5461 N BOTHWELL ROAD 91356

Certificate Information: 5461 N BOTHWELL ROAD 91356

Application / Permit
23010-20000-01910
Plan Check / Job No.
B23VN05857
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
NEW DETACHED 1-STORY (12'-4"x19'-6"), 198 SQFT RECREATION ROOM W/EXTERIOR ACCESS FULL BATH.
Permit Issued
Issued on 1/12/2024
Issuing Office
Valley
Current Status
CofO Issued on 3/25/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/5/2023 APPLICANT
Assigned to Plan Check Engineer 5/18/2023 PETER MOSESIAN
Corrections Issued 5/24/2023 PETER MOSESIAN
Quality Review Completed 5/26/2023 OMID HEDAYAT
Building Plans Picked Up 5/30/2023 APPLICANT
Plan Check Approved 11/21/2023 PETER MOSESIAN
Issued 1/12/2024 APPLICANT
CofO in Progress 2/18/2025 JOHN KIDWELL
Permit Finaled 3/25/2025 JOHN JANSON
CofO Issued 3/25/2025 JOHN JANSON
Permit Finaled 3/25/2025 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/13/2023 DAGOVERTO GUERRERO
Hydrant and Access approval Cleared 7/15/2023 KURT CORRAL
Low Impact Development (LID) Cleared 11/7/2023 SAMUEL LINN
Roof/Waste drainage to street Cleared 11/7/2023 BRYAN GODINEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/19/2024 Partial Approval SEAN HAUPT
Underground Mechanical 1/19/2024 Approved SEAN HAUPT
Footing/Foundation/Slab 1/25/2024 Approved SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 2/2/2024 Approved SEAN HAUPT
Green Building Rough 2/2/2024 Not Ready for Inspection SEAN HAUPT
Verify Sprinkler Sign Off 2/2/2024 Not Ready for Inspection SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 2/12/2024 Approved JOHN KIDWELL
ELECTRICAL-Rough 3/26/2024 Not Ready for Inspection JOHN KIDWELL
HVAC-Rough 3/26/2024 Not Ready for Inspection JOHN KIDWELL
PLUMBING-Rough 3/26/2024 Not Ready for Inspection JOHN KIDWELL
ELECTRICAL-Rough 4/1/2024 Approved JEFFREY HARTLINE
HVAC-Rough 4/1/2024 Approved JEFFREY HARTLINE
PLUMBING-Rough 4/1/2024 Approved JEFFREY HARTLINE
BUILDING-Rough-Frame 4/10/2024 Partial Approval JOHN KIDWELL
Green Building Rough 4/10/2024 Approved JOHN KIDWELL
Verify Sprinkler Sign Off 4/10/2024 Approved JOHN KIDWELL
Insulation 4/18/2024 Not Ready for Inspection JOHN KIDWELL
Interior/Exterior Lathing 4/26/2024 Partial Approval JOHN KIDWELL
BUILDING-Rough-Frame 5/31/2024 Approved JOHN KIDWELL
Drywall Nailing 5/31/2024 Approved JOHN KIDWELL
Green Building Rough 5/31/2024 Approved JOHN KIDWELL
Insulation 5/31/2024 Approved JOHN KIDWELL
Interior/Exterior Lathing 5/31/2024 Partial Approval JOHN KIDWELL
Underground Mechanical 7/2/2024 Partial Approval JOHN KIDWELL
Final 10/11/2024 Not Ready for Inspection JOHN KIDWELL
Green Building Final 10/11/2024 Not Ready for Inspection JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 10/11/2024 SGSOV Not Ready JOHN KIDWELL
Service/Power Release 10/11/2024 Not Ready for Inspection JOHN KIDWELL
Smoke Detectors 10/11/2024 Not Ready for Inspection JOHN KIDWELL
Final 10/29/2024 Not Ready for Inspection JOHN KIDWELL
Green Building Final 10/29/2024 Not Ready for Inspection JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 10/29/2024 SGSOV Approved JOHN KIDWELL
Service/Power Release 10/29/2024 Not Ready for Inspection JOHN KIDWELL
Smoke Detectors 10/29/2024 Approved JOHN KIDWELL
Final 11/26/2024 Corrections Issued JOHN COLEMAN
Green Building Final 11/26/2024 Approved JOHN COLEMAN
Service/Power Release 11/26/2024 Not Ready for Inspection JOHN COLEMAN
Final 12/18/2024 Not Ready for Inspection JOHN KIDWELL
Service/Power Release 12/18/2024 Approved JOHN KIDWELL
Final 2/14/2025 OK to Issue CofO JOHN KIDWELL