10775 N MOUNTAIR AVE 91042

Certificate Information: 10775 N MOUNTAIR AVE 91042

Application / Permit
23010-20000-01996
Plan Check / Job No.
B23VN06208
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 33'-6" X 30'-6" DETACHED ACCESSORY DWELLING UNIT WITH A 7'-6" X 16'-6" ATTACHED PATIO COVER TO THE ACCESSORY DWELLING UNIT PER CA Govt.Code 65852.2(e)(1)(A). WORK DONE PER WFPP.
Permit Issued
Issued on 12/2/2023
Issuing Office
Current Status
CofO Issued on 4/22/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/12/2023 APPLICANT
Assigned to Plan Check Engineer 5/16/2023 MIROOSH KHACHATOORIAN
Corrections Issued 5/17/2023 MIROOSH KHACHATOORIAN
Applicant returned to address corrections 9/1/2023 MIROOSH KHACHATOORIAN
Applicant returned to address corrections 9/14/2023 MIROOSH KHACHATOORIAN
Plan Check Approved 11/30/2023 MIROOSH KHACHATOORIAN
Issued 12/2/2023 APPLICANT
CofO in Progress 4/8/2025 WILLIAM WREN
Permit Finaled 4/22/2025 RUBEN SALAS
CofO Issued 4/22/2025 RUBEN SALAS
Permit Finaled 4/22/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 6/1/2023 RYAN KIM
Eng Process Fee Ord 176,300 Cleared 6/5/2023 RYAN KIM
Sewer availability Cleared 6/5/2023 RYAN KIM
Hydrant and Access approval Cleared 7/17/2023 RUEL COLE
Low Impact Development (LID) Cleared 8/24/2023 SAMUEL LINN
Roof/Waste drainage to street Cleared 8/24/2023 CARLOS AGUILERA
Grading Pre-Inspection Cleared 8/29/2023 SERGIO VALENZUELA
GPI Written Notices Cleared 11/28/2023 MIROOSH KHACHATOORIAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/16/2024 Corrections Issued WILLIAM WREN
Footing/Foundation/Slab 4/23/2024 Approved WILLIAM WREN
BUILDING-Rough-Frame 5/22/2024 Corrections Issued WILLIAM WREN
PLUMBING-Rough 5/22/2024 Partial Approval WILLIAM WREN
Wood Frame 6/10/2024 Not Ready for Inspection WILLIAM WREN
Wood Frame 7/2/2024 Partial Approval WILLIAM WREN
Insulation 7/8/2024 Partial Approval WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 9/4/2024 Corrections Issued WILLIAM WREN
ELECTRICAL-Rough 9/13/2024 Approved WILLIAM WREN
PLUMBING-Rough 9/13/2024 Approved WILLIAM WREN
HVAC-Rough 9/20/2024 Approved WILLIAM WREN
Sewer 10/7/2024 Approved WILLIAM WREN
BUILDING-Rough-Frame 10/30/2024 Approved WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 10/30/2024 Approved WILLIAM WREN
Verify Sprinkler Sign Off 10/30/2024 Approved WILLIAM WREN
Insulation 11/6/2024 Corrections Issued WILLIAM WREN
Insulation 11/12/2024 Approved WILLIAM WREN
Drywall Nailing 11/18/2024 Approved WILLIAM WREN
Interior/Exterior Lathing 11/18/2024 Partial Approval WILLIAM WREN
Interior/Exterior Lathing 12/11/2024 Approved DAVID ANDERSON
Shower Pan 12/11/2024 Approved DAVID ANDERSON
Pre-Inspection 12/19/2024 Partial Inspection WILLIAM WREN
Final 3/12/2025 Corrections Issued WILLIAM WREN
SGSOV-Seismic Gas S/O Valve 3/12/2025 SGSOV Not Required WILLIAM WREN
Service/Power Release 3/12/2025 Not Ready for Inspection WILLIAM WREN
Smoke Detectors 3/12/2025 Approved WILLIAM WREN
Final 4/1/2025 Not Ready for Inspection WILLIAM WREN
Service/Power Release 4/1/2025 Corrections Issued WILLIAM WREN
Final 4/3/2025 OK to Issue CofO WILLIAM WREN
Service/Power Release 4/3/2025 Approved WILLIAM WREN