19704 W BLYTHE ST 91306
Certificate Information: 19704 W BLYTHE ST 91306
- Application / Permit
- 23010-20000-01790
- Plan Check / Job No.
- B23VN05429
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 22'-2" X 34'-0" DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d) - PER ENGINEER
- Permit Issued
- Issued on 9/29/2023
- Issuing Office
- Current Status
- CofO Issued on 8/16/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/28/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/2/2023 | DANIEL ABRAMYAN |
| Corrections Issued | 5/3/2023 | DANIEL ABRAMYAN |
| Applicant returned to address corrections | 5/31/2023 | DANIEL ABRAMYAN |
| Refund in Progress | 6/29/2023 | SELENIA GARCIA |
| Refund in Progress | 7/7/2023 | SELENIA GARCIA |
| Refund Closed | 7/7/2023 | SELENIA GARCIA |
| Refund Denied | 8/10/2023 | EMILY HU |
| Applicant returned to address corrections | 8/23/2023 | DANIEL ABRAMYAN |
| Plan Check Approved | 9/11/2023 | DANIEL ABRAMYAN |
| Issued | 9/29/2023 | APPLICANT |
| CofO in Progress | 5/30/2024 | ARUTYUN MADATYAN |
| Permit Finaled | 8/16/2024 | JOHN JANSON |
| CofO Issued | 8/16/2024 | JOHN JANSON |
| Permit Finaled | 8/16/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 5/23/2023 | NIKKI ZULUETA |
| Eng Process Fee Ord 176,300 | Cleared | 5/24/2023 | NIKKI ZULUETA |
| Sewer availability | Cleared | 5/24/2023 | NIKKI ZULUETA |
| Construction near power lines | Cleared | 6/1/2023 | WALTER RAMIREZ |
| Low Impact Development (LID) | Cleared | 8/4/2023 | VICTOR MENDOZA |
| Roof/Waste drainage to street | Cleared | 8/4/2023 | JOHN LIN |
Contact Information
| Contractor | Bas Associates Construction; Lic. No.: 610162-B | , |
| Engineer | Motavvef,, Nasser; Lic. No.: C40977 | 15335 MORRISON ST 370 SHERMAN OAKS, CA 91403 |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/16/2023 | Partial Approval | ALEXANDER HANDY |
| Sewer | 10/16/2023 | Approved | ALEXANDER HANDY |
| Footing/Foundation/Slab | 10/20/2023 | Corrections Issued | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 10/24/2023 | Not Ready for Inspection | ALEXANDER HANDY |
| Excavation/Setback/Form/Re-Bar | 10/24/2023 | Approved | ALEXANDER HANDY |
| Footing/Foundation/Slab | 10/24/2023 | Approved | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 11/22/2023 | Corrections Issued | ALEXANDER HANDY |
| Green Building Rough | 11/22/2023 | Partial Inspection | ALEXANDER HANDY |
| Verify Sprinkler Sign Off | 11/22/2023 | Not Ready for Inspection | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 12/26/2023 | Corrections Issued | HORACE FULTZ |
| ELECTRICAL-Rough | 12/26/2023 | Approved | HORACE FULTZ |
| Green Building Rough | 12/26/2023 | Approved | HORACE FULTZ |
| HVAC-Rough | 12/26/2023 | Approved | HORACE FULTZ |
| PLUMBING-Rough | 12/26/2023 | Corrections Issued | HORACE FULTZ |
| Verify Sprinkler Sign Off | 12/26/2023 | Not Ready for Inspection | HORACE FULTZ |
| BUILDING-Rough-Frame | 12/28/2023 | Approved | HORACE FULTZ |
| PLUMBING-Rough | 12/28/2023 | Approved | HORACE FULTZ |
| Interior/Exterior Lathing | 1/8/2024 | Corrections Issued | HORACE FULTZ |
| Shower Pan | 1/8/2024 | Approved | HORACE FULTZ |
| Insulation | 1/11/2024 | Corrections Issued | ALEXANDER HANDY |
| Interior/Exterior Lathing | 1/11/2024 | Approved | ALEXANDER HANDY |
| Drywall Nailing | 1/22/2024 | Approved | KRISTEN CAUSEY |
| Final | 4/5/2024 | Corrections Issued | ARUTYUN MADATYAN |
| Green Building Final | 4/5/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 4/5/2024 | SGSOV Not Ready | ARUTYUN MADATYAN |
| Service/Power Release | 4/5/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Smoke Detectors | 4/5/2024 | Approved | ARUTYUN MADATYAN |
| Final | 5/14/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Green Building Final | 5/14/2024 | Approved | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 5/14/2024 | SGSOV Approved | ARUTYUN MADATYAN |
| Service/Power Release | 5/14/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Final | 5/23/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Service/Power Release | 5/23/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| ELECTRICAL-Final | 5/29/2024 | Approved | ARUTYUN MADATYAN |
| Final | 5/29/2024 | OK to Issue CofO | ARUTYUN MADATYAN |
| Special/Order Compliance | 7/30/2024 | Corrections Issued | ARUTYUN MADATYAN |
| Special/Order Compliance | 8/14/2024 | Approved | HENRY KIM |