13406 N GLENOAKS BLVD 91342
Certificate Information: 13406 N GLENOAKS BLVD 91342
- Application / Permit
- 23010-20000-02005
- Plan Check / Job No.
- B23VN06237
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 24' X 40' (2) STORY SINGLE FAMILY DWELLING PER SB 9 WITH ATTACHED 1-CAR GARAGE; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 11/28/2023
- Issuing Office
- Valley
- Current Status
- Issued on 11/28/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/12/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/25/2023 | SELLA BENYAMIN |
| Corrections Issued | 6/1/2023 | SELLA BENYAMIN |
| Quality Review Completed | 6/6/2023 | STEVEN KIM |
| Building Plans Picked Up | 6/8/2023 | APPLICANT |
| Plan Check Approved | 11/28/2023 | SELLA BENYAMIN |
| Issued | 11/28/2023 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 6/13/2023 | TAL SHEMEN |
| Miscellaneous | Cleared | 7/6/2023 | NIALL HUFFMAN |
| Hydrant and Access approval | Cleared | 7/16/2023 | JOHN CONNEALLY |
| Senate Bill 9 | Cleared | 11/6/2023 | ALEX VELA |
| Low Impact Development (LID) | Cleared | 11/13/2023 | LUIS LUVANO |
| Eng Process Fee Ord 176,300 | Cleared | 11/14/2023 | TAL SHEMEN |
| Sewer availability | Cleared | 11/14/2023 | TAL SHEMEN |
| Roof/Waste drainage to street | Cleared | 11/15/2023 | BRYAN GODINEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Van, Valkenburg, John; Lic. No.: C74939 | 13259 KISMET AVE SYLMAR, CA 91342 |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 12/13/2023 | Not Ready for Inspection | KEVIN BERBERYAN |
| Excavation/Setback/Form/Re-Bar | 12/15/2023 | Not Ready for Inspection | KEVIN BERBERYAN |
| Footing/Foundation/Slab | 12/15/2023 | Not Ready for Inspection | KEVIN BERBERYAN |
| Footing/Foundation/Slab | 12/18/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| Posting Pre-Inspection | 12/18/2023 | Partial Inspection | MICHEL ABAJAN |
| PLUMBING-Rough | 12/28/2023 | Partial Approval | MICHEL ABAJAN |
| Footing/Foundation/Slab | 1/11/2024 | Conditional Approval | KEVIN BERBERYAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/12/2024 | Conditional Approval | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 3/14/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 3/28/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/28/2024 | Partial Approval | KEVIN BERBERYAN |
| HVAC-Rough | 3/28/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| PLUMBING-Rough | 3/28/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| Rough-Elec/Plmb/HVAC | 7/15/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| Underground Mechanical | 9/5/2024 | Approved | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 10/24/2024 | Approved | KEVIN BERBERYAN |
| Green Building Rough | 10/24/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| Rough-Elec/Plmb/HVAC | 10/24/2024 | Corrections Issued | KEVIN BERBERYAN |
| Verify Sprinkler Sign Off | 10/24/2024 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 10/30/2024 | Approved | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 11/19/2024 | Approved | KEVIN BERBERYAN |
| ELECTRICAL-Rough | 11/19/2024 | Approved | KEVIN BERBERYAN |
| Green Building Rough | 11/19/2024 | Approved | KEVIN BERBERYAN |
| HVAC-Rough | 11/19/2024 | Approved | KEVIN BERBERYAN |
| PLUMBING-Rough | 11/19/2024 | Approved | KEVIN BERBERYAN |
| Insulation | 11/25/2024 | Conditional Approval | KEVIN BERBERYAN |
| Drywall Nailing | 12/20/2024 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 1/31/2025 | Approved | KEVIN BERBERYAN |