10622 N LAUREL CANYON BLVD 91331
Certificate Information: 10622 N LAUREL CANYON BLVD 91331
- Application / Permit
- 23010-20000-01936
- Plan Check / Job No.
- B23VN05967
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 29'-0" X 25'-0" IRREGULAR SHAPED 2-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 2/23/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/28/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/8/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/18/2023 | MARVEL DELACRUZ |
| Corrections Issued | 5/23/2023 | MARVEL DELACRUZ |
| Quality Review Completed | 5/23/2023 | OMID HEDAYAT |
| Building Plans Picked Up | 6/7/2023 | APPLICANT |
| Applicant returned to address corrections | 2/21/2024 | MARVEL DELACRUZ |
| Plan Check Approved | 2/23/2024 | MARVEL DELACRUZ |
| Issued | 2/23/2024 | APPLICANT |
| CofO in Progress | 1/17/2025 | MICHEL ABAJAN |
| Permit Finaled | 1/28/2025 | RUBEN SALAS |
| CofO Issued | 1/28/2025 | RUBEN SALAS |
| Permit Finaled | 1/28/2025 | RUBEN SALAS |
Permit Application Clearance Information
| ZI | Cleared | 5/30/2023 | ASHLEY RODARTE |
| ZI | Cleared | 5/30/2023 | ASHLEY RODARTE |
| Address approval | Cleared | 5/31/2023 | FERNANDO GIL |
| Low Impact Development (LID) | Cleared | 1/30/2024 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 1/31/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 2/7/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 2/7/2024 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Avila,, Albert Guerrero; Lic. No.: C41726 | 10034 GLADE AVNENUE CHATSWORTH, CA 91311 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| METHANE-Subgrade | 5/22/2024 | Corrections Issued | MICHEL ABAJAN |
| PLUMBING-Rough | 5/22/2024 | Partial Approval | MICHEL ABAJAN |
| Excavation/Setback/Form/Re-Bar | 5/28/2024 | Corrections Issued | JOHN COLEMAN |
| Footing/Foundation/Slab | 5/28/2024 | Not Ready for Inspection | JOHN COLEMAN |
| METHANE-Barrier | 5/28/2024 | Not Ready for Inspection | JOHN COLEMAN |
| METHANE-Subgrade | 5/28/2024 | Corrections Issued | JOHN COLEMAN |
| Excavation/Setback/Form/Re-Bar | 5/31/2024 | Corrections Issued | MICHEL ABAJAN |
| Excavation/Setback/Form/Re-Bar | 6/26/2024 | Approved | MICHEL ABAJAN |
| METHANE-Subgrade | 6/26/2024 | Approved | MICHEL ABAJAN |
| Deputy Reinf. Concrete | 6/28/2024 | Approved | MICHEL ABAJAN |
| Footing/Foundation/Slab | 6/28/2024 | Approved | MICHEL ABAJAN |
| METHANE-Barrier | 6/28/2024 | Approved | MICHEL ABAJAN |
| Wood Frame | 7/9/2024 | Partial Approval | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/1/2024 | Partial Approval | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 8/14/2024 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 8/14/2024 | Approved | MICHEL ABAJAN |
| Green Building Rough | 8/14/2024 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 8/14/2024 | Approved | MICHEL ABAJAN |
| METHANE-Rough | 8/14/2024 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 8/14/2024 | Approved | MICHEL ABAJAN |
| Verify Sprinkler Sign Off | 8/14/2024 | Approved | MICHEL ABAJAN |
| Insulation | 8/22/2024 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 8/22/2024 | Approved | MATTHEW NELSON |
| Drywall Nailing | 8/27/2024 | Corrections Issued | GAREN HAYRAPETYAN |
| Drywall Nailing | 8/29/2024 | Approved | GAREN HAYRAPETYAN |
| ELECTRICAL-Final | 11/4/2024 | Not Ready for Inspection | MICHEL ABAJAN |
| Final | 11/4/2024 | Not Ready for Inspection | MICHEL ABAJAN |
| Green Building Final | 11/4/2024 | Not Ready for Inspection | MICHEL ABAJAN |
| HVAC-Final | 11/4/2024 | Not Ready for Inspection | MICHEL ABAJAN |
| PLUMBING-Final | 11/4/2024 | Not Ready for Inspection | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 11/4/2024 | SGSOV Not Required | MICHEL ABAJAN |
| Smoke Detectors | 11/4/2024 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 1/17/2025 | Approved | MICHEL ABAJAN |
| Final | 1/17/2025 | OK to Issue CofO | MICHEL ABAJAN |
| Green Building Final | 1/17/2025 | Approved | MICHEL ABAJAN |
| HVAC-Final | 1/17/2025 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 1/17/2025 | Approved | MICHEL ABAJAN |