofO Issued-Status Void | 4/23/2024 | JOHN JANSON |
| Permit Finaled-Status Void | 4/23/2024 | JOHN JANSON |
| Re-Activate Permit | 5/7/2024 | JOHN JANSON |
| CofO in Progress | 5/7/2024 | JOHN JANSON |
| CofO in Progress | 5/29/2024 | HORACE FULTZ |
| CofO in Progress | 6/17/2024 | ALEXANDER HANDY |
| Permit Finaled | 6/17/2024 | JOHN JANSON |
| CofO Corrected | 6/17/2024 | JOHN JANSON |
| Permit Finaled | 6/17/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 6/8/2023 | FERNANDO GIL |
| Construction near power lines | Cleared | 6/26/2023 | WALTER RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/27/2023 | FERNANDO GIL |
| Sewer availability | Cleared | 6/27/2023 | FERNANDO GIL |
| Low Impact Development (LID) | Cleared | 7/6/2023 | TOMMY YIN |
| Roof/Waste drainage to street | Cleared | 7/12/2023 | FERNANDO GIL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/30/2023 | Conditional Approval | ALEXANDER HANDY |
| Underground Mechanical | 8/30/2023 | Not Ready for Inspection | ALEXANDER HANDY |
| Footing/Foundation/Slab | 9/6/2023 | Approved | ALEXANDER HANDY |
| Floor/Roof Diaphrgm/Shear Wall | 9/28/2023 | Partial Approval | HENRY KIM |
| ELECTRICAL-Rough | 10/13/2023 | Not Ready for Inspection | ALEXANDER HANDY |
| HVAC-Rough | 10/13/2023 | Approved | ALEXANDER HANDY |
| PLUMBING-Rough | 10/13/2023 | Approved | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 11/2/2023 | Approved | JOHN KIDWELL |
| ELECTRICAL-Rough | 11/2/2023 | Approved | JOHN KIDWELL |
| Green Building Rough | 11/2/2023 | Approved | JOHN KIDWELL |
| Verify Sprinkler Sign Off | 11/2/2023 | Approved | JOHN KIDWELL |
| Insulation | 11/14/2023 | Conditional Approval | ALEXANDER HANDY |
| Interior/Exterior Lathing | 11/14/2023 | Partial Approval | ALEXANDER HANDY |
| Drywall Nailing | 11/22/2023 | Approved | ALEXANDER HANDY |
| Interior/Exterior Lathing | 11/22/2023 | Approved | ALEXANDER HANDY |
| Sewer | 11/22/2023 | Approved | ALEXANDER HANDY |
| ELECTRICAL-Final | 2/28/2024 | Not Ready for Inspection | ALEXANDER HANDY |
| Final | 2/28/2024 | Corrections Issued | ALEXANDER HANDY |
| Green Building Final | 2/28/2024 | Approved | ALEXANDER HANDY |
| HVAC-Final | 2/28/2024 | Approved | ALEXANDER HANDY |
| PLUMBING-Final | 2/28/2024 | Not Ready for Inspection | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 2/28/2024 | SGSOV Approved | ALEXANDER HANDY |
| Service/Power Release | 2/28/2024 | Approved | ALEXANDER HANDY |
| Smoke Detectors | 2/28/2024 | Approved | ALEXANDER HANDY |
| ELECTRICAL-Final | 3/28/2024 | Approved | ALEXANDER HANDY |
| Final | 3/28/2024 | OK to Issue CofO | ALEXANDER HANDY |
| PLUMBING-Final | 3/28/2024 | Approved | ALEXANDER HANDY |
| Special/Order Compliance | 5/8/2024 | Corrections Issued | ALEXANDER HANDY |