4233 S WALTON AVE 90037

Certificate Information: 4233 S WALTON AVE 90037

Application / Permit
23010-20000-01829
Plan Check / Job No.
B23VN05612
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
eplan NEW 2-STORY DUPLEX & ATTACHED 3-CAR GARAGE
Permit Issued
Issued on 8/28/2023
Issuing Office
Current Status
CofO Issued on 2/28/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/2/2023 APPLICANT
Assigned to Plan Check Engineer 5/4/2023 MAHNAZ NOURHASHEMI
Corrections Issued 5/11/2023 MAHNAZ NOURHASHEMI
Quality Review Completed 5/19/2023 TEODORO DIAZ RODRIGUEZ
Plan Check Approved 8/18/2023 MAHNAZ NOURHASHEMI
Issued 8/28/2023 APPLICANT
CofO in Progress 2/28/2024 SABAS ALONSO
Permit Finaled 2/28/2024 DEROLD HAUFF
CofO Issued 2/28/2024 DEROLD HAUFF

Permit Application Clearance Information

Trees in Parkway Cleared 6/5/2023 ADALBERTO VERA
Address approval Cleared 6/10/2023 CELINA MORENO
Permit Cleared 6/10/2023 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 6/13/2023 CELINA MORENO
Sewer availability Cleared 6/13/2023 CELINA MORENO
Low Impact Development (LID) Cleared 6/21/2023 VICTOR MENDOZA
Roof/Waste drainage to street Cleared 6/23/2023 CELINA MORENO
Hydrant and Access approval Cleared 6/30/2023 RUEL COLE
SB8 RUD Cleared 7/18/2023 MARY ARCENA

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240
Engineer Madero,, Fidencio; Lic. No.: NA81695       ,

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/27/2023 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 9/27/2023 Corrections Issued SABAS ALONSO
Footing/Foundation/Slab 9/27/2023 Approved SABAS ALONSO
Underground Mechanical 10/24/2023 Partial Approval SABAS ALONSO
Wood Frame 10/24/2023 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 10/25/2023 Partial Approval SABAS ALONSO
Insulation 10/25/2023 Partial Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 11/3/2023 Partial Approval STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 11/17/2023 Corrections Issued SABAS ALONSO
HVAC-Rough 12/7/2023 Approved SABAS ALONSO
PLUMBING-Rough 12/7/2023 Approved SABAS ALONSO
BUILDING-Rough-Frame 12/8/2023 Approved SABAS ALONSO
ELECTRICAL-Rough 12/8/2023 Approved SABAS ALONSO
Green Building Rough 12/8/2023 Approved SABAS ALONSO
Verify Sprinkler Sign Off 12/8/2023 Approved SABAS ALONSO
Insulation 12/11/2023 Approved SABAS ALONSO
Drywall Nailing 12/28/2023 Approved SABAS ALONSO
Interior/Exterior Lathing 12/28/2023 Approved SABAS ALONSO
Shower Pan 12/28/2023 Approved SABAS ALONSO
ELECTRICAL-Final 2/13/2024 Conditional Approval SABAS ALONSO
ELECTRICAL-Final 2/23/2024 Approved SABAS ALONSO
Final 2/23/2024 Conditional Approval SABAS ALONSO
HVAC-Final 2/23/2024 Approved SABAS ALONSO
PLUMBING-Final 2/23/2024 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 2/23/2024 SGSOV Approved SABAS ALONSO
Service/Power Release 2/23/2024 Approved SABAS ALONSO
Smoke Detectors 2/23/2024 Approved SABAS ALONSO
Final 2/27/2024 OK to Issue CofO SABAS ALONSO
Service/Power Release 2/27/2024 Approved SABAS ALONSO