12374 W SHELDON ST 91352
Certificate Information: 12374 W SHELDON ST 91352
- Application / Permit
- 23010-20000-01855
- Plan Check / Job No.
- B23VN05670
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan NEW 20'-0" X 20'-0" DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). WORK PER ENGINEERING.
- Permit Issued
- Issued on 6/30/2023
- Issuing Office
- Current Status
- CofO Issued on 4/2/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/9/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/11/2023 | ALEC MOUSAKHANIAN |
| Corrections Issued | 5/12/2023 | ALEC MOUSAKHANIAN |
| Applicant returned to address corrections | 5/26/2023 | ISIS ARGUETA |
| Applicant returned to address corrections | 6/15/2023 | ISIS ARGUETA |
| Plan Check Approved | 6/28/2023 | ISIS ARGUETA |
| Issued | 6/30/2023 | APPLICANT |
| CofO in Progress | 2/29/2024 | MATTHEW NELSON |
| Permit Finaled | 4/2/2024 | RUBEN SALAS |
| CofO Issued | 4/2/2024 | RUBEN SALAS |
| Permit Finaled | 4/2/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 5/19/2023 | ROMAN GUTIERREZ |
| Clean Up Green Up | Cleared | 5/19/2023 | RYAN LY |
| Eng Process Fee Ord 176,300 | Cleared | 5/19/2023 | ROMAN GUTIERREZ |
| Roof/Waste drainage to street | Cleared | 5/19/2023 | ROMAN GUTIERREZ |
| Sewer availability | Cleared | 5/19/2023 | ROMAN GUTIERREZ |
Contact Information
| Contractor | Schi Solutions Inc; Lic. No.: 1085283-B | , |
| Engineer | Chang,, Yeh; Lic. No.: S6868 | 168 S SIERRA MADRE BLVD 109 PASADENA, CA 91107 |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 7/31/2023 | Approved | MATTHEW NELSON |
| Underground Mechanical | 7/31/2023 | Partial Approval | MATTHEW NELSON |
| Excavation/Setback/Form/Re-Bar | 8/7/2023 | Corrections Issued | MATTHEW NELSON |
| Excavation/Setback/Form/Re-Bar | 8/8/2023 | Approved | MATTHEW NELSON |
| Footing/Foundation/Slab | 8/8/2023 | Approved | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/24/2023 | Approved | WILLIAM WREN |
| Rough-Elec/Plmb/HVAC | 9/13/2023 | Partial Approval | THOMAS FINNILA |
| Wood Frame | 9/13/2023 | Corrections Issued | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 9/18/2023 | Corrections Issued | DAVID ANDERSON |
| Rough-Elec/Plmb/HVAC | 9/18/2023 | Approved | DAVID ANDERSON |
| Deputy Wood Construction | 9/19/2023 | Conditional Approval | ROBERT GOLD |
| Floor/Roof Diaphrgm/Shear Wall | 9/21/2023 | Approved | RYAN SALAZAR |
| Insulation | 10/4/2023 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 10/4/2023 | Approved | DAVID ANDERSON |
| Drywall Nailing | 10/12/2023 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 10/12/2023 | Approved | WILLIAM WREN |
| Shower Pan | 10/12/2023 | Approved | WILLIAM WREN |
| BUILDING-Rough-Frame | 1/29/2024 | Approved | MATTHEW NELSON |
| Final | 1/29/2024 | Corrections Issued | MATTHEW NELSON |
| Green Building Final | 1/29/2024 | Approved | MATTHEW NELSON |
| Green Building Rough | 1/29/2024 | Approved | MATTHEW NELSON |
| MERV13>=Final | 1/29/2024 | Approved | MATTHEW NELSON |
| MERV13>=Rough | 1/29/2024 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 1/29/2024 | SGSOV Approved | MATTHEW NELSON |
| Service/Power Release | 1/29/2024 | Not Ready for Inspection | MATTHEW NELSON |
| Smoke Detectors | 1/29/2024 | Approved | MATTHEW NELSON |
| Verify Sprinkler Sign Off | 1/29/2024 | Approved | MATTHEW NELSON |
| Final | 2/14/2024 | Corrections Issued | MATTHEW NELSON |
| Service/Power Release | 2/14/2024 | Not Ready for Inspection | MATTHEW NELSON |
| Final | 2/28/2024 | OK to Issue CofO | MATTHEW NELSON |
| Service/Power Release | 2/28/2024 | Approved | MATTHEW NELSON |