8747 N OAK PARK AVE 91325

Certificate Information: 8747 N OAK PARK AVE 91325

Application / Permit
23010-20000-01971
Plan Check / Job No.
B23VN06067
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 20' X 30' DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33(c) AND (d). WORK DONE PER APPROVED ADU STANDARD PLAN. NFPA-13R FIRE SPRINKLERS TO BE INSTALLED THROUGHOUT.
Permit Issued
Issued on 10/23/2023
Issuing Office
Current Status
Issued on 10/23/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/11/2023 APPLICANT
Assigned to Plan Check Engineer 5/16/2023 MADISON ODELL
Corrections Issued 5/17/2023 MADISON ODELL
Applicant returned to address corrections 9/15/2023 MADISON ODELL
Plan Check Approved 9/19/2023 MADISON ODELL
Issued 10/23/2023 APPLICANT

Permit Application Clearance Information

Address approval Cleared 5/26/2023 JOHN LIN
Sewer availability Cleared 5/26/2023 JOHN LIN
Hydrant and Access approval Cleared 7/6/2023 RUEL COLE
Low Impact Development (LID) Cleared 9/6/2023 LUIS LUVANO
Eng Process Fee Ord 176,300 Cleared 9/7/2023 DAGOVERTO GUERRERO
Roof/Waste drainage to street Cleared 9/7/2023 DAGOVERTO GUERRERO
Construction near power lines Cleared 9/15/2023 WALTER RAMIREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Hamilton,, John O; Lic. No.: C53284 P O BOX 866      HAWTHORNE, CA 90251

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/2/2023 Approved JAVIER RAMOS JR
PLUMBING-Rough 11/9/2023 Conditional Approval JOHN COLEMAN
Pre-Inspection 11/9/2023 Corrections Issued JOHN COLEMAN
Footing/Foundation/Slab 11/28/2023 Corrections Issued JAVIER RAMOS JR
Deputy Wood Construction 3/11/2024 Conditional Approval ROBERT GOLD
Floor/Roof Diaphrgm/Shear Wall 3/13/2024 Corrections Issued JAVIER RAMOS JR
ELECTRICAL-Rough 4/26/2024 Approved JAVIER RAMOS JR
HVAC-Rough 4/26/2024 Corrections Issued JAVIER RAMOS JR
PLUMBING-Rough 4/26/2024 Corrections Issued JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 5/20/2024 Corrections Issued JAVIER RAMOS JR
Footing/Foundation/Slab 5/20/2024 Approved JAVIER RAMOS JR
HVAC-Rough 5/20/2024 Partial Inspection JAVIER RAMOS JR
PLUMBING-Rough 5/20/2024 Approved JAVIER RAMOS JR
Verify Sprinkler Sign Off 5/20/2024 Approved JAVIER RAMOS JR
Wood Frame 5/20/2024 Not Ready for Inspection JAVIER RAMOS JR
BUILDING-Rough-Frame 6/6/2024 Partial Inspection JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 6/6/2024 Approved JAVIER RAMOS JR
HVAC-Rough 6/6/2024 Partial Inspection JAVIER RAMOS JR
Insulation 6/6/2024 Not Ready for Inspection JAVIER RAMOS JR
HVAC-Rough 6/14/2024 Not Ready for Inspection JAVIER RAMOS JR
Drywall Nailing 6/28/2024 Approved JAVIER RAMOS JR
Insulation 6/28/2024 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 6/28/2024 Partial Approval JAVIER RAMOS JR
Interior/Exterior Lathing 8/1/2024 Approved LOUIS ESCOTO
Underground Mechanical 9/17/2024 Approved GAREN HAYRAPETYAN
Underground Mechanical 9/23/2024 Not Ready for Inspection GAREN HAYRAPETYAN
ELECTRICAL-Final 9/25/2024 Not Ready for Inspection JAVIER RAMOS JR
PLUMBING-Final 9/25/2024 Not Ready for Inspection JAVIER RAMOS JR
Pre-Inspection 9/25/2024 Approved JAVIER RAMOS JR
PLUMBING-Final 9/30/2024 Partial Inspection JAVIER RAMOS JR
Underground Mechanical 9/30/2024 Partial Approval JAVIER RAMOS JR
ELECTRICAL-Final 10/25/2024 Corrections Issued JENNIFER RABUCHIN
Smoke Detectors 10/25/2024 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 11/6/2024 Approved JAVIER RAMOS JR
Special/Order Compliance 11/6/2024 Corrections Issued JAVIER RAMOS JR
ELECTRICAL-Final 8/12/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
Pre-Inspection 8/19/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
Pre-Inspection 9/5/2025 Corrections Issued NICHOLAS TROWBRIDGE
Pre-Inspection 9/24/2025 Partial Inspection NICHOLAS TROWBRIDGE
Underground Mechanical 9/26/2025 Partial Approval NICHOLAS TROWBRIDGE
Pre-Inspection 11/7/2025 Partial Inspection NICHOLAS TROWBRIDGE
PLUMBING-Final 12/4/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
HVAC-Final 12/10/2025 Corrections Issued CHRISTOPHER ROJAS
PLUMBING-Final 12/10/2025 Corrections Issued CHRISTOPHER ROJAS
Special/Order Compliance 1/13/2026 Corrections Issued CHRISTOPHER ROJAS
BUILDING-Rough-Frame 3/11/2026 Approved CHRISTOPHER ROJAS
ELECTRICAL-Final 3/11/2026 Corrections Issued CHRISTOPHER ROJAS
Final 3/11/2026 Corrections Issued CHRISTOPHER ROJAS
HVAC-Final 3/11/2026 Not Ready for Inspection CHRISTOPHER ROJAS
PLUMBING-Final 3/11/2026 Not Ready for Inspection CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 3/11/2026 SGSOV No Gas CHRISTOPHER ROJAS
ELECTRICAL-Final 4/1/2026 Not Ready for Inspection CHRISTOPHER ROJAS
ELECTRICAL-Final 4/15/2026 No Access for Inspection MISAEL ESPARZA
PLUMBING-Final 4/15/2026 No Access for Inspection MISAEL ESPARZA
ELECTRICAL-Final 4/16/2026 Not Ready for Inspection RAUL OLAGI
PLUMBING-Final 4/16/2026 Not Ready for Inspection RAUL OLAGI
ELECTRICAL-Final 4/20/2026 Approved JOSE AVILA