13887 N WALLABI AVE 91342

Certificate Information: 13887 N WALLABI AVE 91342

Application / Permit
23010-20000-01926
Plan Check / Job No.
B23VN05943
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
(N) 20' X 19'8" DETACHED GARAGE, ALL WORK PER ENGINEERING
Permit Issued
Issued on 1/26/2024
Issuing Office
West Los Angeles
Current Status
Issued on 1/26/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/8/2023 APPLICANT
Assigned to Plan Check Engineer 5/11/2023 RARES BODEA
Corrections Issued 5/15/2023 RARES BODEA
Quality Review Completed 5/17/2023 STEVEN KIM
Building Plans Picked Up 5/18/2023 APPLICANT
Applicant returned to address corrections 8/30/2023 RARES BODEA
Applicant returned to address corrections 12/19/2023 RARES BODEA
Applicant returned to address corrections 1/5/2024 RARES BODEA
Plan Check Approved 1/11/2024 RARES BODEA
Issued 1/26/2024 APPLICANT

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 6/7/2023 TAL SHEMEN
BHO/Hillside ordinance Cleared 6/7/2023 TAL SHEMEN
BHO/Hillside ordinance Cleared 6/7/2023 TAL SHEMEN
BHO/Hillside ordinance Cleared 6/7/2023 TAL SHEMEN
BHO/Hillside ordinance Cleared 6/7/2023 TAL SHEMEN
Eng Process Fee Ord 176,300 Cleared 6/8/2023 TAL SHEMEN
Low Impact Development Cleared 7/5/2023 MARCO SANCHEZ
Roof/Waste drainage to street Cleared 7/5/2023 TAL SHEMEN
Distance to fire station Cleared 8/11/2023 GILBERT URREA
Hydrant and Access approval Cleared 8/11/2023 GILBERT URREA
GPI Written Notices Cleared 1/11/2024 RARES BODEA
Grading Pre-Inspection Cleared 1/11/2024 RARES BODEA

Contact Information

Contractor Owner-Builder       ,
Engineer Kator,, Khaled; Lic. No.: C69781 19519 TULSA ST      NORTHRIDGE, CA 91326

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/1/2024 Corrections Issued MICHEL ABAJAN
Excavation/Setback/Form/Re-Bar 5/9/2025 Partial Approval KEVIN BERBERYAN
Pre-Inspection 5/9/2025 Partial Inspection KEVIN BERBERYAN
Footing/Foundation/Slab 5/19/2025 Approved KEVIN BERBERYAN
Excavation/Setback/Form/Re-Bar 5/28/2025 Partial Inspection KEVIN BERBERYAN
Wood Frame 6/11/2025 Partial Inspection KEVIN BERBERYAN
Interior/Exterior Lathing 7/8/2025 Approved KEVIN BERBERYAN
Drywall Nailing 12/24/2025 Not Ready for Inspection KEVIN BERBERYAN
Final 12/24/2025 Not Ready for Inspection KEVIN BERBERYAN
Green Building Final 12/24/2025 Not Ready for Inspection KEVIN BERBERYAN
Green Building Rough 12/24/2025 Approved KEVIN BERBERYAN
Interior/Exterior Lathing 12/24/2025 Partial Inspection KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 12/24/2025 SGSOV Not Ready KEVIN BERBERYAN
Smoke Detectors 12/24/2025 Not Ready for Inspection KEVIN BERBERYAN
Wood Frame 12/24/2025 Approved KEVIN BERBERYAN
Insulation 1/15/2026 Approved KEVIN BERBERYAN
Drywall Nailing 2/5/2026 Approved JACK KARGODORIAN
Interior/Exterior Lathing 2/20/2026 Approved KEVIN BERBERYAN