10914 N DANUBE AVE 91344

Certificate Information: 10914 N DANUBE AVE 91344

Application / Permit
23010-20000-02075
Plan Check / Job No.
B23VN06418
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 1-STORY DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c)(d) W/ ROOF TRUSS
Permit Issued
Issued on 8/29/2023
Issuing Office
Current Status
CofO Issued on 3/29/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/17/2023 APPLICANT
Assigned to Plan Check Engineer 6/1/2023 NILOOFAR MEHRAIN
Corrections Issued 6/3/2023 NILOOFAR MEHRAIN
Quality Review Completed 6/6/2023 STEVEN KIM
Plan Check Approved 8/29/2023 NILOOFAR MEHRAIN
Issued 8/29/2023 APPLICANT
CofO in Progress 3/14/2024 JAVIER RAMOS JR
Permit Finaled 3/29/2024 DANIEL ORRANTE
CofO Issued 3/29/2024 DANIEL ORRANTE
Permit Finaled 3/29/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 6/10/2023 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 6/14/2023 CARLOS AGUILERA
Sewer availability Cleared 6/14/2023 CARLOS AGUILERA
Hydrant and Access approval Cleared 7/12/2023 JOHN CONNEALLY
Low Impact Development (LID) Cleared 8/7/2023 SHAHIN KHAZEY
Construction near power lines Cleared 8/14/2023 RIDWAN HARDY
Construction within easement Cleared 8/14/2023 RIDWAN HARDY
Roof/Waste drainage to street Cleared 8/21/2023 CARLOS AGUILERA

Contact Information

Architect Dembsky,, Amit; Lic. No.: C30383 5739 KANAN ROAD # 133      AGOURA HILLS, CA 91301
Contractor Ha My Design, Inc; Lic. No.: 999603-B       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/14/2023 Corrections Issued MICHEL ABAJAN
Footing/Foundation/Slab 9/14/2023 Not Ready for Inspection MICHEL ABAJAN
PLUMBING-Rough 9/14/2023 Not Ready for Inspection MICHEL ABAJAN
Footing/Foundation/Slab 9/19/2023 Approved JAVIER RAMOS JR
Sewer 9/19/2023 Approved JAVIER RAMOS JR
Underground Mechanical 9/19/2023 Partial Approval JAVIER RAMOS JR
PLUMBING-Rough 9/21/2023 Not Ready for Inspection JAVIER RAMOS JR
BUILDING-Rough-Frame 9/27/2023 Partial Approval JAVIER RAMOS JR
Insulation 9/27/2023 Partial Approval JAVIER RAMOS JR
PLUMBING-Rough 9/27/2023 Partial Approval JAVIER RAMOS JR
Verify Sprinkler Sign Off 9/27/2023 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 10/2/2023 Partial Approval JAVIER RAMOS JR
BUILDING-Rough-Frame 10/16/2023 Partial Inspection JAVIER RAMOS JR
ELECTRICAL-Rough 10/16/2023 Corrections Issued JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 10/16/2023 Corrections Issued JAVIER RAMOS JR
Interior/Exterior Lathing 10/26/2023 Partial Approval ROBERT GOLD
BUILDING-Rough-Frame 10/27/2023 Corrections Issued MICHEL ABAJAN
ELECTRICAL-Rough 10/27/2023 Approved MICHEL ABAJAN
Green Building Rough 10/27/2023 Not Ready for Inspection MICHEL ABAJAN
HVAC-Rough 10/27/2023 Approved MICHEL ABAJAN
MERV13>=Rough 10/27/2023 Approved MICHEL ABAJAN
PLUMBING-Rough 10/27/2023 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 11/2/2023 Partial Approval JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 11/2/2023 Approved JAVIER RAMOS JR
Green Building Final 11/2/2023 Approved JAVIER RAMOS JR
Shower Pan 11/2/2023 Approved JAVIER RAMOS JR
Green Building Rough 11/6/2023 Approved JAVIER RAMOS JR
Insulation 11/6/2023 Corrections Issued JAVIER RAMOS JR
BUILDING-Rough-Frame 11/15/2023 Approved JAVIER RAMOS JR
Drywall Nailing 11/15/2023 Approved JAVIER RAMOS JR
Insulation 11/15/2023 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 11/15/2023 Approved JAVIER RAMOS JR
ELECTRICAL-Final 2/1/2024 Not Ready for Inspection JAVIER RAMOS JR
Final 2/1/2024 Corrections Issued JAVIER RAMOS JR
HVAC-Final 2/1/2024 Approved JAVIER RAMOS JR
MERV13>=Final 2/1/2024 Approved JAVIER RAMOS JR
PLUMBING-Final 2/1/2024 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 2/1/2024 SGSOV Not Required JAVIER RAMOS JR
Service/Power Release 2/1/2024 Not Ready for Inspection JAVIER RAMOS JR
Smoke Detectors 2/1/2024 Approved JAVIER RAMOS JR
ELECTRICAL-Final 2/21/2024 Approved JAVIER RAMOS JR
Final 2/21/2024 Not Ready for Inspection JAVIER RAMOS JR
PLUMBING-Final 2/21/2024 Approved JAVIER RAMOS JR
Deputy Wood Construction 3/13/2024 Approved JAVIER RAMOS JR
Final 3/13/2024 OK to Issue CofO JAVIER RAMOS JR
Service/Power Release 3/13/2024 Approved JAVIER RAMOS JR