11845-11845 1/2 W HAMLIN ST 91606

Certificate Information: 11845-11845 1/2 W HAMLIN ST 91606

Application / Permit
23010-20000-01854
Plan Check / Job No.
B23VN05667
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan: NEW 2-STORY DETACHED (2) ACCESSORY DWELLING UNITS AT REAR OF EXISTING MULTIFAMILY
Permit Issued
Issued on 2/7/2024
Issuing Office
Current Status
CofO Issued on 7/9/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/4/2023 APPLICANT
Assigned to Plan Check Engineer 5/18/2023 PRANITA SHAH
Corrections Issued 5/25/2023 PRANITA SHAH
Quality Review Completed 6/9/2023 GARO TELMI
Applicant returned to address corrections 9/15/2023 PRANITA SHAH
Plan Check Approved 10/11/2023 PRANITA SHAH
Issued 2/7/2024 APPLICANT
CofO in Progress 2/26/2026 JOSE AVILA
CofO in Progress 7/3/2026 JOSE AVILA
Permit Finaled 7/9/2026 RUBEN SALAS
CofO Issued 7/9/2026 RUBEN SALAS
Permit Finaled 7/9/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 6/9/2023 NIKKI ZULUETA
Highway dedication Cleared 6/9/2023 NIKKI ZULUETA
Eng Process Fee Ord 176,300 Cleared 6/10/2023 NIKKI ZULUETA
Sewer availability Cleared 6/13/2023 NIKKI ZULUETA
Frnt yard landscape/Water mgmt Cleared 7/11/2023 NATHAN ROMINE
Low Impact Development (LID) Cleared 7/31/2023 LUIS LUVANO
Roof/Waste drainage to street Cleared 8/2/2023 TAL SHEMEN
Hydrant and Access approval Cleared 8/16/2023 MATTHEW CRAIG
Redevelopment Project Area Cleared 8/17/2023 CARTER HOWE

Contact Information

Contractor Owner-Builder       ,
Engineer Moradian,, Helbert; Lic. No.: C76618 6854 FOOTHILL BLVD      TUJUNGA, CA 91042

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/9/2024 Corrections Issued ROBERT DAVIS
Footing/Foundation/Slab 4/23/2024 Corrections Issued JOHN KITCKO
Footing/Foundation/Slab 4/25/2024 Approved JOHN KITCKO
Verify Sprinkler Sign Off 6/12/2024 Not Ready for Inspection JOHN KITCKO
Wood Frame 6/12/2024 Partial Inspection JOHN KITCKO
Verify Sprinkler Sign Off 6/25/2024 Not Ready for Inspection JOHN KITCKO
Wood Frame 6/25/2024 Not Ready for Inspection JOHN KITCKO
Verify Sprinkler Sign Off 6/28/2024 Partial Inspection GREGORY POMISH
Wood Frame 6/28/2024 Partial Approval GREGORY POMISH
Interior/Exterior Lathing 9/24/2024 Corrections Issued JOHN KITCKO
Interior/Exterior Lathing 10/4/2024 Partial Approval JOHN KITCKO
Insulation 10/15/2024 Partial Inspection JOHN KITCKO
Special/Order Compliance 11/20/2024 Partial Inspection JUAN VALENZUELA
Verify Sprinkler Sign Off 11/20/2024 Partial Inspection JOHN KITCKO
Wood Frame 11/20/2024 Partial Inspection JOHN KITCKO
Verify Sprinkler Sign Off 12/31/2024 Approved JOSE AVILA
Wood Frame 12/31/2024 Approved JOSE AVILA
Insulation 1/8/2025 Approved JOSE AVILA
Drywall Nailing 1/14/2025 Not Ready for Inspection JOSE AVILA
Drywall Nailing 1/16/2025 Approved JOSE AVILA
Final 1/30/2026 Corrections Issued JOSE AVILA
SGSOV-Seismic Gas S/O Valve 1/30/2026 SGSOV Not Required JOSE AVILA
Smoke Detectors 1/30/2026 Approved JOSE AVILA
Final 2/24/2026 OK to Issue CofO JOSE AVILA