2938 S TILDEN AVE 90064

Certificate Information: 2938 S TILDEN AVE 90064

Application / Permit
23010-20000-02060
Plan Check / Job No.
B23VN06395
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW IRREGULAR SHAPED 33' 11" X 25' 2" TWO STORY ADU 1087 SQFT (ALL ELECTRIC). PER LAMC 12.22 A.33 (c)-(d) . 1 OF 2
Permit Issued
Issued on 9/14/2023
Issuing Office
Valley
Current Status
CofO Issued on 12/28/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/16/2023 APPLICANT
Assigned to Plan Check Engineer 6/1/2023 NAREG ATARIAN
Corrections Issued 6/1/2023 NAREG ATARIAN
Quality Review Completed 6/2/2023 OMID HEDAYAT
Building Plans Picked Up 6/6/2023 APPLICANT
Applicant returned to address corrections 8/22/2023 NAREG ATARIAN
Applicant returned to address corrections 9/1/2023 NAREG ATARIAN
Plan Check Approved 9/1/2023 NAREG ATARIAN
Issued 9/14/2023 APPLICANT
CofO in Progress 11/1/2024 DANIEL VERA
CofO Issued 12/28/2024 RICHARD STEINBACH
Permit Finaled 12/28/2024 RICHARD STEINBACH

Permit Application Clearance Information

Grading Pre-Inspection Cleared 6/15/2023 ALEXANDER HELFER
Address approval Cleared 6/27/2023 DARIN LAM
Construction near power lines Cleared 7/10/2023 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 8/8/2023 DARIN LAM
Sewer availability Cleared 8/8/2023 DARIN LAM
Specific Plan Cleared 8/9/2023 WESTON PRINGLE
Low Impact Development (LID) Cleared 8/18/2023 MITESH PATEL
Roof/Waste drainage to street Cleared 8/20/2023 AHMED AMARRAGY
GPI Written Notices Cleared 9/14/2023 FELIX FIGUEROA

Contact Information

Contractor 3 At Once Inc; Lic. No.: 847812-B 6117 MANTON AVENUE      WOODLAND HILLS, CA 91367
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/29/2023 Partial Approval ARAM AVEDISIAN
Sewer 9/29/2023 Approved ARAM AVEDISIAN
PLUMBING-Rough 10/17/2023 Partial Approval CLAYTON GRAHAM
Special/Order Compliance 10/17/2023 Corrections Issued CLAYTON GRAHAM
Footing/Foundation/Slab 10/25/2023 Corrections Issued JESUS PINEDA
Excavation/Setback/Form/Re-Bar 11/1/2023 Not Ready for Inspection JESUS PINEDA
Excavation/Setback/Form/Re-Bar 11/7/2023 Approved MEL KHACHATOURIAN
Floor/Roof Diaphrgm/Shear Wall 12/27/2023 Corrections Issued JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 1/4/2024 Partial Approval JESUS PINEDA
Deputy Wood Construction 1/22/2024 Conditional Approval JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 1/26/2024 Conditional Approval JESUS PINEDA
BUILDING-Rough-Frame 2/23/2024 Corrections Issued JESUS PINEDA
ELECTRICAL-Rough 2/23/2024 Approved JESUS PINEDA
Green Building Rough 2/23/2024 Approved JESUS PINEDA
HVAC-Rough 2/23/2024 Approved JESUS PINEDA
MERV13>=Rough 2/23/2024 Approved JESUS PINEDA
PLUMBING-Rough 2/23/2024 Approved JESUS PINEDA
Verify Sprinkler Sign Off 2/23/2024 Not Ready for Inspection JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 3/6/2024 Approved SEAN HAUPT
Interior/Exterior Lathing 3/6/2024 Partial Approval SEAN HAUPT
Shower Pan 3/6/2024 Approved SEAN HAUPT
BUILDING-Rough-Frame 3/7/2024 Corrections Issued HERBERT GIRON
BUILDING-Rough-Frame 3/12/2024 Approved JESUS PINEDA
Interior/Exterior Lathing 3/14/2024 Corrections Issued OGANES TARAKHCHYAN
Insulation 3/18/2024 Corrections Issued JESUS PINEDA
Insulation 3/21/2024 Approved JESUS PINEDA
Drywall Nailing 3/28/2024 Approved JESUS PINEDA
Interior/Exterior Lathing 4/2/2024 Approved RICHARD STEINBACH
ELECTRICAL-Final 5/29/2024 Corrections Issued JESUS PINEDA
Footing/Foundation/Slab 5/29/2024 Approved JESUS PINEDA
Green Building Final 5/29/2024 Corrections Issued JESUS PINEDA
MERV13>=Final 5/29/2024 Approved JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 5/29/2024 SGSOV Approved JESUS PINEDA
Service/Power Release 5/29/2024 Not Ready for Inspection JESUS PINEDA
Smoke Detectors 5/29/2024 Approved JESUS PINEDA
ELECTRICAL-Final 7/5/2024 Approved JESUS PINEDA
Final 7/5/2024 Corrections Issued JESUS PINEDA
Green Building Final 7/5/2024 Approved JESUS PINEDA
HVAC-Final 7/5/2024 Approved JESUS PINEDA
PLUMBING-Final 7/5/2024 Approved JESUS PINEDA
Final 9/16/2024 Not Ready for Inspection DANIEL VERA
Service/Power Release 9/16/2024 Not Ready for Inspection DANIEL VERA
Final 9/23/2024 Not Ready for Inspection DANIEL VERA
Service/Power Release 9/23/2024 Not Ready for Inspection DANIEL VERA
Final 11/1/2024 OK to Issue CofO DANIEL VERA
Service/Power Release 11/1/2024 Approved DANIEL VERA
ELECTRICAL-Final 11/12/2024 Approved DANIEL VERA
Service/Power Release 11/12/2024 Approved DANIEL VERA