4212 N BAKMAN AVE 91602
Certificate Information: 4212 N BAKMAN AVE 91602
- Application / Permit
- 23010-20000-02022
- Plan Check / Job No.
- B23VN06282
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 27'-2.5" x 20'-4" DETACHED ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) AND LAMC 12.22 A.33(c)1, (d)1, and (g) - PER ENGINEER
- Permit Issued
- Issued on 3/14/2024
- Issuing Office
- Current Status
- CofO Issued on 7/31/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/17/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/23/2023 | ISIS ARGUETA |
| Corrections Issued | 5/24/2023 | ISIS ARGUETA |
| Applicant returned to address corrections | 11/24/2023 | ISIS ARGUETA |
| Plan Check Approved | 11/30/2023 | DANIEL ABRAMYAN |
| Issued | 3/14/2024 | APPLICANT |
| CofO in Progress | 7/3/2025 | JAVIER RAMOS JR |
| Permit Finaled | 7/31/2025 | RUBEN SALAS |
| Permit Finaled | 7/31/2025 | RUBEN SALAS |
| CofO Issued | 7/31/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 8/17/2023 | FERNANDO GIL |
| Sewer availability | Cleared | 8/17/2023 | FERNANDO GIL |
| Construction near power lines | Cleared | 9/9/2023 | RIDWAN HARDY |
| Low Impact Development (LID) | Cleared | 11/17/2023 | TOMMY YIN |
| Eng Process Fee Ord 176,300 | Cleared | 11/21/2023 | NIKKI ZULUETA |
| Roof/Waste drainage to street | Cleared | 11/21/2023 | NIKKI ZULUETA |
Contact Information
| Contractor | Concept Renovations Inc; Lic. No.: 1016942-B | , |
| Engineer | Mezey,, Steven William; Lic. No.: NA2665 | , |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 5/21/2024 | Approved | CHRISTOPHER ROJAS |
| Footing/Foundation/Slab | 5/23/2024 | Approved | CHRISTOPHER ROJAS |
| Footing/Foundation/Slab | 5/28/2024 | Approved | MISAEL ESPARZA |
| Green Building Rough | 5/28/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Special/Order Compliance | 5/28/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Underground Mechanical | 5/28/2024 | Approved | MISAEL ESPARZA |
| Verify Sprinkler Sign Off | 5/28/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Deputy Wood Construction | 6/5/2024 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 6/7/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/12/2024 | Approved | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 7/2/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 7/2/2024 | Approved | CHRISTOPHER ROJAS |
| HVAC-Rough | 7/2/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 7/2/2024 | Approved | CHRISTOPHER ROJAS |
| Underground Mechanical | 7/2/2024 | Approved | CHRISTOPHER ROJAS |
| HVAC-Rough | 7/5/2024 | Partial Approval | DAVID ANDERSON |
| BUILDING-Rough-Frame | 8/15/2024 | Approved | CHRISTOPHER ROJAS |
| Green Building Rough | 8/15/2024 | Approved | CHRISTOPHER ROJAS |
| HVAC-Rough | 8/15/2024 | Approved | CHRISTOPHER ROJAS |
| Underground Mechanical | 8/15/2024 | Approved | CHRISTOPHER ROJAS |
| Verify Sprinkler Sign Off | 8/15/2024 | Approved | CHRISTOPHER ROJAS |
| Insulation | 9/11/2024 | Approved | MICHAEL CORTEZ |
| Interior/Exterior Lathing | 9/11/2024 | Partial Approval | MICHAEL CORTEZ |
| Drywall Nailing | 9/19/2024 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 9/19/2024 | Approved | CHRISTOPHER ROJAS |
| Shower Pan | 9/19/2024 | Approved | CHRISTOPHER ROJAS |
| Final | 3/7/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Green Building Final | 3/7/2025 | Partial Inspection | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 3/7/2025 | SGSOV Approved | CHRISTOPHER ROJAS |
| Service/Power Release | 3/7/2025 | Partial Inspection | CHRISTOPHER ROJAS |
| Smoke Detectors | 3/7/2025 | Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 5/29/2025 | Partial Inspection | JAVIER RAMOS JR |
| Final | 5/29/2025 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Final | 5/29/2025 | Not Ready for Inspection | JAVIER RAMOS JR |
| HVAC-Final | 5/29/2025 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 5/29/2025 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 6/18/2025 | Approved | JAVIER RAMOS JR |
| Final | 6/18/2025 | Partial Inspection | JAVIER RAMOS JR |
| Green Building Final | 6/18/2025 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 7/3/2025 | Approved | JAVIER RAMOS JR |
| Final | 7/3/2025 | OK to Issue CofO | JAVIER RAMOS JR |