15026 1/2 W VOSE ST 91405
Certificate Information: 15026 1/2 W VOSE ST 91405
- Application / Permit
- 23010-20000-01900
- Plan Check / Job No.
- B23VN05836
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN. NEW 1-STORY DETACHED SINGLE FAMILY DWELLING PER SB9. FIRE SPRINKLERS PER NFPA 13R REQD
- Permit Issued
- Issued on 6/13/2024
- Issuing Office
- Current Status
- CofO Issued on 4/10/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/4/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/18/2023 | PRANITA SHAH |
| Corrections Issued | 5/30/2023 | PRANITA SHAH |
| Quality Review Completed | 6/9/2023 | GARO TELMI |
| Applicant returned to address corrections | 5/3/2024 | PRANITA SHAH |
| Plan Check Approved | 6/4/2024 | PRANITA SHAH |
| Issued | 6/13/2024 | APPLICANT |
| CofO in Progress | 3/24/2025 | RYAN SALAZAR |
| Permit Finaled | 4/10/2025 | RUBEN SALAS |
| CofO Issued | 4/10/2025 | RUBEN SALAS |
| Permit Finaled | 4/10/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 6/21/2023 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 7/10/2023 | LEE GUILBEAUX |
| Sewer availability | Cleared | 7/10/2023 | LEE GUILBEAUX |
| Low Impact Development (LID) | Cleared | 11/9/2023 | MELINEH AGHAKHABIAN |
| Senate Bill 9 | Cleared | 11/14/2023 | ALEX VELA |
| Hydrant and Access approval | Cleared | 1/17/2024 | KURT CORRAL |
| Roof/Waste drainage to street | Cleared | 2/5/2024 | BRYAN GODINEZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/10/2024 | Partial Approval | MICHEL ABAJAN |
| Footing/Foundation/Slab | 7/11/2024 | Partial Approval | RYAN SALAZAR |
| Footing/Foundation/Slab | 7/16/2024 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 8/28/2024 | Corrections Issued | RYAN SALAZAR |
| ELECTRICAL-Rough | 8/28/2024 | Approved | RYAN SALAZAR |
| HVAC-Rough | 8/28/2024 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 8/28/2024 | Partial Approval | RYAN SALAZAR |
| Interior/Exterior Lathing | 9/18/2024 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Rough | 9/23/2024 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 9/25/2024 | Approved | VINCENT HANLEY |
| Green Building Rough | 9/25/2024 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 9/25/2024 | Partial Approval | VINCENT HANLEY |
| Verify Sprinkler Sign Off | 9/25/2024 | Approved | VINCENT HANLEY |
| Insulation | 9/30/2024 | Corrections Issued | RYAN SALAZAR |
| Drywall Nailing | 10/4/2024 | Approved | MICHAEL CORTEZ |
| ELECTRICAL-Rough | 11/5/2024 | Approved | RYAN SALAZAR |
| Sewer | 11/5/2024 | Approved | RYAN SALAZAR |
| Underground Mechanical | 11/5/2024 | Approved | RYAN SALAZAR |
| Underground Mechanical | 11/8/2024 | Approved | RYAN SALAZAR |
| Service/Power Release | 12/6/2024 | Not Ready for Inspection | RYAN SALAZAR |
| ELECTRICAL-Final | 1/13/2025 | Not Ready for Inspection | RYAN SALAZAR |
| HVAC-Final | 1/13/2025 | Not Ready for Inspection | RYAN SALAZAR |
| PLUMBING-Final | 1/13/2025 | Approved | RYAN SALAZAR |
| ELECTRICAL-Final | 2/3/2025 | Approved | RYAN SALAZAR |
| Final | 2/3/2025 | Partial Inspection | RYAN SALAZAR |
| Green Building Final | 2/3/2025 | Approved | RYAN SALAZAR |
| HVAC-Final | 2/3/2025 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 2/3/2025 | SGSOV Not Required | RYAN SALAZAR |
| Service/Power Release | 2/3/2025 | Not Ready for Inspection | RYAN SALAZAR |
| Smoke Detectors | 2/3/2025 | Approved | RYAN SALAZAR |
| Service/Power Release | 2/14/2025 | Approved | RYAN SALAZAR |
| Final | 3/21/2025 | OK to Issue CofO | RYAN SALAZAR |