18622 W FRANKFORT ST 91324

Certificate Information: 18622 W FRANKFORT ST 91324

Application / Permit
23010-20000-01898
Plan Check / Job No.
B23VN05831
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan NEW DETACHED ADU PER ORDINANCE. 1 OF 2
Permit Issued
Issued on 5/26/2023
Issuing Office
Current Status
Issued on 5/26/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/4/2023 APPLICANT
Assigned to Plan Check Engineer 5/9/2023 JOSEPH RAFOLS
Corrections Issued 5/10/2023 JOSEPH RAFOLS
Plan Check Approved 5/25/2023 FARSHAD ALIMOHAMADI
Issued 5/26/2023 APPLICANT

Permit Application Clearance Information

Address approval Cleared 5/12/2023 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 5/12/2023 LEE GUILBEAUX
Sewer availability Cleared 5/24/2023 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 5/25/2023 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,
Engineer Boules,, George H; Lic. No.: C64144 29082 MADRID PL      CASTAIC, CA 91384

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 7/5/2023 Approved JOHN KIDWELL
BUILDING-Rough-Frame 8/8/2023 Corrections Issued DAVID SCANTLIN
ELECTRICAL-Rough 8/8/2023 Not Ready for Inspection DAVID SCANTLIN
Gas Test 8/8/2023 Not Ready for Inspection DAVID SCANTLIN
HVAC-Rough 8/8/2023 Not Ready for Inspection DAVID SCANTLIN
Light Gage Steel Frame 8/8/2023 Not Ready for Inspection DAVID SCANTLIN
PLUMBING-Rough 8/8/2023 Not Ready for Inspection DAVID SCANTLIN
Interior/Exterior Lathing 10/10/2023 Partial Approval JOHN KIDWELL
BUILDING-Rough-Frame 10/17/2023 Approved JOHN KIDWELL
Drywall Nailing 10/17/2023 Approved JOHN KIDWELL
Green Building Rough 10/17/2023 Approved JOHN KIDWELL
Rough-Elec/Plmb/HVAC 10/17/2023 Approved JOHN KIDWELL
Verify Sprinkler Sign Off 10/17/2023 Approved JOHN KIDWELL
Final 11/22/2023 Corrections Issued DAVID SCANTLIN
Footing/Foundation/Slab 11/22/2023 Approved DAVID SCANTLIN
Green Building Final 11/22/2023 Approved DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 11/22/2023 SGSOV Approved DAVID SCANTLIN
Service/Power Release 11/22/2023 Not Ready for Inspection DAVID SCANTLIN
Smoke Detectors 11/22/2023 Approved DAVID SCANTLIN
Final 12/1/2023 Not Ready for Inspection DAVID SCANTLIN
Service/Power Release 12/1/2023 Approved DAVID SCANTLIN