11012 N DE FOE AVE 91331
Certificate Information: 11012 N DE FOE AVE 91331
- Application / Permit
- 23010-20000-01873
- Plan Check / Job No.
- B23VN05752
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 40'-0" X 30'-0" DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). ALL WORK DONE PER WFPP.
- Permit Issued
- Issued on 8/9/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/20/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/3/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/8/2023 | ARTIN ZARUKIAN |
| Corrections Issued | 5/8/2023 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 5/10/2023 | APPLICANT |
| Applicant returned to address corrections | 7/21/2023 | ISIS ARGUETA |
| Plan Check Approved | 8/1/2023 | GIOVANNY CHAVEZ |
| No Progress | 8/1/2023 | GIOVANNY CHAVEZ |
| Plan Check Approved | 8/7/2023 | MADISON ODELL |
| Issued | 8/9/2023 | APPLICANT |
| CofO in Progress | 6/17/2025 | MICHEL ABAJAN |
| Permit Finaled | 6/20/2025 | RUBEN SALAS |
| CofO Issued | 6/20/2025 | RUBEN SALAS |
| Permit Finaled | 6/20/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 5/16/2023 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/22/2023 | MEGAN GODINEZ |
| Sewer availability | Cleared | 5/23/2023 | MEGAN GODINEZ |
| Hydrant and Access approval | Cleared | 5/26/2023 | MATTHEW CRAIG |
| Low Impact Development (LID) | Cleared | 7/11/2023 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 7/18/2023 | MEGAN GODINEZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/10/2023 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 11/20/2023 | Partial Approval | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/4/2023 | Partial Approval | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/20/2023 | Partial Approval | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 2/16/2024 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 2/16/2024 | Approved | MICHEL ABAJAN |
| Green Building Rough | 2/16/2024 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 2/16/2024 | Approved | MICHEL ABAJAN |
| Insulation | 3/6/2024 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 3/6/2024 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 3/13/2024 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 3/13/2024 | Not Ready for Inspection | WILLIAM WREN |
| Interior/Exterior Lathing | 3/22/2024 | Approved | MICHEL ABAJAN |
| Shower Pan | 3/22/2024 | Approved | MICHEL ABAJAN |
| Underground Mechanical | 9/11/2024 | Approved | RYAN SALAZAR |
| ELECTRICAL-Final | 2/7/2025 | No Access for Inspection | MICHEL ABAJAN |
| Final | 2/7/2025 | No Access for Inspection | MICHEL ABAJAN |
| Green Building Final | 2/7/2025 | No Access for Inspection | MICHEL ABAJAN |
| HVAC-Final | 2/7/2025 | No Access for Inspection | MICHEL ABAJAN |
| PLUMBING-Final | 2/7/2025 | No Access for Inspection | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 2/7/2025 | SGSOV Not Ready | MICHEL ABAJAN |
| Smoke Detectors | 2/7/2025 | No Access for Inspection | MICHEL ABAJAN |
| ELECTRICAL-Final | 5/19/2025 | Corrections Issued | MICHEL ABAJAN |
| Final | 5/19/2025 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 5/19/2025 | Approved | MICHEL ABAJAN |
| HVAC-Final | 5/19/2025 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 5/19/2025 | Corrections Issued | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 5/19/2025 | SGSOV Not Required | MICHEL ABAJAN |
| Smoke Detectors | 5/19/2025 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 6/16/2025 | Approved | MICHEL ABAJAN |
| Final | 6/16/2025 | OK to Issue CofO | MICHEL ABAJAN |
| PLUMBING-Final | 6/16/2025 | Approved | MICHEL ABAJAN |