6123 N ETHEL AVE 91401
Certificate Information: 6123 N ETHEL AVE 91401
- Application / Permit
- 23010-20000-01826
- Plan Check / Job No.
- B23VN05597
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) DETACHED 2-STORY ACCESSORY DWELLING UNIT W/ ROOFTOP DECK ABOVE 1ST FLOOR PER LAMC 12.22A33(c)(d) **eplan**
- Permit Issued
- Issued on 12/11/2023
- Issuing Office
- Current Status
- CofO Issued on 1/30/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/8/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/25/2023 | NILOOFAR MEHRAIN |
| Corrections Issued | 5/30/2023 | NILOOFAR MEHRAIN |
| Quality Review Completed | 5/31/2023 | STEVEN KIM |
| Plan Check Approved | 11/13/2023 | NILOOFAR MEHRAIN |
| Issued | 12/11/2023 | APPLICANT |
| Permit Finaled | 1/30/2026 | RUBEN SALAS |
| CofO Issued | 1/30/2026 | RUBEN SALAS |
| Permit Finaled | 1/30/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 6/9/2023 | MEGAN GODINEZ |
| Hydrant and Access approval | Cleared | 7/14/2023 | KURT CORRAL |
| Eng Process Fee Ord 176,300 | Cleared | 8/14/2023 | MEGAN GODINEZ |
| Sewer availability | Cleared | 8/14/2023 | MEGAN GODINEZ |
| Low Impact Development (LID) | Cleared | 9/25/2023 | SHAHIN KHAZEY |
| Construction near power lines | Cleared | 10/11/2023 | RIDWAN HARDY |
| Construction within easement | Cleared | 10/11/2023 | RIDWAN HARDY |
| Roof/Waste drainage to street | Cleared | 10/13/2023 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/7/2025 | Approved | GAREN HAYRAPETYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/14/2025 | Partial Approval | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 4/14/2025 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/17/2025 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/21/2025 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/6/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/13/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/4/2025 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Wood Construction | 7/24/2025 | Conditional Approval | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 8/4/2025 | Approved | GAREN HAYRAPETYAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/4/2025 | Partial Approval | GAREN HAYRAPETYAN |
| HVAC-Rough | 8/4/2025 | Approved | GAREN HAYRAPETYAN |
| PLUMBING-Rough | 8/4/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| BUILDING-Rough-Frame | 8/7/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Interior/Exterior Lathing | 8/7/2025 | Partial Approval | GAREN HAYRAPETYAN |
| Verify Sprinkler Sign Off | 8/7/2025 | Approved | GAREN HAYRAPETYAN |
| Insulation | 8/15/2025 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 8/22/2025 | Approved | GAREN HAYRAPETYAN |
| Shower Pan | 8/22/2025 | Approved | GAREN HAYRAPETYAN |
| Interior/Exterior Lathing | 9/4/2025 | Approved | OGANES TARAKHCHYAN |
| Sewer | 10/6/2025 | Approved | WAYNE REGESTER |
| Underground Mechanical | 10/6/2025 | Approved | WAYNE REGESTER |
| BUILDING-Rough-Frame | 12/23/2025 | Partial Approval | WAYNE REGESTER |
| Final | 12/23/2025 | Not Ready for Inspection | WAYNE REGESTER |
| Service/Power Release | 12/23/2025 | Approved | WAYNE REGESTER |
| Smoke Detectors | 12/23/2025 | Approved | WAYNE REGESTER |
| BUILDING-Rough-Frame | 1/12/2026 | Approved | WAYNE REGESTER |
| Final | 1/12/2026 | Partial Approval | WAYNE REGESTER |