6857 N HINDS AVE 1-2 91605
Certificate Information: 6857 N HINDS AVE 1-2 91605
- Application / Permit
- 23010-20000-02092
- Plan Check / Job No.
- B23VN06481
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- ePLAN. (N) 3 STORY DUPLEX (42'0" X 24' 0", FRONT). NFPA 13D FIRE SPRINKLER SYSTEM IS REQUIRED
- Permit Issued
- Issued on 4/2/2024
- Issuing Office
- Current Status
- CofO Issued on 3/17/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/18/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/1/2023 | NGHI SU |
| Corrections Issued | 6/9/2023 | NGHI SU |
| Quality Review Completed | 6/20/2023 | TU HUA |
| Applicant returned to address corrections | 3/14/2024 | NGHI SU |
| Plan Check Approved | 3/20/2024 | NGHI SU |
| Issued | 4/2/2024 | APPLICANT |
| CofO in Progress | 3/2/2026 | ROBERTO PALACIOS-LOPEZ |
| CofO Issued | 3/17/2026 | RUBEN SALAS |
| Permit Finaled | 3/17/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 7/3/2023 | NIKKI ZULUETA |
| Eng Process Fee Ord 176,300 | Cleared | 7/5/2023 | NIKKI ZULUETA |
| Sewer availability | Cleared | 7/10/2023 | NIKKI ZULUETA |
| Construction near power lines | Cleared | 8/21/2023 | RIDWAN HARDY |
| Hydrant and Access approval | Cleared | 10/10/2023 | LAVEON RIDER |
| Frnt yard landscape/Water mgmt | Cleared | 1/4/2024 | RYAN LY |
| Opn space landscape/Water mgmt | Cleared | 1/4/2024 | RYAN LY |
| SB8 RUD | Cleared | 2/13/2024 | RICHARD TRUONG |
| ZI | Cleared | 2/29/2024 | RYAN LY |
| Low Impact Development (LID) | Cleared | 3/4/2024 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 3/5/2024 | CARLOS RAMIREZ |
Contact Information
| Contractor | Pacific Coast Builders; Lic. No.: 834794-B | 9277OTTO ST DOWNEY, CA 90240 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/4/2024 | Partial Approval | JOHN HAYES |
| Underground Mechanical | 4/4/2024 | Approved | JOHN HAYES |
| Footing/Foundation/Slab | 4/9/2024 | Approved | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 4/22/2024 | Partial Approval | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 5/1/2024 | Corrections Issued | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 5/6/2024 | Partial Approval | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 6/24/2024 | Corrections Issued | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 7/2/2024 | Corrections Issued | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 7/11/2024 | Partial Approval | JOSE AVILA |
| ELECTRICAL-Rough | 8/14/2024 | Corrections Issued | JOSE AVILA |
| PLUMBING-Rough | 8/14/2024 | Corrections Issued | JOSE AVILA |
| HVAC-Rough | 8/21/2024 | Approved | JOSE AVILA |
| PLUMBING-Rough | 8/21/2024 | Not Ready for Inspection | JOSE AVILA |
| PLUMBING-Rough | 8/29/2024 | Approved | JOSE AVILA |
| Verify Sprinkler Sign Off | 8/29/2024 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 9/10/2024 | No Access for Inspection | JOSE AVILA |
| BUILDING-Rough-Frame | 3/28/2025 | Approved | JOSE AVILA |
| ELECTRICAL-Rough | 3/28/2025 | Approved | JOSE AVILA |
| Green Building Rough | 3/28/2025 | Approved | JOSE AVILA |
| Insulation | 3/28/2025 | Approved | JOSE AVILA |
| Drywall Nailing | 4/10/2025 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 4/10/2025 | Approved | JOSE AVILA |
| Shower Pan | 5/12/2025 | Approved | JOSE AVILA |
| Sewer | 6/25/2025 | Approved | JOSE AVILA |
| Underground Mechanical | 6/25/2025 | Partial Approval | JOSE AVILA |
| Underground Mechanical | 7/14/2025 | Approved | JOSE AVILA |
| HVAC-Final | 2/12/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Final | 2/17/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Final | 2/18/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 2/18/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Final | 2/18/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 2/18/2026 | SGSOV Not Required | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 2/18/2026 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 2/18/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Final | 2/24/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 2/24/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 2/24/2026 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Verify Sprinkler Sign Off | 2/24/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Final | 2/27/2026 | Partial Inspection | ROBERTO PALACIOS-LOPEZ |
| Final | 2/27/2026 | OK to Issue CofO | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 2/27/2026 | Approved | ROBERTO PALACIOS-LOPEZ |