19800 W VICTORY BLVD 91367
Certificate Information: 19800 W VICTORY BLVD 91367
- Application / Permit
- 23010-20000-01975
- Plan Check / Job No.
- B23VN06113
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). COMPLY WITH DEPARTMENT ORDER effective date 10/22/2019. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
- Permit Issued
- Issued on 7/18/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/6/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/10/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/15/2023 | JEROME MAGAT PALMA |
| Corrections Issued | 5/16/2023 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 5/17/2023 | APPLICANT |
| Applicant returned to address corrections | 6/15/2023 | LUISANGEL VALENZUELA |
| Plan Check Approved | 7/14/2023 | CRISTINA SALAZAR |
| Issued | 7/18/2023 | APPLICANT |
| CofO in Progress | 6/6/2024 | JOEL GUARDADO |
| Permit Finaled | 6/6/2024 | DAVID JAMES |
| CofO Issued | 6/6/2024 | DAVID JAMES |
| Permit Finaled | 6/6/2024 | DAVID JAMES |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 5/18/2023 | GILBERT URREA |
| Eng Process Fee Ord 176,300 | Cleared | 6/1/2023 | NIKKI ZULUETA |
| Sewer availability | Cleared | 6/1/2023 | NIKKI ZULUETA |
| Address approval | Cleared | 6/5/2023 | NIKKI ZULUETA |
| ZI | Cleared | 6/13/2023 | RYAN LY |
| Low Impact Development (LID) | Cleared | 6/19/2023 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 6/20/2023 | ROMAN GUTIERREZ |
Contact Information
| Contractor | Yourico Construction Inc; Lic. No.: 594159-B | 1241 N THOMPSON AVENUE GLENDALE, CA 91201 |
| Engineer | Koma,, Shahram Javadi; Lic. No.: C69497 | 23241 VENTURA BLVD 300 WOODLAND HILLS, CA 91364 |
Inspector Information
| ARA SINANIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HASANTHA WEERASEKARA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| SCOTT SHUSTER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEL GUARDADO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIYA MIHALEVA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOSE RUBIO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID JAMES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID HICKMAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN HAMILTON, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN STEPHENS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| PIERRE VEGA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK VAN SLOOTEN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MICKEY YAMASHITA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RICHARD ROBLES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HAGOP BADOSSIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM BEAUCHAMP, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK DOVICO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| THOMAS WOODS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL VASQUEZ, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| AUGUSTUS ALBAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| FELIPE PENICHE, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| LEO MILBAUER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/24/2023 | Approved | EMIL ALEXANDRIAN |
| Sewer | 7/24/2023 | Approved | EMIL ALEXANDRIAN |
| Underground Mechanical | 7/24/2023 | Approved | EMIL ALEXANDRIAN |
| BUILDING-Rough-Frame | 10/25/2023 | Corrections Issued | ROBERT SUNSERI |
| Green Building Rough | 10/25/2023 | Approved | ROBERT SUNSERI |
| Rough-Elec/Plmb/HVAC | 10/25/2023 | Partial Approval | ROBERT SUNSERI |
| BUILDING-Rough-Frame | 10/27/2023 | Partial Inspection | JOEL GUARDADO |
| ELECTRICAL-Rough | 10/27/2023 | Approved | JOEL GUARDADO |
| Green Building Rough | 10/27/2023 | Approved | JOEL GUARDADO |
| Insulation | 11/3/2023 | Approved | JOEL GUARDADO |
| Interior/Exterior Lathing | 11/3/2023 | Approved | JOEL GUARDADO |
| Shower Pan | 11/3/2023 | Approved | JOEL GUARDADO |
| Drywall Nailing | 11/9/2023 | Approved | JOEL GUARDADO |
| Rough-Elec/Plmb/HVAC | 12/5/2023 | Approved | JOEL GUARDADO |
| Sewer | 12/5/2023 | Approved | JOEL GUARDADO |
| Underground Mechanical | 12/5/2023 | Approved | JOEL GUARDADO |
| BUILDING-Rough-Frame | 1/31/2024 | Approved | JOEL GUARDADO |
| Final | 1/31/2024 | Partial Inspection | JOEL GUARDADO |
| Green Building Final | 1/31/2024 | Approved | JOEL GUARDADO |
| SGSOV-Seismic Gas S/O Valve | 1/31/2024 | SGSOV Not Ready | JOEL GUARDADO |
| Service/Power Release | 1/31/2024 | Approved | JOEL GUARDADO |
| Smoke Detectors | 1/31/2024 | Approved | JOEL GUARDADO |
| ELECTRICAL-Final | 4/12/2024 | Approved | JOEL GUARDADO |
| Final | 4/12/2024 | Partial Approval | JOEL GUARDADO |
| HVAC-Final | 4/12/2024 | Approved | JOEL GUARDADO |
| PLUMBING-Final | 4/12/2024 | Approved | JOEL GUARDADO |
| SGSOV-Seismic Gas S/O Valve | 4/12/2024 | SGSOV Approved | JOEL GUARDADO |
| Final | 6/6/2024 | OK to Issue CofO | JOEL GUARDADO |