11012 N DE FOE AVE 91331

Certificate Information: 11012 N DE FOE AVE 91331

Application / Permit
23010-20000-01873
Plan Check / Job No.
B23VN05752
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 40'-0" X 30'-0" DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). ALL WORK DONE PER WFPP.
Permit Issued
Issued on 8/9/2023
Issuing Office
Valley
Current Status
CofO Issued on 6/20/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/3/2023 APPLICANT
Assigned to Plan Check Engineer 5/8/2023 ARTIN ZARUKIAN
Corrections Issued 5/8/2023 ARTIN ZARUKIAN
Building Plans Picked Up 5/10/2023 APPLICANT
Applicant returned to address corrections 7/21/2023 ISIS ARGUETA
Plan Check Approved 8/1/2023 GIOVANNY CHAVEZ
No Progress 8/1/2023 GIOVANNY CHAVEZ
Plan Check Approved 8/7/2023 MADISON ODELL
Issued 8/9/2023 APPLICANT
CofO in Progress 6/17/2025 MICHEL ABAJAN
Permit Finaled 6/20/2025 RUBEN SALAS
CofO Issued 6/20/2025 RUBEN SALAS
Permit Finaled 6/20/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 5/16/2023 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 5/22/2023 MEGAN GODINEZ
Sewer availability Cleared 5/23/2023 MEGAN GODINEZ
Hydrant and Access approval Cleared 5/26/2023 MATTHEW CRAIG
Low Impact Development (LID) Cleared 7/11/2023 LUIS LUVANO
Roof/Waste drainage to street Cleared 7/18/2023 MEGAN GODINEZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/10/2023 Approved MICHEL ABAJAN
PLUMBING-Rough 11/20/2023 Partial Approval MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 12/4/2023 Partial Approval MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 12/20/2023 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 2/16/2024 Approved MICHEL ABAJAN
ELECTRICAL-Rough 2/16/2024 Approved MICHEL ABAJAN
Green Building Rough 2/16/2024 Approved MICHEL ABAJAN
PLUMBING-Rough 2/16/2024 Approved MICHEL ABAJAN
Insulation 3/6/2024 Approved MICHEL ABAJAN
Interior/Exterior Lathing 3/6/2024 Approved MICHEL ABAJAN
Drywall Nailing 3/13/2024 Approved WILLIAM WREN
Interior/Exterior Lathing 3/13/2024 Not Ready for Inspection WILLIAM WREN
Interior/Exterior Lathing 3/22/2024 Approved MICHEL ABAJAN
Shower Pan 3/22/2024 Approved MICHEL ABAJAN
Underground Mechanical 9/11/2024 Approved RYAN SALAZAR
ELECTRICAL-Final 2/7/2025 No Access for Inspection MICHEL ABAJAN
Final 2/7/2025 No Access for Inspection MICHEL ABAJAN
Green Building Final 2/7/2025 No Access for Inspection MICHEL ABAJAN
HVAC-Final 2/7/2025 No Access for Inspection MICHEL ABAJAN
PLUMBING-Final 2/7/2025 No Access for Inspection MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 2/7/2025 SGSOV Not Ready MICHEL ABAJAN
Smoke Detectors 2/7/2025 No Access for Inspection MICHEL ABAJAN
ELECTRICAL-Final 5/19/2025 Corrections Issued MICHEL ABAJAN
Final 5/19/2025 Corrections Issued MICHEL ABAJAN
Green Building Final 5/19/2025 Approved MICHEL ABAJAN
HVAC-Final 5/19/2025 Approved MICHEL ABAJAN
PLUMBING-Final 5/19/2025 Corrections Issued MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 5/19/2025 SGSOV Not Required MICHEL ABAJAN
Smoke Detectors 5/19/2025 Approved MICHEL ABAJAN
ELECTRICAL-Final 6/16/2025 Approved MICHEL ABAJAN
Final 6/16/2025 OK to Issue CofO MICHEL ABAJAN
PLUMBING-Final 6/16/2025 Approved MICHEL ABAJAN