9451 N ALDEA AVE 91325

Certificate Information: 9451 N ALDEA AVE 91325

Application / Permit
23010-20000-02014
Plan Check / Job No.
B23VN06258
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED TWO STORY DETACHED ACCESSORY DWELLING UNIT [PER LAMC 12.22A33(C) AND (D)].
Permit Issued
Issued on 12/7/2023
Issuing Office
Current Status
Issued on 12/7/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/12/2023 APPLICANT
Assigned to Plan Check Engineer 5/18/2023 DAWN MC NULTY
Corrections Issued 5/23/2023 DAWN MC NULTY
Quality Review Completed 5/30/2023 STEVEN KIM
Applicant returned to address corrections 10/10/2023 DAWN MC NULTY
Applicant returned to address corrections 10/12/2023 DAWN MC NULTY
Applicant returned to address corrections 10/24/2023 DAWN MC NULTY
Plan Check Approved 10/26/2023 DAWN MC NULTY
Issued 12/7/2023 APPLICANT

Permit Application Clearance Information

Address approval Cleared 5/23/2023 NIKKI ZULUETA
BHO/Hillside ordinance Cleared 5/23/2023 NIKKI ZULUETA
BHO/Hillside ordinance Cleared 5/23/2023 NIKKI ZULUETA
BHO/Hillside ordinance Cleared 5/23/2023 NIKKI ZULUETA
BHO/Hillside ordinance Cleared 5/23/2023 NIKKI ZULUETA
BHO/Hillside ordinance Cleared 5/23/2023 NIKKI ZULUETA
Eng Process Fee Ord 176,300 Cleared 5/24/2023 NIKKI ZULUETA
Sewer availability Cleared 5/24/2023 NIKKI ZULUETA
Hydrant and Access approval Cleared 6/29/2023 KURT CORRAL
Low Impact Development (LID) Cleared 8/31/2023 SAMUEL LINN
GPI Written Notices Cleared 10/9/2023 DAWN MC NULTY
Grading Pre-Inspection Cleared 10/9/2023 DAWN MC NULTY

Contact Information

Contractor Voskanian Razmik Thomas; Lic. No.: 909850-B       ,
Engineer Burnazyan,, Gegam; Lic. No.: NA76761       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/12/2023 Corrections Issued JOHN COLEMAN
Footing/Foundation/Slab 1/19/2024 Corrections Issued JAVIER RAMOS JR
PLUMBING-Rough 1/19/2024 Partial Approval JAVIER RAMOS JR
Footing/Foundation/Slab 1/31/2024 Corrections Issued JAVIER RAMOS JR
BUILDING-Rough-Frame 4/4/2024 Corrections Issued JAVIER RAMOS JR
Pre-Inspection 8/27/2024 Corrections Issued JAVIER RAMOS JR
ELECTRICAL-Rough 9/10/2024 Not Ready for Inspection RAUL OLAGI
HVAC-Rough 9/10/2024 Not Ready for Inspection RAUL OLAGI
PLUMBING-Rough 9/10/2024 Not Ready for Inspection RAUL OLAGI
Special/Order Compliance 9/10/2024 Corrections Issued RAUL OLAGI
ELECTRICAL-Rough 9/16/2024 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 9/16/2024 Corrections Issued JAVIER RAMOS JR
Footing/Foundation/Slab 9/16/2024 Partial Approval JAVIER RAMOS JR
Gas Test 9/16/2024 Partial Approval JAVIER RAMOS JR
HVAC-Rough 9/16/2024 Corrections Issued JAVIER RAMOS JR
PLUMBING-Rough 9/16/2024 Corrections Issued JAVIER RAMOS JR
Wood Frame 9/16/2024 Corrections Issued JAVIER RAMOS JR
Wood Frame 10/18/2024 Partial Approval KEVIN BERBERYAN
Interior/Exterior Lathing 1/27/2025 Partial Approval MICHAEL CORTEZ
Insulation 1/29/2025 Corrections Issued JAVIER RAMOS JR
HVAC-Rough 2/3/2025 Approved JAVIER RAMOS JR
Insulation 2/3/2025 Not Ready for Inspection JAVIER RAMOS JR
PLUMBING-Rough 2/3/2025 Approved JAVIER RAMOS JR
Drywall Nailing 2/7/2025 Approved LOUIS ESCOTO
Insulation 2/7/2025 Approved LOUIS ESCOTO
Shower Pan 2/19/2025 Approved LOUIS ESCOTO
Gas Test 9/24/2025 Partial Approval NICHOLAS TROWBRIDGE
Underground Mechanical 9/24/2025 Partial Approval NICHOLAS TROWBRIDGE
Sewer 9/30/2025 Approved NICHOLAS TROWBRIDGE