7620 N ARCOLA AVE 91352
Certificate Information: 7620 N ARCOLA AVE 91352
- Application / Permit
- 23010-20000-02091
- Plan Check / Job No.
- B23VN05779
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- *EPLAN* NEW 2-STORY SFD WTIH ATTACHED 2-CAR GARAGE. NFPA 13D
- Permit Issued
- Issued on 12/26/2023
- Issuing Office
- Current Status
- CofO Issued on 8/19/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/4/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/11/2023 | VIVIAN LAO |
| Corrections Issued | 5/18/2023 | VIVIAN LAO |
| Quality Review Completed | 5/23/2023 | GARO TELMI |
| Applicant returned to address corrections | 11/14/2023 | VIVIAN LAO |
| Plan Check Approved | 12/21/2023 | VIVIAN LAO |
| Issued | 12/26/2023 | APPLICANT |
| CofO in Progress | 7/12/2025 | DAVID ANDERSON |
| Permit Finaled | 8/19/2025 | RUBEN SALAS |
| CofO Issued | 8/19/2025 | RUBEN SALAS |
| Permit Finaled | 8/19/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 7/17/2023 | DAGOVERTO GUERRERO |
| Certificate of Compliance | Cleared | 7/18/2023 | ASHLEY RODARTE |
| Permit | Cleared | 7/18/2023 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 7/19/2023 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 7/19/2023 | DAGOVERTO GUERRERO |
| Hydrant and Access approval | Cleared | 10/26/2023 | JOHN CONNEALLY |
| Low Impact Development (LID) | Cleared | 11/8/2023 | TOMMY YIN |
| Roof/Waste drainage to street | Cleared | 11/14/2023 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Baraty,, Patrick; Lic. No.: S5900 | 450 NORTH BRAND BLVD STE 600 GLENDALE, CA 91203 |
Inspector Information
| DAVID ANDERSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/23/2024 | Corrections Issued | DAVID ANDERSON |
| BUILDING-Rough-Frame | 1/25/2024 | Not Ready for Inspection | DAVID ANDERSON |
| Green Building Rough | 1/25/2024 | Not Ready for Inspection | DAVID ANDERSON |
| PLUMBING-Rough | 1/25/2024 | Partial Approval | DAVID ANDERSON |
| Verify Sprinkler Sign Off | 1/25/2024 | Not Ready for Inspection | DAVID ANDERSON |
| Footing/Foundation/Slab | 1/29/2024 | Approved | DAVID ANDERSON |
| Special/Order Compliance | 1/29/2024 | Corrections Issued | DAVID ANDERSON |
| BUILDING-Rough-Frame | 2/13/2024 | Partial Approval | DAVID ANDERSON |
| Green Building Rough | 2/13/2024 | Not Ready for Inspection | DAVID ANDERSON |
| PLUMBING-Rough | 2/13/2024 | Partial Approval | DAVID ANDERSON |
| Verify Sprinkler Sign Off | 2/13/2024 | Corrections Issued | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 2/16/2024 | Approved | DAVID ANDERSON |
| Pre-Inspection | 2/16/2024 | Approved | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/4/2024 | Partial Approval | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/22/2024 | Partial Approval | DAVID ANDERSON |
| BUILDING-Rough-Frame | 4/19/2024 | Corrections Issued | DAVID ANDERSON |
| ELECTRICAL-Rough | 4/19/2024 | Approved | DAVID ANDERSON |
| Green Building Rough | 4/19/2024 | Approved | DAVID ANDERSON |
| HVAC-Rough | 4/19/2024 | Corrections Issued | DAVID ANDERSON |
| PLUMBING-Rough | 4/19/2024 | Corrections Issued | DAVID ANDERSON |
| Verify Sprinkler Sign Off | 4/19/2024 | Not Ready for Inspection | DAVID ANDERSON |
| BUILDING-Rough-Frame | 5/17/2024 | Approved | DAVID ANDERSON |
| Deputy Wood Construction | 5/17/2024 | Conditional Approval | DAVID MATSON |
| HVAC-Rough | 5/17/2024 | Approved | DAVID ANDERSON |
| PLUMBING-Rough | 5/17/2024 | Approved | DAVID ANDERSON |
| Verify Sprinkler Sign Off | 5/17/2024 | Approved | DAVID ANDERSON |
| Insulation | 5/28/2024 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 5/28/2024 | Approved | DAVID ANDERSON |
| Drywall Nailing | 6/4/2024 | Approved | GREGG CUMMINGS |
| Shower Pan | 6/18/2024 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 7/15/2024 | Approved | DAVID ANDERSON |
| Underground Mechanical | 6/4/2025 | Approved | DAVID ANDERSON |
| Final | 7/8/2025 | Corrections Issued | DAVID ANDERSON |
| Green Building Final | 7/8/2025 | Not Ready for Inspection | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 7/8/2025 | SGSOV Approved | DAVID ANDERSON |
| Service/Power Release | 7/8/2025 | Not Ready for Inspection | DAVID ANDERSON |
| Smoke Detectors | 7/8/2025 | Approved | DAVID ANDERSON |
| Final | 7/11/2025 | OK to Issue CofO | DAVID ANDERSON |
| Green Building Final | 7/11/2025 | Approved | DAVID ANDERSON |
| Service/Power Release | 7/11/2025 | Approved | DAVID ANDERSON |