17832 W TRIBUNE ST 91344
Certificate Information: 17832 W TRIBUNE ST 91344
- Application / Permit
- 23010-20000-01914
- Plan Check / Job No.
- B23VN05433
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan: NEW 800 S.F. ACCESSORY DWELLING UNIT AT THE REAR. ADU PER STATE LAW FIRE SPRINKLERED NFPA 13D THROUGH OUT
- Permit Issued
- Issued on 4/11/2024
- Issuing Office
- Current Status
- CofO Issued on 7/14/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/28/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/4/2023 | JAD BASMA |
| Corrections Issued | 5/6/2023 | JAD BASMA |
| Quality Review Completed | 5/15/2023 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 1/31/2024 | JAD BASMA |
| Applicant returned to address corrections | 3/8/2024 | JAD BASMA |
| Plan Check Approved | 3/28/2024 | JAD BASMA |
| Issued | 4/11/2024 | APPLICANT |
| CofO in Progress | 5/13/2025 | STEVEN BACK |
| CofO in Progress | 5/16/2025 | STEVEN BACK |
| CofO in Progress | 7/9/2025 | HENRY KIM |
| Permit Finaled | 7/14/2025 | JOHN JANSON |
| CofO Issued | 7/14/2025 | JOHN JANSON |
| Permit Finaled | 7/14/2025 | JOHN JANSON |
Permit Application Clearance Information
| ZI | Cleared | 8/3/2023 | MAYELA VILLA |
| Address approval | Cleared | 8/7/2023 | TAL SHEMEN |
| Eng Process Fee Ord 176,300 | Cleared | 8/9/2023 | TAL SHEMEN |
| Sewer availability | Cleared | 8/9/2023 | TAL SHEMEN |
| Low Impact Development (LID) | Cleared | 11/3/2023 | SAMUEL LINN |
| Roof/Waste drainage to street | Cleared | 11/16/2023 | NIKKI ZULUETA |
| Construction near power lines | Cleared | 11/21/2023 | RIDWAN HARDY |
| Hydrant and Access approval | Cleared | 1/25/2024 | MATTHEW CRAIG |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY PARD, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
| STEVEN BACK, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/29/2024 | Partial Approval | STEVEN BACK |
| Excavation/Setback/Form/Re-Bar | 5/7/2024 | Corrections Issued | STEVEN BACK |
| Footing/Foundation/Slab | 5/7/2024 | Corrections Issued | STEVEN BACK |
| Footing/Foundation/Slab | 5/10/2024 | Corrections Issued | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 6/11/2024 | Partial Approval | STEVEN BACK |
| Footing/Foundation/Slab | 6/11/2024 | Approved | STEVEN BACK |
| ELECTRICAL-Rough | 7/10/2024 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 7/10/2024 | Approved | STEVEN BACK |
| HVAC-Rough | 7/10/2024 | Corrections Issued | STEVEN BACK |
| PLUMBING-Rough | 7/10/2024 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 7/24/2024 | Corrections Issued | STEVEN BACK |
| HVAC-Rough | 7/24/2024 | Approved | STEVEN BACK |
| Verify Sprinkler Sign Off | 7/24/2024 | Approved | STEVEN BACK |
| Green Building Rough | 7/29/2024 | Approved | KRISTEN CAUSEY |
| Interior/Exterior Lathing | 7/29/2024 | Partial Approval | KRISTEN CAUSEY |
| BUILDING-Rough-Frame | 8/19/2024 | Corrections Issued | STEVEN BACK |
| Insulation | 8/19/2024 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 8/19/2024 | Approved | STEVEN BACK |
| Pre-Inspection | 8/19/2024 | Partial Inspection | STEVEN BACK |
| Shower Pan | 8/19/2024 | Approved | STEVEN BACK |
| Underground Mechanical | 9/24/2024 | Not Ready for Inspection | JEFFREY PARD |
| BUILDING-Rough-Frame | 2/6/2025 | Corrections Issued | STEVEN BACK |
| ELECTRICAL-Final | 2/6/2025 | Approved | STEVEN BACK |
| Final | 2/6/2025 | Corrections Issued | STEVEN BACK |
| HVAC-Final | 2/6/2025 | Approved | STEVEN BACK |
| PLUMBING-Final | 2/6/2025 | Approved | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 2/6/2025 | SGSOV Approved | STEVEN BACK |
| Service/Power Release | 2/6/2025 | Not Ready for Inspection | STEVEN BACK |
| Smoke Detectors | 2/6/2025 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 4/10/2025 | Corrections Issued | STEVEN BACK |
| Final | 4/10/2025 | Corrections Issued | STEVEN BACK |
| Green Building Final | 4/10/2025 | Not Ready for Inspection | STEVEN BACK |
| BUILDING-Rough-Frame | 4/24/2025 | Approved | STEVEN BACK |
| Final | 4/24/2025 | Corrections Issued | STEVEN BACK |
| Green Building Final | 4/24/2025 | Approved | STEVEN BACK |
| Pre-Inspection | 4/28/2025 | Partial Inspection | STEVEN BACK |
| Final | 5/13/2025 | Corrections Issued | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 5/13/2025 | SGSOV Not Required | STEVEN BACK |
| Final | 5/16/2025 | Corrections Issued | STEVEN BACK |
| Service/Power Release | 5/21/2025 | Approved | STEVEN BACK |
| Final | 7/9/2025 | OK to Issue CofO | HENRY KIM |