17009 W MAGNOLIA BLVD 91316

Certificate Information: 17009 W MAGNOLIA BLVD 91316

Application / Permit
23010-20000-01835
Plan Check / Job No.
B23VN05629
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Accessory Living Quarters
Work Description
NEW DET. 28' x 51'-7" TWO-STORY ACCESSORY LIVING QUARTERS; NFPA-13R THRU-OUT
Permit Issued
Issued on 7/14/2025
Issuing Office
Current Status
Issued on 7/14/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/2/2023 APPLICANT
Assigned to Plan Check Engineer 5/18/2023 SEAN SHAHMIRI
Corrections Issued 5/22/2023 SEAN SHAHMIRI
Quality Review Completed 5/22/2023 OMID HEDAYAT
Building Plans Picked Up 5/23/2023 APPLICANT
Plan Check Approved 7/14/2025 SEAN SHAHMIRI
Issued 7/14/2025 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/17/2025 RYAN CASTRO
Sewer availability Cleared 1/17/2025 RYAN CASTRO
Hydrant and Access approval Cleared 2/13/2025 JERRY KAO
Low Impact Development (LID) Cleared 6/10/2025 DANIEL LEON-MENDOZA
Roof/Waste drainage to street Cleared 7/10/2025 BIAINA HARITUNIAN

Contact Information

Contractor E T Development Inc; Lic. No.: 994749-B 7256 BELLAIRE AVENUE      NORTH HOLLYWOOD, CA 91605
Engineer Khansa,, Eyass; Lic. No.: C91758 2252 JOSIE AVE      LONG BEACH, CA 90815

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 12/8/2025 Partial Approval MORRIS JACKSON
Footing/Foundation/Slab 12/17/2025 Not Ready for Inspection MORRIS JACKSON
Excavation/Setback/Form/Re-Bar 12/22/2025 Corrections Issued MORRIS JACKSON
Footing/Foundation/Slab 12/22/2025 Approved MORRIS JACKSON
Floor/Roof Diaphrgm/Shear Wall 2/4/2026 Corrections Issued MORRIS JACKSON
Floor/Roof Diaphrgm/Shear Wall 2/20/2026 Partial Approval MORRIS JACKSON
Deputy Wood Construction 3/16/2026 Conditional Approval ROBERT GOLD
BUILDING-Rough-Frame 3/19/2026 Corrections Issued MORRIS JACKSON
Floor/Roof Diaphrgm/Shear Wall 3/19/2026 Partial Approval MORRIS JACKSON
PLUMBING-Rough 4/17/2026 Approved JON MCHUGH
ELECTRICAL-Rough 4/28/2026 Not Ready for Inspection MORRIS JACKSON
ELECTRICAL-Rough 5/4/2026 Not Ready for Inspection MORRIS JACKSON
HVAC-Rough 5/4/2026 Approved MORRIS JACKSON
BUILDING-Rough-Frame 5/6/2026 Not Ready for Inspection MORRIS JACKSON
ELECTRICAL-Rough 5/6/2026 Approved MORRIS JACKSON
Verify Sprinkler Sign Off 5/6/2026 Corrections Issued MORRIS JACKSON
BUILDING-Rough-Frame 5/12/2026 Approved SEAN WIRCH
Green Building Rough 5/12/2026 Approved SEAN WIRCH
Interior/Exterior Lathing 5/12/2026 Partial Approval SEAN WIRCH
Verify Sprinkler Sign Off 5/12/2026 Approved SEAN WIRCH
Insulation 5/19/2026 Approved JON MCHUGH
Drywall Nailing 6/1/2026 Approved JON MCHUGH
Interior/Exterior Lathing 6/1/2026 Approved JON MCHUGH
Shower Pan 6/1/2026 Approved JON MCHUGH