14143 W FILMORE ST 91331
Certificate Information: 14143 W FILMORE ST 91331
- Application / Permit
- 23010-20000-01970
- Plan Check / Job No.
- B23VN06064
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED 21'-0" x 40'-0" ACCESSORY DWELLING UNIT TO COMPLY WITH GCS 65852.2(e)(1)(B) AND LAMC 12.22 A.33(c),(d) AND (g). WORK PER WFPP.
- Permit Issued
- Issued on 8/15/2023
- Issuing Office
- Current Status
- CofO Issued on 3/24/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/10/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/12/2023 | ALFRED RAMIREZ |
| Corrections Issued | 5/14/2023 | ALFRED RAMIREZ |
| Applicant returned to address corrections | 8/2/2023 | ISIS ARGUETA |
| Applicant returned to address corrections | 8/4/2023 | MIROOSH KHACHATOORIAN |
| Applicant returned to address corrections | 8/9/2023 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 8/11/2023 | ALEC MOUSAKHANIAN |
| Issued | 8/15/2023 | APPLICANT |
| CofO in Progress | 3/5/2026 | JENNIFER RABUCHIN |
| Permit Finaled | 3/24/2026 | RUBEN SALAS |
| CofO Issued | 3/24/2026 | RUBEN SALAS |
| Permit Finaled | 3/24/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 5/31/2023 | FERNANDO GIL |
| Construction near power lines | Cleared | 6/27/2023 | WALTER RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 7/7/2023 | FERNANDO GIL |
| Sewer availability | Cleared | 7/7/2023 | FERNANDO GIL |
| Low Impact Development (LID) | Cleared | 7/26/2023 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 7/27/2023 | FERNANDO GIL |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/25/2025 | Approved | JENNIFER RABUCHIN |
| Excavation/Setback/Form/Re-Bar | 5/7/2025 | Conditional Approval | JENNIFER RABUCHIN |
| Pre-Inspection | 5/7/2025 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 5/20/2025 | Partial Approval | JENNIFER RABUCHIN |
| METHANE-Rough | 5/20/2025 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 5/20/2025 | Partial Approval | JENNIFER RABUCHIN |
| Verify Sprinkler Sign Off | 5/20/2025 | Approved | JENNIFER RABUCHIN |
| Insulation | 5/22/2025 | Partial Approval | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 5/27/2025 | Partial Approval | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 6/17/2025 | Partial Approval | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 7/9/2025 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 7/9/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Deputy Wood Construction | 7/16/2025 | Conditional Approval | RAUL OLAGI |
| Gas Test | 7/22/2025 | Approved | NICHOLAS TROWBRIDGE |
| Interior/Exterior Lathing | 7/22/2025 | Partial Approval | NICHOLAS TROWBRIDGE |
| Rough-Elec/Plmb/HVAC | 7/22/2025 | Partial Approval | NICHOLAS TROWBRIDGE |
| SGSOV-Seismic Gas S/O Valve | 7/22/2025 | SGSOV Not Ready | NICHOLAS TROWBRIDGE |
| BUILDING-Rough-Frame | 8/4/2025 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 8/4/2025 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 8/4/2025 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Rough | 8/15/2025 | Approved | JENNIFER RABUCHIN |
| Insulation | 8/15/2025 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 8/15/2025 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 9/29/2025 | Approved | JENNIFER RABUCHIN |
| Underground Mechanical | 9/29/2025 | Approved | JENNIFER RABUCHIN |
| Shower Pan | 10/15/2025 | Approved | MICHAEL CORTEZ |
| Service/Power Release | 10/17/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 10/22/2025 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 10/22/2025 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 2/4/2026 | Not Ready for Inspection | RUBEN SALAS |
| Final | 2/4/2026 | Not Ready for Inspection | RUBEN SALAS |
| Footing/Foundation/Slab | 2/4/2026 | Not Ready for Inspection | RUBEN SALAS |
| HVAC-Final | 2/4/2026 | Not Ready for Inspection | RUBEN SALAS |
| METHANE-Barrier | 2/4/2026 | Not Ready for Inspection | RUBEN SALAS |
| METHANE-Subgrade | 2/4/2026 | Not Ready for Inspection | RUBEN SALAS |
| PLUMBING-Final | 2/4/2026 | Not Ready for Inspection | RUBEN SALAS |
| SGSOV-Seismic Gas S/O Valve | 2/4/2026 | SGSOV Not Ready | RUBEN SALAS |
| Service/Power Release | 2/4/2026 | Not Ready for Inspection | RUBEN SALAS |
| Smoke Detectors | 2/4/2026 | Not Ready for Inspection | RUBEN SALAS |
| ELECTRICAL-Final | 2/13/2026 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 2/13/2026 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 2/13/2026 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 2/13/2026 | Corrections Issued | JENNIFER RABUCHIN |
| Service/Power Release | 2/13/2026 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Smoke Detectors | 2/13/2026 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 2/20/2026 | Approved | JENNIFER RABUCHIN |
| Final | 2/20/2026 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 2/20/2026 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 2/20/2026 | Approved | JENNIFER RABUCHIN |
| METHANE-Barrier | 2/20/2026 | Approved | JENNIFER RABUCHIN |
| METHANE-Subgrade | 2/20/2026 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 2/20/2026 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 2/20/2026 | SGSOV Approved | JENNIFER RABUCHIN |
| Service/Power Release | 2/20/2026 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 2/26/2026 | OK to Issue CofO | JENNIFER RABUCHIN |
| Service/Power Release | 2/26/2026 | Approved | JENNIFER RABUCHIN |