10622 N FERNGLEN AVE 91042
Certificate Information: 10622 N FERNGLEN AVE 91042
- Application / Permit
- 23010-20000-02096
- Plan Check / Job No.
- B23VN06500
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan NEW DETACHED 858 SQ.FT SFD PER SB9 2 UNIT DEVELOPMENT PER CA GOVT CODE 65852.21
- Permit Issued
- Issued on 12/18/2023
- Issuing Office
- Current Status
- CofO Corrected on 8/27/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/18/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/1/2023 | SUNMIN LEE |
| Corrections Issued | 6/5/2023 | SUNMIN LEE |
| Quality Review Completed | 6/13/2023 | GARO TELMI |
| Applicant returned to address corrections | 11/29/2023 | SUNMIN LEE |
| Plan Check Approved | 12/8/2023 | SUNMIN LEE |
| Issued | 12/18/2023 | APPLICANT |
| CofO in Progress | 7/16/2024 | WILLIAM WREN |
| CofO Issued-Status Void | 7/17/2024 | RUBEN SALAS |
| Permit Finaled-Status Void | 7/17/2024 | RUBEN SALAS |
| Re-Activate Permit | 8/27/2024 | DANIEL ORRANTE |
| CofO Corrected | 8/27/2024 | DANIEL ORRANTE |
| Permit Finaled | 8/27/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 6/30/2023 | TAL SHEMEN |
| Eng Process Fee Ord 176,300 | Cleared | 7/31/2023 | TAL SHEMEN |
| Sewer availability | Cleared | 7/31/2023 | TAL SHEMEN |
| Low Impact Development (LID) | Cleared | 11/3/2023 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 11/6/2023 | TAL SHEMEN |
| Construction near power lines | Cleared | 11/17/2023 | TINA MIRANDA |
| GPI Written Notices | Cleared | 11/29/2023 | SUNMIN LEE |
| Grading Pre-Inspection | Cleared | 11/29/2023 | SUNMIN LEE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Baraty,, Patrick; Lic. No.: S5900 | 450 NORTH BRAND BLVD STE 600 GLENDALE, CA 91203 |
| Engineer | Molai,, Mohamad Ali; Lic. No.: L9192 | 24308 BURBANK BLVD WOODLAND HILLS, CA 91367 |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/4/2024 | Corrections Issued | THOMAS FINNILA |
| Excavation/Setback/Form/Re-Bar | 1/5/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Pre-Inspection | 1/12/2024 | Corrections Issued | WILLIAM WREN |
| Footing/Foundation/Slab | 1/16/2024 | Approved | WILLIAM WREN |
| PLUMBING-Rough | 1/26/2024 | Corrections Issued | CRAIG DAVIS |
| Wood Frame | 1/26/2024 | Partial Approval | CRAIG DAVIS |
| PLUMBING-Rough | 1/30/2024 | Not Ready for Inspection | CRAIG DAVIS |
| Wood Frame | 1/30/2024 | Not Ready for Inspection | CRAIG DAVIS |
| PLUMBING-Rough | 1/31/2024 | Partial Approval | CRAIG DAVIS |
| BUILDING-Rough-Frame | 2/15/2024 | Not Ready for Inspection | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 2/15/2024 | Partial Approval | WILLIAM WREN |
| Green Building Rough | 2/15/2024 | Not Ready for Inspection | WILLIAM WREN |
| Verify Sprinkler Sign Off | 2/15/2024 | Not Ready for Inspection | WILLIAM WREN |
| Wood Frame | 2/20/2024 | Not Ready for Inspection | WILLIAM WREN |
| HVAC-Rough | 2/23/2024 | Approved | WILLIAM WREN |
| PLUMBING-Rough | 2/23/2024 | Approved | WILLIAM WREN |
| ELECTRICAL-Rough | 3/7/2024 | Corrections Issued | WILLIAM WREN |
| BUILDING-Rough-Frame | 3/8/2024 | Approved | WILLIAM WREN |
| ELECTRICAL-Rough | 3/8/2024 | Approved | WILLIAM WREN |
| Green Building Rough | 3/8/2024 | Approved | WILLIAM WREN |
| Verify Sprinkler Sign Off | 3/8/2024 | Approved | WILLIAM WREN |
| Insulation | 3/11/2024 | Conditional Approval | WILLIAM WREN |
| Drywall Nailing | 3/19/2024 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 3/19/2024 | Approved | WILLIAM WREN |
| Shower Pan | 3/19/2024 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 3/29/2024 | Partial Approval | GREGG CUMMINGS |
| Sewer | 5/1/2024 | Approved | WILLIAM WREN |
| Underground Mechanical | 5/1/2024 | Approved | WILLIAM WREN |
| ELECTRICAL-Final | 6/25/2024 | Not Ready for Inspection | WILLIAM WREN |
| Pre-Inspection | 6/25/2024 | Partial Inspection | WILLIAM WREN |
| Final | 7/2/2024 | Corrections Issued | WILLIAM WREN |
| Green Building Final | 7/2/2024 | Not Ready for Inspection | WILLIAM WREN |
| SGSOV-Seismic Gas S/O Valve | 7/2/2024 | SGSOV Not Required | WILLIAM WREN |
| Service/Power Release | 7/2/2024 | Not Ready for Inspection | WILLIAM WREN |
| Smoke Detectors | 7/2/2024 | Approved | WILLIAM WREN |
| Final | 7/8/2024 | OK to Issue CofO | WILLIAM WREN |
| Green Building Final | 7/8/2024 | Approved | WILLIAM WREN |
| Service/Power Release | 7/8/2024 | Approved | WILLIAM WREN |