2654 S ORCHARD AVE 90007

Certificate Information: 2654 S ORCHARD AVE 90007

Application / Permit
23010-20000-01791
Plan Check / Job No.
B23VN05432
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New Detached 2-story ADU with attached storage
Permit Issued
Issued on 10/4/2023
Issuing Office
Current Status
CofO Issued on 10/28/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/1/2023 APPLICANT
Assigned to Plan Check Engineer 5/4/2023 JOE VO
Corrections Issued 5/7/2023 JOE VO
Quality Review Completed 5/9/2023 GARO TELMI
Applicant returned to address corrections 6/7/2023 JOE VO
Applicant returned to address corrections 8/21/2023 JOE VO
Plan Check Approved 10/3/2023 JOE VO
Issued 10/4/2023 APPLICANT
CofO in Progress 8/21/2024 WILLIAM SIERRA
Permit Finaled 10/28/2024 RUBEN SALAS
CofO Issued 10/28/2024 RUBEN SALAS
Permit Finaled 10/28/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 5/18/2023 TREVOR QUAN
Highway dedication Cleared 5/18/2023 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 5/20/2023 TREVOR QUAN
Sewer availability Cleared 5/20/2023 TREVOR QUAN
Hydrant and Access approval Cleared 6/14/2023 JOHN CONNEALLY
Specific Plan Cleared 6/28/2023 DANIEL MATA
Low Impact Development (LID) Cleared 8/15/2023 LUIS LUVANO
Roof/Waste drainage to street Cleared 8/15/2023 JEANIE LAM
Construction near power lines Cleared 9/22/2023 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Yiu,, Siu; Lic. No.: S5801 PO BOX 5143      EL MONTE, CA 91734

Inspector Information

WILLIAM SIERRA, (213) 202-3122 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/8/2023 Approved KATHRYN BUTTERWORTH
Footing/Foundation/Slab 11/8/2023 Approved KATHRYN BUTTERWORTH
METHANE-Barrier 11/8/2023 Approved KATHRYN BUTTERWORTH
METHANE-Subgrade 11/8/2023 Approved KATHRYN BUTTERWORTH
Excavation/Setback/Form/Re-Bar 11/21/2023 Corrections Issued KATHRYN BUTTERWORTH
Green Building Rough 11/21/2023 Not Ready for Inspection KATHRYN BUTTERWORTH
METHANE-Rough 11/21/2023 Not Ready for Inspection KATHRYN BUTTERWORTH
Verify Sprinkler Sign Off 11/21/2023 Approved KATHRYN BUTTERWORTH
Wood Frame 11/21/2023 Corrections Issued KATHRYN BUTTERWORTH
Excavation/Setback/Form/Re-Bar 11/27/2023 Approved KATHRYN BUTTERWORTH
Wood Frame 11/27/2023 Partial Approval KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 11/29/2023 Partial Approval KATHRYN BUTTERWORTH
Insulation 11/29/2023 Corrections Issued KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 12/11/2023 Corrections Issued KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 12/13/2023 Partial Approval KATHRYN BUTTERWORTH
Deputy Wood Construction 1/29/2024 Conditional Approval JOSH MEISTER
Floor/Roof Diaphrgm/Shear Wall 1/31/2024 Corrections Issued ALEJANDRO DE ARTOLA
METHANE-Rough 1/31/2024 Corrections Issued ALEJANDRO DE ARTOLA
Pre-Inspection 1/31/2024 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 2/8/2024 Corrections Issued ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 2/14/2024 Approved ARTHUR NEGRETE
METHANE-Rough 2/21/2024 Approved ARTHUR NEGRETE
Insulation 2/23/2024 Approved ARTHUR NEGRETE
Drywall Nailing 2/28/2024 Approved SCOTT FINNILA
Green Building Rough 2/28/2024 Approved SCOTT FINNILA
Special/Order Compliance 2/28/2024 Corrections Issued SCOTT FINNILA
Wood Frame 2/28/2024 Approved SCOTT FINNILA
Drywall Nailing 3/26/2024 Approved ARTHUR NEGRETE
Interior/Exterior Lathing 3/26/2024 Approved ARTHUR NEGRETE
Final 7/12/2024 Corrections Issued JOSEPH MCGARRY
Green Building Final 7/12/2024 Approved JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 7/12/2024 SGSOV Approved JOSEPH MCGARRY
Smoke Detectors 7/12/2024 Approved JOSEPH MCGARRY
Final 7/30/2024 Corrections Issued WILLIAM SIERRA
Final 8/6/2024 Partial Approval WILLIAM SIERRA
Final 8/21/2024 OK to Issue CofO WILLIAM SIERRA