4927 N DENNY AVE 91601

Certificate Information: 4927 N DENNY AVE 91601

Application / Permit
23010-20000-01965
Plan Check / Job No.
B23VN06051
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ACCESSORY DWELLING UNIT WITH COVERED PORCH PER LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 6/21/2024
Issuing Office
Current Status
Issued on 6/21/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/11/2023 APPLICANT
Assigned to Plan Check Engineer 5/25/2023 CARLOS MONTES
Corrections Issued 6/1/2023 CARLOS MONTES
Quality Review Completed 6/1/2023 GARO TELMI
Applicant returned to address corrections 3/19/2024 CARLOS MONTES
Applicant returned to address corrections 5/29/2024 CARLOS MONTES
Plan Check Approved 6/20/2024 CARLOS MONTES
Issued 6/21/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 8/22/2023 COLIN LOREDO
Sewer availability Cleared 8/28/2023 COLIN LOREDO
Low Impact Development (LID) Cleared 4/26/2024 SAMUEL LINN
Roof/Waste drainage to street Cleared 4/26/2024 MARKOS PEREZ-BRAN
Eng Process Fee Ord 176,300 Cleared 4/29/2024 CARLOS AGUILERA

Contact Information

Architect Diradourian,, Richard C; Lic. No.: NA10336       ,
Contractor Owner-Builder       ,

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/8/2024 Partial Inspection JOSE AVILA
Special/Order Compliance 7/8/2024 Corrections Issued JOSE AVILA
Footing/Foundation/Slab 7/12/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 9/3/2024 Partial Approval MISAEL ESPARZA
BUILDING-Rough-Frame 10/16/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 10/16/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 10/16/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
Green Building Rough 10/16/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
HVAC-Rough 10/16/2024 Approved ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 10/16/2024 Approved ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 10/16/2024 Approved ROBERTO PALACIOS-LOPEZ
Verify Sprinkler Sign Off 10/16/2024 Approved ROBERTO PALACIOS-LOPEZ
Insulation 11/7/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Insulation 11/12/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Underground Mechanical 11/12/2024 Order to Comply Issued ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 11/15/2024 Approved ROBERTO PALACIOS-LOPEZ
Drywall Nailing 11/15/2024 Approved ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 11/15/2024 Approved ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 11/15/2024 Approved ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 11/15/2024 Approved ROBERTO PALACIOS-LOPEZ
Green Building Rough 11/15/2024 Approved ROBERTO PALACIOS-LOPEZ
Insulation 11/15/2024 Approved ROBERTO PALACIOS-LOPEZ
Shower Pan 11/22/2024 Approved JOSE AVILA
Interior/Exterior Lathing 11/26/2024 Approved ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 11/26/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 1/14/2025 Partial Inspection JOSE AVILA
ELECTRICAL-Rough 3/4/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
Final 6/24/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Final 6/24/2025 Approved ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 6/24/2025 SGSOV Not Required ROBERTO PALACIOS-LOPEZ
Service/Power Release 6/24/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Smoke Detectors 6/24/2025 Approved ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 7/8/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Final 7/8/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
HVAC-Final 7/8/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Final 7/8/2025 Approved ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 7/23/2025 Approved ROBERTO PALACIOS-LOPEZ
Final 7/23/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
HVAC-Rough 7/23/2025 Approved ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 7/23/2025 SGSOV Not Required ROBERTO PALACIOS-LOPEZ
Service/Power Release 7/23/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ