15300 W ROMAR ST 91345

Certificate Information: 15300 W ROMAR ST 91345

Application / Permit
23010-20000-02106
Plan Check / Job No.
B23VN06532
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c)-(d). WORK PER WFPP.
Permit Issued
Issued on 3/23/2024
Issuing Office
Current Status
CofO Issued on 12/18/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/20/2023 APPLICANT
Assigned to Plan Check Engineer 5/24/2023 ROSENDO MEDINA
Corrections Issued 5/25/2023 ROSENDO MEDINA
Plan Check Approved 2/5/2024 ROSENDO MEDINA
Issued 3/23/2024 APPLICANT
CofO in Progress 12/3/2024 JENNIFER RABUCHIN
CofO Issued 12/18/2024 RUBEN SALAS
Permit Finaled 12/18/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 6/1/2023 RYAN KIM
Miscellaneous Cleared 6/1/2023 RYAN KIM
Eng Process Fee Ord 176,300 Cleared 6/12/2023 RYAN KIM
Sewer availability Cleared 6/12/2023 RYAN KIM
Construction near power lines Cleared 9/18/2023 RIDWAN HARDY
Low Impact Development (LID) Cleared 1/16/2024 MELINEH AGHAKHABIAN
Roof/Waste drainage to street Cleared 1/19/2024 JOHN LIN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/2/2024 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 7/10/2024 Partial Approval JENNIFER RABUCHIN
Insulation 7/10/2024 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 7/10/2024 Partial Approval JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 7/12/2024 Partial Approval MATTHEW NELSON
Insulation 7/12/2024 Not Ready for Inspection MATTHEW NELSON
ELECTRICAL-Rough 8/6/2024 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 8/6/2024 Approved JENNIFER RABUCHIN
HVAC-Rough 8/6/2024 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 8/6/2024 Corrections Issued JENNIFER RABUCHIN
Wood Frame 8/6/2024 Approved JENNIFER RABUCHIN
Insulation 8/13/2024 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 8/13/2024 Partial Approval JENNIFER RABUCHIN
Drywall Nailing 8/21/2024 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 8/21/2024 Approved JENNIFER RABUCHIN
Shower Pan 8/21/2024 Approved JENNIFER RABUCHIN
Underground Mechanical 9/4/2024 Approved LOUIS ESCOTO
BUILDING-Rough-Frame 11/5/2024 Partial Inspection JENNIFER RABUCHIN
Final 11/5/2024 Not Ready for Inspection JENNIFER RABUCHIN
Green Building Final 11/5/2024 Approved JENNIFER RABUCHIN
Green Building Rough 11/5/2024 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 11/5/2024 SGSOV Not Ready JENNIFER RABUCHIN
Service/Power Release 11/5/2024 Not Ready for Inspection JENNIFER RABUCHIN
Smoke Detectors 11/5/2024 Not Ready for Inspection JENNIFER RABUCHIN
Verify Sprinkler Sign Off 11/5/2024 Approved JENNIFER RABUCHIN
Final 11/6/2024 Corrections Issued JENNIFER RABUCHIN
BUILDING-Rough-Frame 11/25/2024 Approved KEVIN BERBERYAN
Final 11/25/2024 Partial Approval KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 11/25/2024 SGSOV Not Required KEVIN BERBERYAN
Service/Power Release 11/25/2024 Approved KEVIN BERBERYAN
Smoke Detectors 11/25/2024 Approved KEVIN BERBERYAN
Service/Power Release 11/26/2024 Conditional Approval JENNIFER RABUCHIN
ELECTRICAL-Final 12/4/2024 Approved JENNIFER RABUCHIN
Final 12/4/2024 OK to Issue CofO JENNIFER RABUCHIN
HVAC-Final 12/4/2024 Approved JENNIFER RABUCHIN
PLUMBING-Final 12/4/2024 Approved JENNIFER RABUCHIN